Station. The term of the FasTracks East Corridor IGA extends through 2056, unless earlier terminated in writing by mutual consent of the parties, or by court order. The FasTracks East Corridor IGA provides that the Department will grant a lease of certain property at the Airport to RTD with an initial term of 50 years, and up to three renewal periods of 15 years each, with each renewal being subject to FAA approval. The Department hired a planning and engineering firm to manage the construction of the South Terminal Redevelopment Program, and contracted with M. Arthur Gensler and Associates to design the South Terminal Redevelopment Program. The final design of the South Terminal Redevelopment Program is underway and currently includes the following integrated project elements: 0 The construction of the DIA Rail Station with public circulation space and two RTD tracks to meet the obligations of the Department under the FasTracks East Corridor IGA regarding the construction and opening of the DIA Rail Station. The Department is planning the DIA Rail Station to provide additional capacity for future transportation modes. 0 The expansion of Airport baggage systems to allow passengers using the RTD train service to check--in bags at the DIA Rail Station. - The expansion of the AGTS to provide needed additional service capacity to the existing concourses. 0 The construction of the DIA Rail Station roof, which will also form a plaza (the "Plaza") that would provide public access between the landside terminal, the DIA Rail Station and the planned Airport Hotel discussed below. The Plaza area may also include future concessions for Airport passengers. 0 The construction of the Airport Hotel, a proposed 519-room, full-service hotel above the DIA Rail Station and plaza, which is planned to be accessible from the landside terminal, the plaza and the DIA Rail Station. The Airport Hotel is to feature an all--purpose restaurant and bar, a coffee express outlet, approximately 29,000 square feet of meeting space, a health club, a swimming pool, a fitness center, a business center and a gift shop. The Department has selected Starwood Hotels and Resorts to operate the Airport Hotel under the "Westin" brand. The various agreements relating to the Airport Hotel, between the City, for and on behalf of the Department, and Westin, were executed in April of 2011. For a further description of the agreements with Westin, see Airport Hotel" below and ANALYSIS Nonairline Revenues -- Other Tenriinal Revenues -- Airport Hotel" in the Report of the Airport Consultant, attached hereto as APPENDIX A. Completion and commencement of operations of the Airport Hotel are currently projected to occur in August 2015. 0 The realignment of certain existing on-Airport roadways that serve the landside terminal to accommodate the rail lines and the relocation of certain utilities. The Department has established a budget for the South Terminal Redevelopment Program of approximately $500 million (in 2012 dollars). The Department currently expects that, if any reduction in the currently planned size or scope of the South Terminal Redevelopment Program becomes necessary due to cost constraints, it would likely occur in non-revenue producing portions of the proposed facilities. Accordingly, material changes to the size and scope of the Airport Hotel are not currently anticipated given that it is expected to be financially self-sustaining when it opens, based in part on projections set 35