Contract No. 2801 CONTRACT MODIFICATIONS-CHANGE ORDER No. 1 SEATTLE DEPARTMENT OF TRANSPORTATION GOODS AND SERVICES CONTRACT FOR STREETCAR VEHICLES Pursuant to the Section 5.9 of the Special Provisions of the Contract, the contract is modi?ed to replace the following sections in their entirety and to add new special provisions addressing the administration of technical specifications as follows, with all other provisions of the contract to remain in effect: 5.2.2 DELIVERY SCHEDULE The Contractor shall deliver the cars and provide commissioning support to meet the Conditional Acceptance milestone (5.6.1) for the base order and ?rst option car, no later than the dates specified below: Car No. Conditional Acceptance 1 4!22f2015 2 6130l2015 3 5129l2015 4 51123015 5 6!0512015 6 613022015 7 (Option Car) SH 5201 5 5.2.3 DAMAGES Streetcars and materials procured under this Contract are needed to support opening of the First Hill Streetcar Line. SDOT will suffer signi?cant tangible and intangible damages if the opening has to be delayed. The parties acknowledge and agree that the project opening has been delayed by delays in delivery and acceptance of the streetcars. Because of the difficulty of determining the actual loss to SDOT, the parties agree that the Contractor shall pay to SDOT liquidated damages at the rates set forth below. Damages resulting from delays between October 6, 2014 and December 31, 2014 are converted to a lump sum of $111,000, which sum shall be paid by additional spare parts to be delivered by the Contractor to SDOT. SDOT shall specify the spare parts, which shall be priced as speci?ed in Schedule of the Contract price. Damages resulting from delay between January 1, 2015 and May 31, 2015 are waived in consideration of changes to liquidated damages to be assessed beginning June 1, 2015 as follows: a) June 1 to June 15: $500 per car per day b) June 16 to June 30: $750 per car per day c) July 1 to Delivery: $1,000 per car per day The parties agree that these payments are not a penalty, but are a reasonable forecast of the actual damages that SDOT would suffer. The total amount for liquidated damages shall not exceed ten percent of the Total Base Contract Price. SDOT may deduct liquidated damages from progress payments due under this Contract. 5.4.3 SHIPPING DESTINATION All cars, including the first option car, shall be shipped to SDOT's First Hill Streetcar Maintenance Facility on 3. Charles St. between 7th Ave. S. and 8th Ave. S., in Seattle, Washington. The Contractor shall be responsible for all work and all costs associated with the placing of cars in a ready-to-run condition on the rails of SDOT's Streetcar System. One of the cars, to be specified by SDOT, shall subsequently be shipped to South Lake Union Maintenance Facility at 318 Fairview Avenue in Seattle, Washington, at Contractor?s expense. 5.7.1 PAYMENT PROCEDURES SDOT shall pay to the Contractor, at the times and in the manner hereinafter provided, the amounts set forth in the Contract for the cars and other work furnished pursuant to the Contract. The Contractor agrees to accept such amounts as full and final payment for all labor, materials, supplies, equipment, overhead, profit, taxes, duties, and charges of whatever nature incurred by the Contractor in performing its obligations under the Contract. The Contractor shall submit invoices to SDOT detailing the payment milestones completed in the payment period. The Contractor may submit only one invoice per month. The invoice shall be accompanied by all documentation that supports the 2 amount of the payment being requested. SDOT reserves the right to inspect any and all items relating tO payment verification, on the Contractor?s premises. The Contractor must submit the progress report and schedule update (TS 19.1) with or before the invoice in order to receive payment. Progress payments are specified percentages for each milestone listed below and are based on the Price Items 1, 2, and 3 as shown on Form Ill, Schedule of Prices. As shown on Form Schedule A, Price Item 2 includes g? shipping, duty, and customs costs. The Contractor's invoices shall account the work events described in the progress payment schedule below. Progress payment invoices shall not exceed the following stated percentages Of the Contract price at the time of the following stated work events: CUMULATIVE PERCENTAGE PRICE PRICE ITEM1: ITEM 2: ITEM 3: SPARE PARTS, SPECIAL 6 TOOLS AND STREET SYSTEM TEST MILESTONE CARs SUPPORT EQUIPMENT A Ten percent of Price Items 1, 2 and 3 upon NTP. 10 10 10 Ten percent of Price Items 1, 2 and 3 upon approval of the project schedule. 20 20 20 Ten percent of Price Items 1, 2 and 3 upon award Of subcontracts for: carbody, truck frames, prepulsion system, friction brake system, doors, HVAC, auxiliary power system, communication system, and TWO. 30 30 30 Ten percent of Price Items 1, 2 and 3 upon approval of all truck frame fatigue tests and carbody structural tests, including any required follow-on stress analyses. 4D 40 40 Two and one half percent Of Price Item 1 upon completion Of each car shell including final paint times 8 cars 15% total). 55 40 40 Two and one half percent Of Price Item 1 upon arrival Of each car shell at the Contractor?s final assembly location times 6 cars 15% total). 70 40 4O CUMULATIVE PERCENTAGE PRICE PRICE PRICE ITEM 1: ITEM 2: ITEM 3: SPARE PARTS, SPECIAL TOOLS AND STREET SYSTEM TEST MILESTONE DESCRIPTION CARS SUPPORT EQUIPMENT (3.1 (3.1: One and one quarter percent of 56. Price Item 1 upon delivery of electrical 2 components (traction inverter, HVAC, pantograph and OESS) to carbuilder facility. G2: One and one quarter percent of Price Item 1 upon completion of installation of all roof equipment, interior electrical lockers and panels, carbody wiring, and terminations for each car times 6 cars 15% total). 85 40 40 Twenty five percent of Price Item 2 (System Support) upon approval of the following ?rst article inspections: coupler, doors, HVAC, auxiliary power system, propulsion system, OESS, and friction brakes 85 65 40 I One percent of Price Item 1 on shipment of the each car from the Contractor's final assembly location (provided cars meet "Shipment Authorization" defined in Section times 6 cars 6% total). 91 65 40 Twenty-five percent of Price item 2 upon delivery of approved training, operating and maintenance manuals. 91 90 40 Fifty percent of Price Item 3 (Spare Parts, Special Tools, and Test Equipment) upon delivery of fifty percent of the total value of spare parts, Special tools, and test equipment 91 90 90 One half percent of Price Item 1 upon substantial completion of each streetcar per OF times 5 cars total). 94 90 90 One half percent of Price Item 1 upon conditional acceptance of each streetcar by SDOT per CP 5.6.1 times 6 cars 3% total). 97 90 90 CUMULATIVE PERCENTAGE PRICE PRICE PRICE ITEM 1: ITEM 2: ITEM 3: SPARE PARTS, SPECIAL 6 TOOLS AND STREET SYSTEM TEST MILESTONE DESCRIPTION CARS SUPPORT EQUIPMENT One half percent of Price Item 1 upon final acceptance of each streetcar by SDOT per CP 5.6.2 (0.5 times 6 cars 3% total). 100 90 90 Ten percent of Price Item 3 upon delivery Of all Spare parts. special tools, and test equipment. 100 90 100 0 Ten percent of Price Item 2 at Contract 100 100 100 Within thirty (30) days after receipt of an invoice by SDOT, SDOT shall either Pay 100% of the invoice, or Pay the amount SDOT determines is properly due. and inform the Contractor in writing of the reason for withholding any amounts not paid, or Notify the Contractor in writing that SDOT elects to defer payment as specified in Section CP 5.7.2 SDOT may withhold all or part of a payment to protect SDOT from loss because of: Defective work not remedied; Third-party claims filed, or evidence reasonably indicating that a third-party Claim will be filed; Failure of the Contractor to make payments properly to subcontractors or suppliers, or for labor, materials, or equipment; Damage to The Contractor's failure to carry out the work in accordance with the Contract; or The Contractor's failure to comply with any provision or requirement of the Contract. SDOT may withhold accrued liquidated damages from payments due to the Contractor. No approval for payment. nor any payment by SDOT, shall constitute an acceptance of any cars or other Contract deliverables that are not in accordance with the Contract. 5.8.2 OPTION FOR ADDITIONAL CARS At the option of SDOT, the Contractor shall provide additional cars at the applicable Option Unit Price per additional streetcar as defined in this Section and listed on the Form Schedule of Prices-Price Summary. SDOT shall order additional cars by written notice to the Contractor. The notice shall specify the quantity of additional cars being ordered. SDOT may place one or more orders for additional cars, or none, but in no event shall SDOT order more than a total of twenty-five (25) additional option streetcar vehicles. An option to order additional cars may be exercised at any time of SDOT's choosing up to seventy-two (72) months after NTP. Delivery of additional cars shall be in accordance with the following: The first additional car shall be delivered not more than eighteen (18) months after exercising of the option, but not before delivery of the last car of the base order or previous option order. All following cars procured under this provision shall be delivered at a rate of one (1) car per month. 5.8.2.2 PAYMENT FOR OPTION CARS Payment for options shall be made in accordance with the progress payment schedule below: CUMULATIVE MILESTONE DESCRIPTION PERCENTAGE A Ten percent of the total option price immediately following 10 execution of the option. Twenty?five percent of the unit price for each option streetcar 35 upon completion of the car shell. Twenty percent of the unit price for each option streetcar upon 55 installation and completion of wiring of the car body mounted components of the following major sub-systems: Propulsion System, Friction Brake System. Auxiliary Electrical Equipment, HVAC, and Doors. Thirty percent of the unit price for each Option streetcar on 35 shipment of each streetcar from the Contractor's plant, (provided cars meet "Shipment Authorization" de?ned in Section 5.4.1 Ten percent 10%) of the unit price for each streetcar upon conditional 95 acceptance of the car by SDOT. CUMULATIVE MILESTONE DESCRIPTION PERCENTAGE Five percent of the unit price for each streetcar upon final 100 acceptance of the car by SDOT. ADMINISTRATION OF TECHNICAL SPECIFICATIONS: SUBMITTAL AND TESTING REQUIREMENTS - SDOT will expedite review and approval of CDRL submittal requirements. At SDOT's discretion, that are not related to vehicle safety and ongoing maintenance may be waived by our Project Engineer. - At SDOT's discretion, the scope of some non?safety testing requirements may be modified by our Project Engineer to accelerate testing. CONTRACTOR CITY OF By: f. . By: (Signature) . (Signature) Name: Josef Husek Meme: Scott Kubly Title: President, lnekon Group Title: Director. of Transportation Date: Date: