Case 1:16-cv-01534-JEB Document 191 Filed 03/27/17 Page 1 of 3 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA STANDING ROCK SIOUX TRIBE; YANKTON SIOUX TRIBE; ROBERT FLYING HAWK; OGLALA SIOUX TRIBE, Plaintiffs, and CHEYENNE RIVER SIOUX TRIBE, Case No. 1:16-cv-01534-JEB Intervenor Plaintiff, v. U.S. ARMY CORPS OF ENGINEERS, Defendant, and DAKOTA ACCESS, LLC, Intervenor Defendant.   STATUS REPORT OF DAKOTA ACCESS, LLC Pursuant to the Court’s February 13, 2017 Order, Dakota Access, LLC (“Dakota Access”) hereby provides this updated status report on construction of the Dakota Access Pipeline at Lake Oahe. Oil has been placed in the Dakota Access Pipeline underneath Lake Oahe. Dakota Access is currently commissioning the full pipeline and is preparing to place the pipeline into service. In light of these developments, Dakota Access understands that weekly status reports are no longer required under the terms of the February 13, 2017 Order. The company therefore will not be filing additional reports unless otherwise directed by the Court. 1 Case 1:16-cv-01534-JEB Document 191 Filed 03/27/17 Page 2 of 3 Dated: March 27, 2017 Respectfully submitted, Kimberly Caine William J. Leone Robert D. Comer NORTON ROSE FULBRIGHT US LLP 799 9th St. NW, Suite 1000 Washington, D.C. 20001-4501 (202) 662-0200 /s/ William S. Scherman William S. Scherman David Debold GIBSON, DUNN & CRUTCHER LLP 1050 Connecticut Avenue, N.W. Washington, D.C. 20036 (202) 955-8500 wscherman@gibsondunn.com Counsel for Dakota Access, LLC 2 Case 1:16-cv-01534-JEB Document 191 Filed 03/27/17 Page 3 of 3 CERTIFICATE OF SERVICE I hereby certify that on this 27th day of March, 2017, I electronically filed the foregoing document using the CM/ECF system. Service was accomplished by the CM/ECF system. /s/ William S. Scherman William S. Scherman GIBSON, DUNN & CRUTCHER LLP 1050 Connecticut Avenue, N.W. Washington, D.C. 20036 (202) 955-8500 wscherman@gibsondunn.com Counsel for Dakota Access, LLC