Buildings for Our Future-March 2017 Referendum Adjusted Project Scope December 22, 2016 Buildings for Our Future Projects-Reduced Scope Longfellow Lyseth Presumpscot Reiche Total A CONSTRUCTION 1 Construction Estimate Renovation/Reconfiguration Structural/Architectural Mechanical/Plumbing/Sprinkler Electrical Renovation non-equity model New Construction/Addition Demolition Built-in Equipment Site Development Elevator (CIP Project) Subtotal $2,347,330 $2,162,112 $1,342,928 $1,639,264 $3,232,078 $0 $699,444 $1,135,151 $0 $12,558,306 $1,684,560 $1,605,899 $963,067 $683,502 $7,733,316 $60,744 $644,007 $2,356,216 $0 $15,731,312 $1,194,543 $883,160 $599,972 $424,113 $7,500,983 $0 $570,878 $1,319,436 $0 $12,493,085 $3,357,532 $3,469,776 $2,417,651 $2,691,906 $1,235,621 $0 $481,236 $804,796 -$800,000 $13,658,517 $8,583,964 $8,120,946 $5,323,618 $5,438,785 $19,701,998 $60,744 $2,395,565 $5,615,600 -$800,000 $54,441,221 $0 $1,028,084 $55,000 $0 $35,000 $1,255,831 $2,373,915 $0 $1,198,292 $55,000 $0 $35,000 $1,573,131 $2,861,423 $0 $1,005,628 $55,000 $0 $35,000 $1,249,309 $2,344,937 $0 $1,180,835 $55,000 $0 $35,000 $1,365,852 $2,636,687 $0 $4,412,839 $220,000 $0 $140,000 $5,444,123 $10,216,962 $1,112,237 $10,000 $39,400 $0 $18,760 $39,500 $15,000 $125,000 $84,000 $65,000 $0 $1,508,897 $1,285,410 $10,000 $39,400 $0 $27,532 $45,500 $15,000 $125,000 $84,000 $80,000 $0 $1,711,842 $999,319 $10,000 $39,400 $0 $18,760 $39,500 $15,000 $125,000 $84,000 $60,000 $0 $1,390,979 $1,286,669 $10,000 $39,400 $0 $18,760 $39,500 $15,000 $125,000 $84,000 $80,000 $0 $1,698,329 $4,683,635 $40,000 $157,600 $0 $83,812 $164,000 $60,000 $500,000 $336,000 $285,000 $0 $6,310,047 $16,441,119 $20,304,577 $16,229,001 $17,993,533 $70,968,229 B ADMINISTRATIVE COSTS & RESERVES 2 3 4 5 6 7 Land Purchase and Related Costs Moveable Equipment Advertising and Legal Percent for Art Project Reserves Project Contingency Subtotal C FEES AND SERVICES 8 9 10 11 12 13 14 15 16 17 18 Architect / Engineer Basic Services Architect / Engineer Additional Services Architect / Engineer Reimbursables Site Selection Permitting & Approvals Survey and Soils Construction Testing PPS-Project Manager Clerk of the Works Commissioning Other Professional Services Subtotal 6.9% D TOTAL PROJECT COST E POTENTIAL REDUCTIONS 19 Potential Reductions (see individual project budgets) F ADJUSTED TOTAL PROJECT COSTS $0 $0 $0 $0 $0 -$2,657,474 -$4,004,512 -$2,600,822 -$747,256 -$10,010,065 $13,783,644 $16,300,065 $13,628,178 $17,246,276 $60,958,164 Proposed Reduction 1 $10,010,065 12/22/2016 Longfellow Elementary School Grades Pre-K through 5 December 22, 2016 BFOF EscalatedReduced Scope A CONSTRUCTION 1 Construction Estimate Renovation/Reconfiguration Structural/Architectural 25,949sf x $43 + 19,594sf x $63 Mechanical/Plumbing/Sprinkler45,543sf x $47 Electrical 45,543sf x $29 Renovation non-equity model 15,844sf x $204 New Construction/Addition Demolition Built-in Equipment Site Development Subtotal $2,347,330 $2,162,112 $1,342,928 $1,639,264 $3,232,078 $0 $699,444 $1,135,151 $12,558,306 B ADMINISTRATIVE COSTS & RESERVES 2 3 4 5 6 7 Land Purchase and Related Costs Moveable Equipment Advertising and Legal Percent for Art Project Reserves Project Contingency Subtotal $0 $1,028,084 $55,000 $0 $35,000 $1,255,831 $2,373,915 C FEES AND SERVICES 8 9 10 11 12 13 14 15 16 17 18 Architect / Engineer Basic Services # Architect / Engineer Additional Services Architect / Engineer Reimbursables Site Selection Permitting & Approvals Survey and Soils Construction Testing Project Coordination Clerk of the Works Commissioning Other Professional Services Subtotal D TOTAL PROJECT COST $1,112,237 $10,000 $39,400 $0 $18,760 $39,500 $15,000 $125,000 $84,000 $65,000 $0 $1,508,897 $16,441,119 G1 SBE Design & Funding Approval x/yy/zz $0 E POTENTIAL ADJUSTMENTS* 19 20 21 22 23 24 25 26 27 28 Reduce moveable equipment allowance to 4% Reduce size of gym to ES size Remove locker rooms Delete playground improvements Remove Outdoor Learning improvements Built-In equipment reduction Delete generator pad/conduit Elevator Phase 1-SRRF Application Elevator Phase 2-Future SRRF Application/CIP Masonry restoration of brick façade-CIP Project Subtotal F ADJUSTED TOTAL PROJECT COSTS 2 *Reduction Costs include associated markups and fees -$228,463 -$263,250 -$163,800 -$137,715 -$77,465 -$175,000 -$7,297 -$500,484 -$580,000 -$524,000 -$2,657,474 $13,783,644 12/22/2016 Lyseth Elementary School Grades Pre-K through 5 December 22, 2016 BFOF EscalatedReduced Scope A CONSTRUCTION 1 Construction Estimate Renovation/Reconfiguration Structural/Architectural 23,249sf x $36 + 16,855sf x $50 Mechanical/Plumbing/Sprinkler40,104sf x $40 Electrical 40,104sf x $24 Renovation non-equity model New Construction/Addition 37,908sf x $204 Demolition Built-in Equipment Site Development Subtotal $1,684,560 $1,605,899 $963,067 $683,502 $7,733,316 $60,744 $644,007 $2,356,216 $15,731,312 B ADMINISTRATIVE COSTS & RESERVES 2 3 4 5 6 7 Land Purchase and Related Costs Moveable Equipment Advertising and Legal Percent for Art Project Reserves Project Contingency Subtotal $0 $1,198,292 $55,000 $0 $35,000 $1,573,131 $2,861,423 C FEES AND SERVICES 8 9 10 11 12 13 14 15 16 17 18 Architect / Engineer Basic Services # Architect / Engineer Additional Services Architect / Engineer Reimbursables Site Selection Permitting & Approvals Survey and Soils Construction Testing Project Coordination Clerk of the Works Commissioning Other Professional Services Subtotal D TOTAL PROJECT COST E POTENTIAL ADJUSTMENTS* 19 20 21 22 23 24 25 26 27 28 Reduce moveable equipment allowance to 4% Reduce size of gym to ES size Remove locker rooms Delete playground improvements Remove Outdoor Learning improvements Delete second floor addition Built-In equipment reduction Delete Moore Parking improvements Delete generator pad/conduit Delete Bus loop/field work Subtotal F ADJUSTED TOTAL PROJECT COSTS3 *Reduction Costs include associated markups and fees $1,285,410 $10,000 $39,400 $0 $27,532 $45,500 $15,000 $125,000 $84,000 $80,000 $0 $1,711,842 $20,304,577 $0 -$266,316 -$320,112 -$131,976 -$77,465 -$68,857 -$1,260,000 -$175,000 -$247,489 -$7,297 -$1,450,000 -$4,004,512 $16,300,065 12/22/2016 Presumpscot Elementary School Grades Pre-K through 5 December 22, 2016 BFOF EscalatedReduced Scope A CONSTRUCTION 1 Construction Estimate Renovation/Reconfiguration Structural/Architectural 10,587sf x $38 + 14,397sf x $55 Mechanical/Plumbing/Sprinkler24,984sf x $35 Electrical 24,984sf x $24 Renovation non-equity model 36,770sf x $204 New Construction/Addition Demolition Built-in Equipment Site Development Subtotal $1,194,543 $883,160 $599,972 $424,113 $7,500,983 $0 $570,878 $1,319,436 $12,493,085 B ADMINISTRATIVE COSTS & RESERVES 2 3 4 5 6 7 Land Purchase and Related Costs Moveable Equipment Advertising and Legal Percent for Art Project Reserves Project Contingency $0 $1,005,628 $55,000 $0 $35,000 $1,249,309 $2,344,937 Subtotal C FEES AND SERVICES 8 9 10 11 12 13 14 15 16 17 18 Architect / Engineer Basic Services # Architect / Engineer Additional Services Architect / Engineer Reimbursables Site Selection Permitting & Approvals Survey and Soils Construction Testing Project Coordination Clerk of the Works Commissioning Other Professional Services Subtotal $999,319 $10,000 $39,400 $0 $18,760 $39,500 $15,000 $125,000 $84,000 $60,000 $0 $1,390,979 D TOTAL PROJECT COST $16,229,001 E POTENTIAL ADJUSTMENTS* 19 20 21 22 23 24 25 26 27 $0 Reduce moveable equipment allowance to 5% Reduce size of gym to ES size Delete playground improvements Remove Outdoor Learning improvements Delete second floor addition Built-In equipment reduction Add Operable partitions Delete generator pad/conduit Reduce size of admin space Subtotal F ADJUSTED TOTAL PROJECT COSTS $0 -$111,736 -$283,433 -$34,428 -$34,428 -$2,025,000 -$100,000 $58,500 -$7,297 -$63,000 -$2,600,822 $13,628,178 4 *Reduction Costs include associated markups and fees 12/22/2016 Reiche Elementary School Grades Pre-K through 5 December 22, 2016 BFOF EscalatedReduced Scope A CONSTRUCTION 1 Construction Estimate Renovation/Reconfiguration Structural/Architectural 31,458sf x $37 + 44,459sf x $49 Mechanical/Plumbing/Sprinkler75,917sf x $46 Electrical 75,917sf x $32 Renovation non-equity model New Construction/Addition 6,057sf x $204 Demolition Built-in Equipment Site Development Elevator (CIP Project) Subtotal $3,357,532 $3,469,776 $2,417,651 $2,691,906 $1,235,621 $0 $481,236 $804,796 -$800,000 $13,658,517 B ADMINISTRATIVE COSTS & RESERVES 2 3 4 5 6 7 Land Purchase and Related Costs Moveable Equipment Advertising and Legal Percent for Art Project Reserves Project Contingency Subtotal $0 $1,180,835 $55,000 $0 $35,000 $1,365,852 $2,636,687 C FEES AND SERVICES 8 9 10 11 12 13 14 15 16 17 18 Architect / Engineer Basic Services # Architect / Engineer Additional Services Architect / Engineer Reimbursables Site Selection Permitting & Approvals Survey and Soils Construction Testing Project Coordination Clerk of the Works Commissioning Other Professional Services Subtotal D TOTAL PROJECT COST E POTENTIAL ADJUSTMENTS* 19 20 21 22 23 24 25 Reduce moveable equipment allowance to 4% Delete playground improvements Remove Outdoor Learning improvements Delete floor infill (stepped areas) Built-In equipment reduction Add operable partitions Delete generator pad/conduit Subtotal F ADJUSTED TOTAL PROJECT COSTS *Reduction Costs include associated markups5 and fees $1,286,669 $10,000 $39,400 $0 $18,760 $39,500 $15,000 $125,000 $84,000 $80,000 $0 $1,698,329 $17,993,533 $0 -$257,074 -$177,783 -$280,302 -$189,000 -$50,000 $214,200 -$7,297 -$747,256 $17,246,276 12/22/2016