July 8, 2015 Mr. John Currier Colorado River Water Conservation District P.O. Box 1120 Glenwood Springs, CO. 81602 Mr. Gerry Knapp Aurora Water Arkansas Valley Range Project 17850 Road JJ Rocky Ford, CO 81067 Mr. Pat Wells Water Supply Department Colorado Springs Utilities 111 S. Cascade Ave. Colorado Springs, CO 80903 Mr. Bryce Romig Climax Molybdenum Company Henderson Operations P.O. Box 68 Empire, CO 80439 Mr. Todd Fessenden Eagle Park Reservoir Company 846 Forest Road Vail, CO 81657 RE: Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 Draft Dear ERMOU Partners, The Eagle River MOU (ERMOU) technical advisors are pleased to provide the following scope of services for Phase 2 of the ERMOU Project Alternatives Study. This phase will provide feasibility-level evaluations of ERMOU project alternatives identified for investigation in Phase 1 of the Study (ERMOU Project Alternatives Screening). BACKGROUND A copy of the ERMOU is presented in Attachment 1. The primary objectives of the ERMOU are: A. West Slope Water Users: Develop a Firm Dry Year Yield of 10,000 Acre Feet per Year Virtually all of the consumptive portion of this supply is required at or downstream of the Eagle River at Dowds Junction, although some West Slope water is needed upstream of this location. B. Aurora and Colorado Springs: Develop an Average Yield of 20,000 Acre Feet per Year It may be preferable to deliver East Slope water supplies to the existing Homestake Reservoir, however alternate delivery locations to the Arkansas or Platte River watersheds may also be suitable. C. Climax: Develop Additional Water Storage with a Capacity of 3,000 acre feet Reservoir storage must be in a location in proximity to the Climax Mine site, in order that existing water supplies of Climax may be stored in the facility. ERMOU Partners held a planning workshop on December 8, 2014 where ERMOU Partner goals and objectives were reviewed and potential ERMOU development alternatives were discussed. During the workshop, technical advisors to ERMOU Partners were directed to review past investigations associated with ERMOU alternatives, and to develop a cooperative work plan to update the past investigations as appropriate. ERMOU technical advisors include Wilson Water Group (WWG), RJH Consultants (RJH), Helton & Williamsen, PC (H&W), Leonard Rice Engineers (LRE), and W.W. Wheeler and Associates (WWW). 1 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 ERMOU technical advisors participated in a planning workshop on December 23, 2014 and developed a final draft work plan dated April 27, 2015. Technical advisors for the following entities participated in the workshop (Cities of Aurora and Colorado Springs, Climax Molybdenum Company, Colorado River Water Conservation District, Eagle Park Reservoir Company, Eagle River Water and Sanitation District, Upper Eagle Regional Water Authority, and Vail Associates). The final draft ERMOU work plan was subsequently distributed to the ERMOU Partners and was received with much support. The ERMOU Partners directed the ERMOU technical advisors to implement an initial screening of all proposed ERMOU project alternatives (Phase 1 Study) and identify specific ERMOU project elements for feasibility-level evaluation in a second phase of the Study, including scopes, schedules, and budgets to complete Phase 2. The ERMOU technical advisors completed Phase 1 activities through compilation of supporting information (ERMOU Library), facilitation of a screening workshop on May 27, 2015, and documentation of a summary screening report (Attachment 2). The attached Phase 1 report summarizes screening methods, rationale for continued evaluations of specific project alternatives, and two levels of recommended activities for Phase 2 of the Study: Tier 1 – Potential ERMOU Project Alternatives Requiring Feasibility-Level Study Tier 2 – Potential ERMOU Project Alternatives Requiring Preliminary-Level Review This scope of services includes an approach, budget, and schedule to complete Tier 1 and Tier 2 evaluations. APPROACH The following four work tasks are proposed for Phase 2 of the Study. Task 1 – Tier 1 Evaluations Tier 1 evaluations will be completed for three ERMOU project alternatives that have been identified in Phase 1 of the Study as requiring additional feasibility-level study (Eagle Park Reservoir, Whitney Creek Reservoir, and Bolts Lake). These three alternatives are considered key facilities with good potential to contribute to ERMOU water yield objectives and that require refined information and decision processes for feasibility-level evaluation. Tier 1 evaluations will be completed through combined efforts by WWG, H&W, and WWW (water supply); LRE (environmental); and RJH (engineering). WWG, H&W, and WWW will provide engineering services in connection with the hydrological investigations in the upper Eagle River basin for selected Tier 1 ERMOU Project Alternatives related to water supply, demands, and project yields for each project and for combinations of projects. A primary objective of the water supply evaluation is to develop sizing and capacity information for reservoirs, pipelines, and pump stations associated with the Project Alternatives. Information will be shared and work coordinated between the firms and the ERMOU Partners including review of water supply models and review of operating assumptions, model data, and model operation. It is anticipated that the water supply model(s) will be available for use by all ERMOU Partners for future water supply planning efforts; however, it is also anticipated that the model(s) will be proprietary to ERMOU partners and will not be available or distributed for general public use. LRE will conduct investigations for selected Tier 1 ERMOU Project Alternatives to determine the environmental permitting and approval requirements of federal, state and local agencies for each alternative. Federal, state, and environmental permitting and approval requirements will be similar for each of the ERMOU Project Alternatives, but the environmental issues of concern that must be addressed in the approval processes could differ substantially between different project locations. LRE will identify environmental issues that could potentially make the permitting processes more difficult and identify potential mitigation requirements and opportunities for each Project Alternative. LRE will coordinate with RJH to assure that identification of approval requirements is 2 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 based upon reasonably complete information about the configuration of storage and collection facilities, such as diversion, conveyance, pumping, and storage facilities. LRE will assist RJH with identifying possible modifications to the configuration of storage and collection facilities that could potentially mitigate environmental concerns. RJH will provide engineering investigations for the selected Tier 1 ERMOU Project Alternatives related to storage and collection options including identify diversion and conveyance needs and capacities, identify and/or update cost estimates for storage facilities including pumps and pipelines, and identify geotechnical feasibility issues, and develop construction cost estimates. 1.1 Eagle Park Reservoir 1.1.1 Water Supply H&W will complete the following activities to support Eagle Park Reservoir evaluations. 1. Update and extend stream flow record – Assemble existing daily compiled stream flow, diversion, and storage records for the upper Eagle River basin and check the records for accuracy and completeness. This will include USGS stream flow records, transmountain diversion records, Climax records, and Eagle Park and Homestake Reservoirs operation records. Quantify gravity inflows to Eagle Park Reservoir for the study period. 2. Develop West Slope Water Demands – Evaluate west slope water demands seasonally, including components of augmentation, water supply, water quality, and stream enhancement. Water demands for water quality and stream enhancement uses will be developed cooperatively with LRE. Previous studies categorized the demand for average, dry, and wet year conditions with deliveries during the winter months. 3. Develop reservoir yield – Review procedures and logic used by WWG in the reservoir operation model to estimate yields. 4. Prepare Report – Prepare a technical memorandum briefly summarizing background and key issues, and documenting development of daily gravity inflow available at Eagle Park Reservoir. WWW will complete the following activities to support Eagle Park Reservoir evaluations. 1. Enlargement Constraints – Provide engineering data concerning the maximum water surface elevation and other design constraints for enlargement of Eagle Park Reservoir. Identify potential conflicts and mitigation options related to impacts to the existing Robinson Reservoir and other Climax facilities if Eagle Park Reservoir is enlarged. 2. Hydrology – Provide existing data related to estimated inflows to Eagle Park Reservoir within its drainage basin. 3. Operations – Provide Climax’s potential water demands, conceptual input and comment to other consultants related to the operation study and yield analysis of Eagle Park Reservoir. WWG will complete the following activities to support Eagle Park Reservoir evaluations. 1. Review available reports related to reservoir expansion including, but not limited to, previous work completed by W. W. Wheeler and Associates, Helton and Williamsen, and Black and Veatch. 2. Evaluate available water supply for various collection system alternatives including (1) existing gravity water supplies, (2) gravity connector ditch to the Columbine Ditch, (3) a new or enlarged pumping station from 3 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 appropriate sites on the East Fork of the Eagle River downstream of the reservoir, and (4) a new pump station at downstream locations in the vicinity of Camp Hale. 3. Assess reservoir operation and yield for West Slope (firm yield) and East Slope (average yield) purposes. 4. Assess two reservoir alternatives (enlargements to approximately 6,000 acre-feet 9,000 acre-feet). 5. Evaluate potential yield impacts to downstream and/or upstream facilities/components. 6. Prepare a technical memorandum briefly summarizing background and key issues, discussion on assessment methodology (if applicable) and other applicable studies, conclusions on preliminary feasibility as an ERMOU project element, and recommendations on further investigations and to include project elements within a portfolio of combined project elements. Water supply opportunities associated with Eagle Park Reservoir will be evaluated with a previously developed basin-wide spreadsheet model. This model assesses water supply and reservoir operation on a daily basis for the historical period of 1947 through 2003. The model will be updated to evaluate the time period through 2014, and will be reconfigured as needed to evaluate an East Fork Eagle River pump station as an alternate source of water supply for Eagle Park Reservoir. WWG anticipates the following primary work tasks. 7. Review daily gravity inflow estimates to Eagle Park Reservoir based on actual measured historical operation of Eagle Park Reservoir. Reservoir inflow will be correlated with the measured discharge of the East Fork of the Eagle River and the Eagle River near Red Cliff, in order to extend the period of record. Daily gravity inflow will be calculated for the 1947 through 2013 period. 8. Daily divertible flow estimates will be developed for the Columbine Ditch. The estimates will be based upon historical diversions, and upon estimates of available flow to the Columbine Ditch during periods that the ditch did not historically divert water. 9. Update model to allow consideration of gravity inflow to Eagle Park Reservoir from Columbine Ditch. 10. Review estimates of native stream flow of the East Fork of the Eagle River considering USGS stream flow records, historical Columbine Ditch diversions, and historical diversion by Eagle Park Reservoir. 11. Update model to simulate and operate Columbine Ditch. 12. Update model to include pump station alternatives in the vicinity of Camp Hale 1.1.2 Environment LRE will complete the following activities to support Eagle Park Reservoir evaluations. 1. Compile and review previous studies and information – LRE is generally familiar with the location of the Project Alternative. Documents identified in the ERMOU Bibliography of Reports will be utilized and referenced to document land management/ownership, project components and configuration, and the environmental setting. In addition, LRE will review other pertinent and relevant documents, such as the White River National Forest Land and Resource Management Plan, to identify current land management guidelines and objectives. This information will be used to develop general descriptions of the existing environment and land use conditions in the areas that will be impacted by development of the Project Alternative. 4 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 2. Identify and evaluate permitting requirements – LRE will identify the land use and environmental permitting requirements associated with the Project Alternative based upon their knowledge of federal, state and local permitting requirements associated with similar projects that have been completed in the Upper Colorado River Basin. This task will include preparation of brief descriptions of each of the permitting requirements and the investigations and documentation (e.g., an Environmental Impact Statement) needed to satisfy the permitting requirements. This task will also include development of preliminary timelines for the permitting processes associated with the Project Alternative including completion of field studies, NEPA documentation, and the agency and public review processes. 3. Assess permitting issues – Environmental issues and concerns associated with the Project Alternative will be identified and evaluated to assess the potential permitting risks. In addition, this task will include an evaluation of the mitigation requirements (e.g., estimated acres of wetlands mitigation) for the Project Alternative. It is important to note that the purpose and need for the Project Alternative will most likely include an environmental component, such as instream flow enhancement, that will be important to consider in the context of mitigation. 4. Prepare report – LRE will document the results of the investigations completed in tasks 1, 2, and 3 above in a technical memorandum summarizing existing environmental conditions, permitting requirements, mitigation requirements, and potential permitting risk factors. 5. Consult and coordinate with the ERMOU study team – LRE will work closely with other members of the study team to assure the consistency of assumptions and approach to the investigations described in this SOW. This task includes meetings and other communications with the project team to coordinate our efforts and review of draft documents prepared by other consultants. In addition, this task includes consultation, review, and information sharing with H&W and WWG for the development of the hydrology needed for the Project Alternative. 1.1.3 Engineering Background – Eagle Park Reservoir is located just north of the Continental Divide between the East Fork Eagle River and Robinson Lake. The existing dam is approximately 135-feet-high and has a storage capacity of about 3,300 acre-feet. Eagle Park Reservoir is currently filled from surface water interceptor ditches along various locations of the Climax mine site. We understand that these interceptor ditches would not provide a sufficient supply to fill an expanded reservoir. If this site is used in the future by the ERMOU partners, Eagle Park Reservoir would be enlarged to provide additional water storage (potentially up to about 8,000 to 9,000 acre-feet) and would be filled by diversions from the Eagle River near Camp Hale (i.e. Resolution Creek) or the East Fork Eagle River near Cataract Creek. Diversions from East Fork Eagle River could also occur through an existing pump station that may need to be modified for increased flows. Water from Eagle Park Reservoir could be conveyed to Freemont Pass by a pipeline and pump stations for eastern slope usage. Black and Veatch developed the Camp Hale to Eagle Park Reservoir Water Delivery System Report (2009). This report presents a conceptual design and evaluation of a enlarging the reservoir to 6,500 acre-feet and a pipeline and pump system to convey flows from Camp Hale to Eagle Park Reservoir for a flow rate of either 40 cfs and 150 cfs. The level of effort for the report is generally similar to about a 30-percent design for the pipeline and pump stations and includes electrical and geotechnical evaluations. RJH will identify any possible technical issues with pump station and pipeline design concepts and update the cost opinion to 2015 dollars based on construction cost index data. 5 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 Evaluations for the dam enlargement are described minimally in the Black and Veatch report and the report does not include a description of concepts or sizes for the embankment modifications, spillway or outlet works. It would be difficult for RJH to confirm the suitability of concepts and costs for the dam enlargement presented in this report without performing independent engineering analyses. RJH will utilize information from this report where possible to assist with our evaluations. RJH has included evaluations for one dam enlargement scenario that maximizes the enlargement without impacting existing facilities at Robinson Lake in this scope of work. Engineering evaluations and cost opinions for diversion facilities from the East Fork Eagle River near Cataract Creek and from the East Fork Eagle River through the existing pump station have not been performed and are included in this scope of work. Engineering evaluations and cost opinions for conveyance facilities from the Eagle Park Reservoir for East Slope supply have not been performed and are included in this scope of work. Approach – RJH will complete the following activities. 1. Collect and review available data including available county and USGS topographic mapping data, aerial photographs, existing engineering reports and evaluations, GIS information, regional geologic maps, and any other available project documentation. 2. Review existing engineering reports and identify technical issues that could impact the cost opinions and may need to be addressed in subsequent phases of design. 3. Perform a site reconnaissance to observe the existing dam. Perform a geologic site visit to a) confirm published mapping is appropriate, b) evaluate surficial and bedrock geology and identify possible geologic hazards that could present a possible “fatal flaw” with enlarging the dam, and c) identify potential borrow areas to obtain materials for use in enlargement of the dam. 4. Develop elevation-capacity information and identify the maximum water surface elevation based on avoiding impacts to existing facilities at Robinson Lake. 5. Develop embankment geometries and concepts based on engineering judgment and experience. Develop an embankment layout and footprint to identify potential conflicts. 6. Identify required modifications to the existing seepage collection system. 7. Delineate the drainage basin and perform simplified hydrologic analyses to develop an estimate of the inflow design flood (IDF) hydrograph for spillway sizing. 8. Perform simplified reservoir routing analyses and hydraulic analyses to support selection of a spillway type and configuration, requirements for freeboard, and feasibility-level design of the spillway. 9. Perform simplified hydraulic analyses to select the size and configuration of the outlet works system to meet operational, size, and SEO release requirements. 10. Evaluate the feasibility of increasing diversions from the existing 6 cfs pump station at East Fork Eagle River and identify required modifications to the existing pump station and pipeline. Develop a schematic hydraulic profile of the conveyance. 6 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 11. Perform simplified hydraulic analyses to select the location and required sizes for the diversion structure, pump stations, and pipeline to convey flows from the East Fork Eagle River near Cataract Creek. Based on the selected facilities, develop a schematic hydraulic profile for the diversion pipeline. Facilities will be selected to provide a design similar to the concept presented in the 2009 Black and Veatch report to provide a consistent cost comparison. Significant components from the Black and Veatch report will be utilized where possible and may include pipeline alignment, pump station layout, bid schedule items, etc. 12. Identify a feasibility-level alignment for the diversion pipeline from the Eagle Park Reservoir to Freemont Pass. 13. Perform hydraulic analyses to select the location and required sizes for the diversion structure, pump stations, and pipeline to convey flows from Eagle Park Reservoir to Freemont Pass. Based on the selected facilities, develop a schematic hydraulic profile for the diversion pipeline. 14. Develop feasibility-level layouts of the components described above. Prepare conceptual-level plans and sections to illustrate Project components in an 11-inch by 17-inch format. Figures will include a plan and typical section of the dam and plans and profiles of conveyance facilities. 15. Estimate quantities of primary materials required to construct the Project components based on the feasibility-level layouts. 16. Develop unit price and lump sum costs for key work items 17. Update cost opinions to 2015 dollars for diversion facilities (i.e. pump stations and pipelines) from the Eagle River near Camp Hale as presented in the Camp Hale to Eagle Park Reservoir Water Delivery System Report by Black and Veatch (2009) based on construction cost index data. 18. Develop a feasibility-level Opinion of Probable Construction Cost. 19. Prepare and submit a draft Technical Memorandum for the site that presents a summary of the data collected, design concepts, concept drawings, and cost opinions from the feasibility-level evaluations. 20. Prepare and submit a final Technical Memorandum for the site based on comments provided by Wilson Water and the other ERMOU technical advisory members. 1.2 Whitney Creek Reservoir 1.2.1 Water Supply H&W water supply evaluations identified for Eagle Park Reservoir will support Whitney Creek Reservoir evaluations. WWG will complete the following activities to support Whitney Creek Reservoir evaluations. 1. Assess reservoir operation and yield for West Slope (firm yield) and East Slope (average yield) purposes. 2. Assess alternate reservoir capacities as identified in engineering evaluations associated with the study. 3. Evaluate potential yield impacts to downstream and/or upstream facilities/components, and provide qualitative cost impacts to downstream and upstream components to mitigate impacted yield. 7 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 4. Prepare a technical memorandum briefly summarizing background and key issues, discussion on assessment methodology (if applicable) and other applicable studies, conclusions on preliminary feasibility as an ERMOU project element, and recommendations on further investigations and to include project elements within a portfolio of combined project elements. Water availability associated with a Whitney Creek Reservoir alternative will also be evaluated with the previously developed basin-wide spreadsheet model. Whitney Creek will divert water from the Eagle River at Camp Hale, and from Homestake Creek. Water diverted or stored in the reservoir will either be pumped to Homestake Reservoir, or released to Homestake Creek for West Slope uses. WWG anticipates the following primary work tasks. 5. Develop native flow estimates for Homestake Creek through 2014. The native flow estimates will be calculated based upon the gaged flow of Homestake Creek, daily changes in storage of Homestake Reservoir, and daily deliveries through the Homestake Tunnel. 6. The model will be updated to evaluate the time period through 2014, and will be reconfigured as needed to consider the influence of the operation of Eagle Park Reservoir, and potential changes in the historical operation of the Columbine Ditch. 1.2.2 Environment LRE will complete the same level of environmental evaluations (including the same level of reporting and team coordination) identified for Eagle Park Reservoir to support Whitney Creek Reservoir evaluations. This task includes a site visit to the proposed location of the Whitney Creek Reservoir. 1.2.3 Engineering Background – The Whitney Creek Reservoir site is located along Homestake Creek about 5 miles downstream of Homestake Reservoir. If this site is used in the future by the ERMOU partners, the project would involve constructing a new dam and ancillary facilities. The reservoir would primarily be filled by diversions from the Eagle River near Camp Hale. Flows would be conveyed from the Eagle River to the reservoir through a gravity pipeline or tunnel. A pump station and pipeline will also be installed to convey flows from Whitney Creek Reservoir to Homestake Reservoir for subsequent diversion over the Continental Divide to conveyance systems operated by individual ERMOU partners. In 2014, RJH and Wilson Water performed a screening evaluation of potential Whitney Creek reservoir sites for reservoirs between 3,600 to 10,400 ac-ft. Based on this screening level evaluation, two sites were identified as feasible and geophysical surveys were performed to evaluate subsurface conditions. Based on this data, a preferred site could not be identified. The screening-level report by RJH and Wilson did not include the development of concepts and configurations for the embankment, spillway, and outlet works and did not include cost opinions. These evaluations are included in the scope of work presented herein. RJH will perform evaluations for two reservoir alternatives: one that maximizes reservoir storage without inundating the Wilderness Area and one that maximizes reservoir storage without requiring construction in the Wilderness Area. Black and Veatch developed the Draft Eagle River Drainage Basin Report (2009). This report presents a screeninglevel evaluation and cost opinions for hydraulic facilities to convey flows from the Eagle River near Camp Hale to Whitney Creek Reservoir and from Whitney Creek Reservoir to Homestake Reservoir. Evaluations are described minimally in the Black and Veatch report and the report does not provide a description of the pipeline and pump station concepts other than pipe size, and the cost estimate does not include a breakdown of primary quantities or unit costs. It would be difficult for RJH to confirm the suitability of concepts and costs presented in this report 8 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 without performing independent engineering analyses. However, we understand that the ERMOU partners would like RJH to utilize information from this report and update costs to 2015 dollars. RJH will perform high-level checks to confirm the reasonableness of basic components (i.e. pipe size, total pumping head, etc.) and update the overall cost to 2015 dollars based on construction cost index data. Approach – RJH will complete the following activities. 1. Collect and review available data including available county and USGS topographic mapping data, aerial photographs, existing engineering reports and evaluations, GIS information, regional geologic maps, and any other available project documentation. 2. Review existing engineering reports and identify technical issues that could impact the cost opinions and may need to be addressed in subsequent phases of design. 3. Update the previous elevation-capacity information and select the required dam height and normal pool elevation for each alternative. 4. Develop a graphical relationship between reservoir storage and Wilderness Area inundated area. 5. Develop embankment geometries and concepts based on engineering judgment and experience for each alternative. Develop an embankment layout and footprint to identify potential conflicts. Identify a reasonable concept for foundation treatments. 6. Perform simplified reservoir routing analyses and hydraulic analyses to support selection of a spillway type and configuration, requirements for freeboard, and feasibility-level design of the spillway for each alternative. 7. Perform simplified hydraulic analyses to select the size and configuration of the outlet works system to meet operational, size, and SEO release requirements for each alternative. 8. Develop feasibility-level layouts of the components described above. Prepare conceptual-level plans and sections to illustrate Project components in an 11-inch by 17-inch format. Figures will include a plan and typical section of the dam and plans and profiles of conveyance facilities. 9. Estimate quantities of primary materials required to construct the Project components based on the feasibility-level layouts. 10. Identify a feasibility-level alignment for the tunnel from the Eagle River to the reservoir. 11. Develop unit price and lump sum costs for key work items and cost opinions for the two dam alternatives. 12. Perform a high-level engineering review to confirm sizes and identify possible technical issues for the pipeline and pump station as presented in the Black and Veatch Report. 13. Update cost opinions to 2015 dollars for diversion facilities (i.e. pump stations and pipelines) from the from the Eagle River near Camp Hale to Whitney Creek Reservoir and from Whitney Creek Reservoir to Homestake Reservoir as presented in the Draft Eagle River Drainage Basin Report by Black and Veatch (2009) based on construction cost index data. 14. Develop a feasibility-level Opinion of Probable Construction Cost. 9 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 15. Develop a simplified cost opinion to convey flows from the Eagle River at Camp Hale to Whitney Creek Reservoir through a tunnel. The cost opinion will be based on our engineering experience and generalized tunneling cost curves. 16. Prepare and submit a draft Technical Memorandum for the site that presents a summary of the data collected, design concepts, concept drawings, and cost opinions from the feasibility-level evaluations. 17. Prepare and submit a final Technical Memorandum for the site based on comments provided by Wilson Water and the other ERMOU technical advisory members. 1.3 Bolts Lake 1.3.1 Water Supply H&W water supply evaluations identified for Eagle Park Reservoir will support Bolts Lake Reservoir evaluations. WWG will complete the following activities to support Bolts Lake evaluations. 1. Assess Eagle River diversion options. 2. Assess reservoir operation and yield for West Slope (firm yield) purposes. 3. Prepare a technical memorandum briefly summarizing background and key issues, discussion on assessment methodology (if applicable) and other applicable studies, conclusions on preliminary feasibility as an ERMOU project element, and recommendations on further investigations and to include project elements within a portfolio of combined project elements. A simple spreadsheet model will be developed to evaluate the operation of Bolts Lake enlargement. Because of the relatively small yield of Bolts Lake, it is not anticipated that this model will be integrated into the basin-wide operational model described above. 1.3.2 Environment LRE will complete the same level of environmental evaluations (including the same level of reporting and team coordination) identified for Eagle Park Reservoir to support Bolts Lake Reservoir evaluations. 1.3.3 Engineering Background – Bolts Lake is an existing 10 to 15 foot high dam located about 3 miles southeast of Minturn, CO. The dam was originally constructed in the 1880’s and we understand that the reservoir was in use throughout subsequent periods of mining and reclamation. In the 1990’s, the SEO required lowering of the reservoir because of dam safety concerns. This was accomplished by constructing a trench spillway in native ground adjacent to the dam. We understand that Bolts Lake was previously filled by a diversion from Cross Creek but this diversion was abandoned about 5 years ago. If this site is used in the future by the ERMOU partners, Bolts Lake would be enlarged to provide additional water storage and would be filled by a diversion from the Eagle River. This would be accomplished by constructing a diversion structure on the Eagle River, pump station, and diversion pipeline. 10 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 Applegate Group developed the Diversion Structure Engineering Review – Battle Mountain Project (2010) that presented a conceptual-level evaluation and cost opinion for diversion facilities from the Eagle River to Bolts Lake. The Eagle River diversion facilities were evaluated for a peak flow of 50 cfs. Evaluations are described minimally in the report. It would be difficult for RJH to confirm the suitability of concepts and costs presented in this report without performing independent engineering analyses. However, we understand that the ERMOU partners would like RJH to utilize information from this report and update costs to 2015 dollars. RJH will perform high-level checks to confirm the reasonableness of basic components (i.e. pipe size, total pumping head, pipe length, etc.) and update the overall cost to 2015 dollars based on construction cost index data. 8140 Partners LLC prepared 30-percent level design drawings (2012) for the reservoir lining system. The reservoir lining drawings do not include other necessary components such as an outlet works, upstream slope protection, filters, etc. and a cost opinion was not prepared for this design. In addition, RJH has identified some initial technical concerns with the design concept that should be more thoroughly investigated. However, as requested, RJH will assume that the lining concept can be utilized without additional engineering evaluations. RJH will prepare a cost estimate for the liner based on the 30-percent level design by 8140 Partners. Costs and concepts for the outlet works, spillway, slope protection and other ancillary facilities are presented in the Bolt Lake Engineering Review Report (2010) by Applegate Group. Evaluations are described minimally in the report. It would be difficult for RJH to confirm the suitability of concepts and costs presented in this report without performing independent engineering analyses. However, we understand that the ERMOU partners would like RJH to utilize information from this report and update costs to 2015 dollars. RJH will perform high-level checks to confirm the reasonableness of basic components and update the overall cost to 2015 dollars based on construction cost index data. Approach – RJH will complete the following activities. 1. Review existing engineering reports and identify technical issues that could impact the cost opinions and may need to be addressed in subsequent phases of design. 2. Perform a high-level engineering review to confirm sizes and identify possible technical issues for the diversion facilities presented in the Applegate Group report. 3. Perform a high-level engineering review to confirm sizes and identify possible technical issues for the dam and appurtenant facilities presented in the Applegate Group report. 4. Estimate quantities of primary materials required to construct the liner based on the 30-percent design by 8140 Partners. 5. Develop unit price and lump sum costs for key work items for the liner. 6. Update cost opinions to 2015 dollars for diversion facilities (i.e. pump stations and pipelines) as presented in the Diversion Structure Engineering Review – Battle Mountain Project (2010) by Applegate Group. 7. Update cost opinions to 2015 dollars for dam facilities (i.e. embankment, outlet works, slope protection, etc.) not including the liner, as presented in the Bolt Lake Engineering Review Report (2010) by Applegate Group. 8. Develop a feasibility-level Opinion of Probable Construction Cost. 9. Prepare and submit a draft Technical Memorandum for the site that presents a summary of the data collected, engineering reviews, and cost opinions from the feasibility-level evaluations. 11 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 10. Prepare and submit a final Technical Memorandum for the site based on comments provided by Wilson Water and the other ERMOU technical advisory members. Task 2 – Tier 2 Evaluations Tier 2 evaluations will be completed for four ERMOU project alternatives that have been identified in Phase 1 of the Study as requiring additional preliminary-level review (Wolcott Reservoir, Piney River Reservoir, EagleArkansas Ditch, and Iron Mountain Reservoir). These four alternatives require compilation of more preliminary information to assess their potential to contribute to ERMOU water yield objectives. Tier 2 evaluations will be completed through combined efforts by WWG and H&W (water supply); LRE (environmental); and RJH (engineering). 2.1 Wolcott Reservoir 2.1.1 Water Supply H&W water supply evaluations identified for Eagle Park Reservoir will support Wolcott Reservoir evaluations. WWG will complete the following activities to support Wolcott Reservoir evaluations. 1. Review, evaluate and update options to fill reservoir by gravity from Eagle River Pipeline. 2. Review, evaluate, and update delivery options from the reservoir to the Eagle River at Dowds Junction. 3. Assess reservoir operation and yield for West Slope (firm yield) purposes. 4. Prepare a technical memorandum briefly summarizing background and key issues, discussion on assessment methodology (if applicable) and other applicable studies, conclusions on preliminary feasibility as an ERMOU project element, and recommendations on further investigations and to include project elements within a portfolio of combined project elements. Water availability and operation of a Wolcott Reservoir will also be evaluated with the previously developed spreadsheet model. Wolcott Reservoir will divert water from the Eagle River either via a pump station immediately below the reservoir, or via a gravity pipeline that extends up valley to a site near Dowds Junction. Water diverted and stored in the reservoir will be released to the Eagle River for West Slope uses. The following primary work tasks are anticipated. 5. Develop native flow estimates for the Eagle River below Alkali Creek and for the Eagle River at Dowds Junction for the period from 1947 through 2014. 6. The model will be updated to evaluate the time period through 2014, and will be reconfigured as needed to consider the influence of the operation of Eagle Park Reservoir, Whitney Creek Reservoir, and potential changes in the historical operation of the Columbine Ditch. The model will also be updated to evaluate the effect of reservoir releases delivered to Dowds Junction. 2.1.2 Environmental LRE will complete the same level of environmental evaluations (including the same level of reporting and team coordination) identified for Eagle Park Reservoir to support Wolcott Reservoir evaluations. 12 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 2.1.3 Engineering Background – The Wolcott Reservoir site is located just north of Interstate-70 near Wolcott, Colorado. Several potential reservoir sites have been previously evaluated by others along both Alkali Creek and Ute Creek with sizes ranging from 50,000 to 350,000 ac-ft. Denver Water is the primary land owner for site along Alkali Creek and a potential partnership with Denver Water to construct Wolcott Reservoir along Alkali Creek may be possible or required. Relocation of Highway 131 may be required depending upon the size and configuration of the reservoir. The Colorado River Water Conservation District (CRWCD) is the primary land owner for site along Ute Creek. The location, size, and configuration of the reservoir may be limited in some cases by the existing landfill located in the upper portion of the Ute Creek drainage basin. The reservoir would be primarily filled by diversions from the Eagle River. This could be accomplished by a) constructing a new pump station along the Eagle River near Wolcott or b) by constructing a pump station at Dowds Junction, which is located near the confluence of the Eagle River and Gore Creek about 20 miles southeast of Wolcott, with a bi-directional flow pipeline. The bi-directional flow pipeline would also allow gravity releases from Wolcott Reservoir to Dowds Junction. Western Engineers developed the Wolcott and Red Cliff Projects Eagle Valley Pipeline Report (1988) that presented a conceptual-level evaluation and cost opinion for the pipeline and pump station from the proposed Wolcott Reservoir to Dowds Junction. The level of effort for the pipeline is similar to a 30-percent design. RJH will perform a high-level review to identify any technical issues with pump station and pipeline design concepts, and update the cost opinion to 2015 dollars. Grand River Consulting Corporation developed the Wolcott Reservoir Feasibility Assessment (2004) that presented a screening-level evaluation five reservoir configurations at two sites on Alkali Creek with storage capacities ranging from 50,000 acre-feet to 150,000 acre-feet and hydraulic facilities to convey fill the reservoir from the Eagle River. The report does not include a description of concepts or sizes for the embankment geometry, spillway or outlet works. It would be difficult for RJH to confirm the suitability of concepts and costs presented in this report without performing independent engineering analyses. However, we understand that the ERMOU partners would like RJH to utilize information from this report and update costs to 2015 dollars. RJH will perform high-level checks to confirm the reasonableness of basic components and update the overall cost to 2015 dollars based on construction cost index data. Approach – RJH will complete the following activities: 1. Collect and review available project documentation including available county and USGS topographic mapping data, aerial photographs, existing engineering reports and evaluations, GIS information, regional geologic maps, and any other available project documentation. 2. Identify a feasibility-level alignment for the diversion pipeline from the Eagle River near Wolcott to Wolcott Reservoir. 3. Perform simplified hydraulic analyses to select the location and required sizes for the diversion structure, pump stations, and pipeline to convey flows from the Eagle River near Wolcott to Wolcott Reservoir. 4. Develop a schematic plan figure showing the general location of facilities. 5. Estimate quantities of primary materials required to construct the Project components described above. 13 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 6. Develop unit price and lump sum costs for key work items. 7. Perform a high-level engineering review to confirm sizes and identify possible technical issues for the diversion facilities from Down Junction presented in the Western Engineers Report. 8. Perform a high-level engineering review to confirm sizes and identify possible technical issues for the dam facilities as presented in the Grand River Consulting report. 9. Update cost opinions to 2015 dollars for diversion facilities to/from Down Junction as presented in the Wolcott and Red Cliff Projects Eagle Valley Pipeline Report (1988) by Western Engineers using construction cost index data. 10. Update cost opinions to 2015 dollars for dam facilities as presented in the Wolcott Reservoir Feasibility Assessment (2004) by Grand River Consulting using construction cost index data. 11. Develop a feasibility-level Opinion of Probable Construction Cost. 12. Prepare and submit a draft Technical Memorandum for the site that presents a summary of the data collected, design concepts, engineering reviews, and cost opinions from the feasibility-level evaluations. 13. Prepare and submit a final Technical Memorandum for the site based on comments provided by WWG and the other ERMOU partners. 2.2 Piney River Reservoir One of the identified Tier 2 projects is a reservoir on the Piney River near Piney Lake. It was identified by Denver Water as part of their Eagle-Piney Project as a regulating reservoir for water pumped from Eagle-Colorado Reservoir (aka Wolcott Reservoir). It also collected Piney River stream flows and water diverted from tributaries of the Piney River. The Piney River is a tributary of the Colorado River. 1. LRE will conduct a preliminary review of readily available information on environmental issues associated with Piney River Reservoir site proposed by Denver Water as part of the Eagle-Piney Project and prepare a technical memorandum identifying potential permitting requirements and environmental issues that could affect permitting feasibility. 2. H&W will review existing reports and stream flow records for the Piney River and its tributaries; identify project components (pumps, pipelines, reservoir capacities) needed to make it usable for the ERMOU participants; and prepare a technical memorandum presenting conclusions and recommendations concerning preliminary feasibility as an ERMOU project. 2.3 Eagle-Arkansas Ditch WWG will review existing information associated with Eagle Arkansas Ditch and prepare a technical memorandum presenting conclusions and recommendations concerning preliminary feasibility as an ERMOU project. 2.4 Iron Mountain Reservoir WWG will review existing information associated with Iron Mountain Reservoir and prepare a technical memorandum presenting conclusions and recommendations concerning preliminary feasibility as an ERMOU project. 14 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 Task 3 – Reporting 3.1 Workshop – A one-day workshop will be held with the ERMOU Partners and the ERMOU technical advisors to review results of the Tier 1 and Tier 2 evaluations. The workshop will be used to compare attributes of each identified project alternative, to identify any new or modified alternatives for consideration, and to consider combining alternatives into portfolios for future planning purposes. Results of the workshop will be documented in a brief memorandum for inclusion to the draft report described below. 3.2 Draft Report – WWG will prepare a draft technical report summarizing: 1) results of the workshop described above; 2) evaluation procedures and results associated with water supply, environmental, and engineering considerations for ERMOU project alternatives; 3) and feasibility-level cost estimates for project alternatives deemed feasible. The draft report will be presented in a manner that facilitates comparison of ERMOU project alternatives to a level of detail that is consistent with information available and used for Phase 2 activities. The draft report will identify any deficiencies in available information and recommended investigations that would be necessary to address such deficiencies. 3.3 Peer Review – WWG will provide the draft technical report to the ERMOU Partners for review and comment. For the purposes of multi-disciplinary peer review, the ERMOU technical advisors will review and comment on select sections of the draft report for which they were not primary authors. WWG will compile the comments. 3.4 Final Report – WWG will finalize the draft technical report in response to peer review comments. The final technical report will include a conceptual phased plan for any further required investigations as well as permitting and construction of feasible project alternatives to develop the contemplated ERMOU yield. Task 4 – Team Coordination and Project Management Due to the number of participants in this project, a significant amount of effort is expected to effectively coordinate project activities, task deliverables, and communications between the ERMOU Partners and the technical advisors. Careful coordination will help avoid potential duplication of efforts on work tasks that are related and overlapping and assure the consistency of assumptions. WWG will manage Phase 2 of the Study through close coordination with the project team, participate in up to three onsite coordination meetings with the ERMOU Partners, and prepare monthly progress reports with invoices throughout the duration of the project. 15 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 BUDGET AND SCHEDULE We propose to complete the above scope of services on a time and expenses basis for an estimated total cost of $316,000 and according to the estimated schedule summarized by work task in Table 1 below. Fees will not exceed this amount without prior authorization from the ERMOU Partners. Table 1. Estimated Budget and Schedule – Eagle River MOU Project Alternatives Study – Phase 2 ERMOU CONSULTANT TEAM COST ESTIMATES ERMOU PROJECT WORK TASKS 1.1 Eagle Park Reservoir 1. Tier 1 Eval's 1.2 Whitney Ck Reservoir 1.3 Bolts Lake 2.1 Wolcott Reservoir 2. Tier 2 Eval's 3. Report Water Supply WWG H&W WWW $15,000 $12,000 $7,000 Environment LRE $9,400 $4,000 $13,100 Engineering $2,500 $8,700 Engineering $2,500 $7,600 Engineering $4,000 $37,000 $13,900 $1,800 $15,500 $5,800 $2,000 $2,000 2.4 Iron Mountain Reservoir $1,000 $1,000 3.1 Workshop $4,500 $15,000 3.3 Peer Review $1,500 3.4 Final Report Mar $50,000 2.3 Eagle-Arkansas Ditch $1,500 Feb $7,600 $15,500 3.2 Draft Report Jan $12,500 Environment 2.2 Piney River Reservoir Dec $8,700 $13,900 $5,000 Nov $7,500 Environment Water Supply Oct $13,100 $37,000 $5,000 Sep $14,000 Environment Water Supply Aug $9,400 $50,000 $10,000 ESTIMATED SCHEDULE $29,000 Engineering Water Supply RJH TOTAL COST ESTIMATES $1,500 $1,500 $2,500 $11,500 $15,000 $1,500 $1,500 $1,500 $1,500 $7,500 $5,000 $5,000 4. Team Coordination and Project Mgmt. $50,000 $50,000 TOTAL: $114,000 $28,000 $10,000 $43,600 $120,400 $316,000 The cost and schedule estimates are based on current workload of the ERMOU technical advisors, current understanding of the Project, and the scope of services described above. The budget for each task was developed based on estimating the level of effort and direct costs that are expected to be required to perform the work, recognizing that the actual level of effort to complete a particular work task could be more or less than estimated. 16 Scope of Services – Eagle River MOU Project Alternatives Study – Phase 2 Basis of Scope of Work and Fee Estimates for ‘Engineering’ Activities 1. Geotechnical investigations and laboratory testing will not be performed. 2. Topographic surveying will not be required. Engineering evaluations will be based on USGS 10-meter Digital Elevation Mapping. 3. Environmental permitting evaluations will be performed by others. 4. Water rights and yield evaluations will be performed by others. 5. Concepts and layouts for facilities will be developed based on engineering judgment, general design criteria, and previous experience on similar project. Feasibility-level layouts will illustrate key design features and be suitable to support the development of an opinion of probable construction cost. 6. Reservoir capacities and flow rates for pipelines and pump stations will be provided by WWG unless stated otherwise in the scope of work. 7. Coordination with the Colorado Office of the State Engineer (SEO) will not be required. 8. Costs for purchasing property, easements, rights-of-way, permitting, and legal costs will not be included in the opinion of probable construction cost. 17