ID Task Mode 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Project: RFP Gantt Chart Date: Mon 12/26/11 Task Name Duration Start June Finish July 6/26 All tasks 83 days? Posting RFP 1 day? Floating RFP 31 days? Final date to submit questions 1 day? Submit answers to questions by 1 day ARC Submitting RFP 1 day Selection consultant 24 days? Sign contract consultant 27 days? 0 days Implementation period estimation 164 days for one house Set - up 11 days? Design phase 22 days? Structural drawings 11 days Approval 15 days? 0 days STEP 1 Foundation 21 days? STEP 2 Walls and columns 21 days? STEP 3 beams 8 days? STEP 4 roof structure 11 days STEP 5 roof 4 days STEP 6 doors and windows 11 days STEP 7 plaster 14 days STEP 8 paint 14 days Hand over 1 day? Fri 1/6/12 Fri 1/6/12 Mon 1/9/12 Fri 1/20/12 Tue 1/31/12 Tue 5/1/12 Fri 1/6/12 Mon 2/20/12 Fri 1/20/12 Tue 1/31/12 Mon 2/20/12 Tue 2/21/12 Mon 3/26/12 Tue 5/1/12 Fri 6/1/12 Mon 2/20/12 Fri 3/23/12 Tue 5/1/12 Tue 5/1/12 Wed 1/16/13 7/3 7/10 7/17 7/24 Fri 6/1/12 Fri 6/15/12 Mon 6/18/12 Tue 7/17/12 Wed 7/18/12 Wed 8/1/12 Thu 8/2/12 Wed 8/22/12 Thu 8/23/12 Thu 8/23/12 Thu 8/23/12 Thu 9/20/12 Fri 9/21/12 Fri 10/19/12 Mon 10/22/12Wed 10/31/12 Thu 11/1/12 Thu 11/15/12 Fri 11/16/12 Wed 11/21/12 Thu 11/22/12 Thu 12/6/12 Fri 12/7/12 Wed 12/26/12 Thu 12/27/12 Tue 1/15/13 Wed 1/16/13 Wed 1/16/13 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Milestone Inactive Milestone Start-only Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 1 August 7/31 8/7 8/14 ID Task Mode 25 Project: RFP Gantt Chart Date: Mon 12/26/11 Task Name Duration Start June Finish July 6/26 0 days 7/3 7/10 7/17 7/24 Wed 1/16/13 Wed 1/16/13 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Milestone Inactive Milestone Start-only Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 2 August 7/31 8/7 8/14 8/14 8/21 September 8/28 9/4 Project: RFP Gantt Chart Date: Mon 12/26/11 9/11 9/18 9/25 October 10/2 10/9 10/16 10/23 November 10/30 11/6 11/13 11/20 December 11/27 12/4 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Milestone Inactive Milestone Start-only Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 3 12/11 12/18 12/25 8/14 8/21 September 8/28 9/4 Project: RFP Gantt Chart Date: Mon 12/26/11 9/11 9/18 9/25 October 10/2 10/9 10/16 10/23 November 10/30 11/6 11/13 11/20 December 11/27 12/4 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Milestone Inactive Milestone Start-only Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 4 12/11 12/18 12/25 12/25 January 1/1 1/8 1/15 1/22 February 1/29 2/5 2/12 2/19 March 2/26 3/4 3/11 3/18 3/25 April 4/1 4/8 4/15 4/22 May 4/29 5/1 Project: RFP Gantt Chart Date: Mon 12/26/11 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Milestone Inactive Milestone Start-only Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 5 5/6 12/25 January 1/1 1/8 Project: RFP Gantt Chart Date: Mon 12/26/11 1/15 1/22 February 1/29 2/5 2/12 2/19 March 2/26 3/4 3/11 3/18 3/25 April 4/1 4/8 4/15 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Milestone Inactive Milestone Start-only Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 6 4/22 May 4/29 5/6 May June 5/6 5/13 5/20 5/27 6/3 6/10 6/17 6/24 July 7/1 7/8 7/15 7/22 August 7/29 8/5 8/12 8/19 8/26 5/1 8/23 Project: RFP Gantt Chart Date: Mon 12/26/11 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Milestone Inactive Milestone Start-only Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 7 September 9/2 9/9 9/16 May June 5/6 5/13 5/20 Project: RFP Gantt Chart Date: Mon 12/26/11 5/27 6/3 6/10 6/17 6/24 July 7/1 7/8 7/15 7/22 August 7/29 8/5 8/12 8/19 8/26 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Milestone Inactive Milestone Start-only Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 8 September 9/2 9/9 9/16 9/16 9/23 October 9/30 10/7 Project: RFP Gantt Chart Date: Mon 12/26/11 10/14 10/21 November 10/28 11/4 11/11 11/18 11/25 December 12/2 12/9 12/16 12/23 January 12/30 1/6 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Milestone Inactive Milestone Start-only Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 9 1/13 1/20 1/27 9/16 9/23 October 9/30 10/7 Project: RFP Gantt Chart Date: Mon 12/26/11 10/14 10/21 November 10/28 11/4 11/11 11/18 11/25 December 12/2 12/9 12/16 12/23 January 12/30 1/6 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Milestone Inactive Milestone Start-only Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 10 1/13 1/20 1/16 1/27