7 2014 BUSINESS PLAN CAPITAL COST ESTIMATE UPDATE 2014 BUSINESS PLAN ESTIMATE SUMMARY COSTS BY PHASE • High and Low Costs (millions, 2012 $$) PHASE 2012 Low FCS $ IOS 2012 High 5,444 2014 Low 2014 High $ 5,444 $ 5,672 $ 5,672 $ 27,344 $ 31,923 $ 35,754 $ 38,236 B2B $ 42,042 $ 49,904 $ 49,984 $ 55,439 PH 1 $ 54,371 $ 63,441 $ 56,942 $ 63,091 • Phase I Low Cost increased $2.6 billion or 4.7% • Phase I High Cost decreased $0.3 billion or 0.5% DRAFT 2014 BUSINESS PLAN ESTIMATE SUMMARY COSTS BY SECTION • High and Low Costs (millions, 2012 $$) $18,000 $16,000 $14,000 $12,000 2012 Low $10,000 2012 High 2014 Low $8,000 2014 High $6,000 FEIR/S or Staff Recommended Preferred Alignment $4,000 $2,000 $SF-SJ DRAFT SJ-M M-F F-B B-P P-LA 2014 BUSINESS PLAN ESTIMATE DESIGN DEVELOPMENT STAGE Environmental Section San Francisco to San Jose Design Stage 2012 BP Design Stage 2014 BP 5% Design 5% Design San Jose to Merced Draft 15% Design Draft 15% Design Merced to Fresno Final 15% Design 15% - PE4P Design Fresno to Bakersfield Final 15% Design 15% - PE4P Design Bakersfield to Palmdale 5% Design 5% - Draft 15% Design Palmdale to Los Angeles 5% Design 5% Design DRAFT 2014 BUSINESS PLAN ESTIMATE ALIGNMENT ALTERNATIVES Environmental Section Low Cost Alignment Alternative High Cost Alignment Alternative San Francisco to San Jose Blended Operation East of UPRR /Pacheco Pass SR152/Henry Miller Avenue 24 Blended Operation US101 trench/Pacheco Pass/Henry Miller Avenue 21 San Jose to Merced Merced to Fresno Fresno to Bakersfield Bakersfield to Palmdale Palmdale to Los Angeles Hybrid/Avenue 24 Alternative Hanford East/WascoShafter/Bakersfield Hybrid elevated alignment Hybrid/Avenue 24 Alternative Hanford East/WascoShafter/Bakersfield Hybrid elevated alignment Oak Creek Alignment* SR14West/Santa Clarita South/elevated LAUS approach Tehachapi Alignment SR14East/Santa Clarita North/tunnel LAUS approach *Low cost alignment was developed as a derivative of the high cost option reflecting potential cost saving measures being implemented in the Oak Creek alignment alternative currently under study. DRAFT 2014 BUSINESS PLAN ESTIMATE SIGNIFICANT ASSUMPTIONS • Unit Price Elements reflect 25% markup for Contractor’s overhead and profit; • Allocated contingencies range from 10% to 25% per cost category; • Unallocated contingency is assumed at 5% of construction and ROW acquisition costs; • Soft costs assumed as % of construction costs: • 2% of total Construction for PE/E • 3% of total Construction for PM • 6% of total Construction for Final Design (3% for tunnels) • 4% of total Construction for CM • 0.5% of total Construction for Agency Costs • 6% of Systems and Electrification for Testing • Temporary facilities and indirect costs at 4% DRAFT 2014 BUSINESS PLAN ESTIMATE SIGNIFICANT INCLUSIONS • CP1 award costs including provisional sums and approved contingency; • SR 99 relocation costs per Caltrans agreement ($225.9 million); • CP1 agreements with 3rd parties ($80 million); • ‘Sunk costs’ (PM and PE/E, not including Authority's costs) from FY06/07 through FY12/13 ($497 million); • Projected cost for PE/E effort going forward ($539 million); • Connection to the Utility Grid costs ($960 million); • ‘Early Projects’ allowance for LA-ANA ($519 million). DRAFT 2014 BUSINESS PLAN ESTIMATE SIGNIFICANT EXCLUSIONS • Escalation to Year of Expenditure; • Overtime or accelerated schedule; • Post-Construction Costs; • Costs to implement interim service over FCS. DRAFT 2014 BUSINESS PLAN ESTIMATE SIGNIFICANT ADJUSTMENTS • Market Conditions – CP1 Bid Average Adjustment CP1 Bid Results vs. Budget $1,800 $1,600 $1,400 $1,200 $1,000 $800 $600 $400 $200 $0 $1,238 $1,407 YOE, millions • CP1 bid-average price is 88% of the CP1 Budget value; • Adjustment factor of 12% was applied on the UPEs for similar projectwide scope; • Accounts for $2.3 billion adjustment to Phase 1 costs in 2012 DRAFT 2014 BUSINESS PLAN ESTIMATE SIGNIFICANT ADJUSTMENTS • Escalation to Base Year • Estimate is based on 2009 pricing • Escalation has been per ENR published CCIs: – Industry recognized historic escalation index – Based on a hypothetical assembly of: – 200 hour of common labor – 2,500 lb of structural steel – 1.126 tons of portland cement – 1,088 ft of 2x4 lumber DRAFT 2014 BUSINESS PLAN ESTIMATE SIGNIFICANT ADJUSTMENTS • Escalation by Component Weights* Aggregated Escalation Factor 15.00% 15.20% 25.80% Concrete 6.40% 10.00% Steel Labor Concrete 5.00% Steel Equipment 8.70% Other Labor 0.00% 44.00% 2009 -5.00% 2010 2011 2012 Equipment Other Overall *Based on rail transit projects nation-wide. Price Indexes: -10.00% -15.00% • Steel – ENR price index • Concrete – ENR price index • Equipment - BLS data • Labor – Prevailing wage agreements • Other – Consumer Price Index DRAFT 2014 BUSINESS PLAN ESTIMATE SIGNIFICANT ADJUSTMENTS • Escalation Index – ENR vs. Component Weights • Reflects an escalation approach targeting linear rail construction • Founded on published cost indexes in California and nationally • Accounts for $370-$410 million increase to Phase 1 costs in 2012 dollars. Compound Escalation Rates 8.00% 7.00% 6.73% 6.08% 6.00% 5.00% 4.15% 4.00% ENR CCI Component Weights 3.00% 2.00% 1.93% 2.13% 1.00% 0.65% 0.00% 2010 2011 2012 DRAFT DRAFT 2014 BUSINESS PLAN ESTIMATE COMPARISON TO 2012 BY CATEGORY $14,000 $12,000 $12,000 $10,000 $10,000 $8,000 $8,000 $6,000 $6,000 $4,000 $2,000 2012 BP, Low $4,000 2012 BP, High 2014 BP, Low $2,000 2014 BP, High $Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. $- Env. Section 2012 Low 2012 High 2014 Low 2014 High SF-SJ $ 5,686 $ 5,686 $ 3,977 $ 3,977 SJ-M $ 13,733 $ 17,017 $ 13,195 $ 16,168 M-F $ 3,863 $ 6,859 $ 4,110 $ 4,110 F-B $ 6,425 $ 7,460 $ 8,479 $ 8,479 B-P $ 7,733 $ 7,953 $ 10,023 $ 10,906 P-LA $ 12,557 $ 14,092 $ 12,645 $ 14,937 2014 BUSINESS PLAN ESTIMATE PROGRAM-WIDE UPDATES $350 • Environmental Mitigation $300 • Based on scope definition in M-F section; $250 • Adjusted for level of development; $150 • Adjusted for relation to grade. $100 $200 2012 BP 2014 BP $50 $- • ROW Acquisition SF-SJ Section ROW Cost Update Contingency SF-SJ June, 2011 20% SJ-M June, 2011 10% M-F April, 2013 25% F-B August, 2012 10% B-P June, 2013 10% P-LA April, 2013 25% SJ-M M-F F-B B-P P-LA DRAFT 2014 BUSINESS PLAN ESTIMATE SAN FRANCISCO – SAN JOSE $2,500 $2,500 $2,000 $2,000 $1,500 $1,500 $1,000 $1,000 2012 BP, Low 2014 BP, Low $500 2014 BP, High $500 Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. $Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. $- 2012 BP, High • $1,710 million reduction: • Reduction in Transbay allowance to $500 million • Transfer of TSMF to SJ-M section • Reductions in viaducts and walls due to CP1 adjustment DRAFT 2014 BUSINESS PLAN ESTIMATE SAN JOSE - MERCED $3,500 $3,500 $3,000 $3,000 $2,500 $2,500 $2,000 $2,000 $1,500 $1,500 2012 BP, Low $1,000 2012 BP, High $1,000 2014 BP, High $500 $- $Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. $500 • $540 - $850 million reduction: Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. 2014 BP, Low • Reduction in viaducts due to CP1 adjustment • Reduction in grade separations due to CP1 adjustment • Reduction in utility relocations • Reduction in mitigation due to tunneling • Added Sunk Costs and PE/E allowance DRAFT 2014 BUSINESS PLAN ESTIMATE MERCED - FRESNO $700 $3,000 $600 $2,500 $500 $2,000 $400 $1,500 $300 2012 BP, Low $200 2012 BP, High $1,000 2014 BP, Low $- $- Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. $100 Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. 2014 BP, High $500 • $250 million increase to $2,750 million decrease: • Increase in ROW acquisition costs • Reductions in grade separations due to CP1 adjustment • Significant cost reduction by adoption of Hybrid Alternative DRAFT 2014 BUSINESS PLAN ESTIMATE FRESNO - BAKERSFIELD $2,500 $2,500 $2,000 $2,000 $1,500 $1,500 $1,000 $1,000 2012 BP, High 2012 BP, Low 2014 BP, Low $500 2014 BP, High $500 Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. $- $- • $2,050 million increase (low vs. preferred): • More viaducts in through town alignments • Allowance for taller viaducts over Kings River complex • Added station access roadways at Hanford • Increased Utilities and ROW acquisition costs • Added Sunk Costs and PE/E allowance DRAFT 2014 BUSINESS PLAN ESTIMATE BAKERSFIELD - PALMDALE $3,500 $3,000 $3,000 $2,500 $2,500 $2,000 $2,000 $1,500 $1,500 2012 BP, Low $1,000 2012 BP, High $1,000 2014 BP, High $- $Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. $500 $500 • $2,290 - $2,950 million increase: Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. 2014 BP, Low • Significant increases in cut/fill quantities • Very tall and long span viaduct structures • Access roadways, lateral and along alignment • Included TSMF from P-LA section • Increased Utilities and ROW acquisition costs • Added Sunk Costs and PE/E allowance DRAFT 2014 BUSINESS PLAN ESTIMATE PALMDALE – LOS ANGELES $6,000 $5,000 $4,500 $5,000 $4,000 $3,500 $4,000 $3,000 $3,000 $2,500 $2,000 2012 BP, Low $1,500 2014 BP, Low $1,000 2012 BP, High $2,000 2014 BP, High $1,000 $500 Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. • $90 - $845 million increase: Track Earthwork Viaducts Tunnels Trenches Facilities Grade Seps Utilities Demo & Temp. Mitigation Walls & Barriers Systems Electrification ROW Prof. Serv. $- $- • Increase in tunneling costs due to unit price update • Transfer of TSMF to B-P section • Reduction in environmental mitigation due to tunneling • Increased ROW acquisition costs • Added Sunk Costs and PE/E allowance DRAFT 2014 BUSINESS PLAN ESTIMATE FOLLOW UP ACTIONS • Escalation to YOE – in P6 utilizing KPMG inflation rates • Confirm limits of implementation stages – IOS terminus • Arrange for Independent Cost Estimate (ICE) • Implement sensitivity analyses where feasible DRAFT THANK