DEPARTMENT OF HOMELAND SECURITY U.S. CUSTOMS AND BORDER PROTECTION INTERAGENCY AGREEMENT WITH DEPARTMENT OF THE INTERIOR OFFICE OF THE SECRETARY OFFICE OF LAW ENFORCEMENT AND SECURITY INTERAGENCY AGREEMENT FINAL REPORT DELIVERABLE UNDER CONTRACT NUMBER 1010X00180 March 2016 PRODUCED FOR: INTERAGENCY BORDERLAND COORDINATOR DEPARTMENT OF THE INTERIOR PREPARED BY: BORDER MITIGATION COORDINATOR DEPARTMENT OF THE INTERIOR FISH AND WILDLIFE SERVICE 1.0 INTRODUCTION This report is the final deliverable under Interagency Agreement (IAA) number 1010X00180, as amended February 2012, between the Department of Homeland Security (DHS) and the Department of the Interior (DOI). The agreement period of performance was between August 25, 2010, to September 30, 2015, and was funded at $17,812,803.00. Table 1 depicts the allocation of funds for implementation of the 11 conservation actions along the southern border from California to Texas. This report is the culmination of the efforts by the DOI to implement the conservation actions in accordance with the IAA Statement of Work, Project Description Worksheets. Table 1. Fund Status as of September 30, 2015 Conservation Action Number and Title 200A Mitigation Coordinator 200B Sasabe Biological Opinion 200C Organ Pipe Cactus NM Biological Opinion 200D San Bernardino Valley Mitigation 200E Rio Yaqui Fish Studies 200F Peninsular Bighorn Sheep Study 200G Coronado NM Agave Restoration 200H Northern Aplomado Falcon Reintroduction and Habitat 200I Border-wide Bat Conservation 200J CA Land Acquisition 200K TX Land Acquisition Initial Budgeted Amount $685,500.00 $2,119,000.00 $980,000.00 Amount Realigned Amount Unspent $0.00 -$99,000.00 $0.00 $0.83 $0.68 $2,958.05 $657,480.00 $441,250.00 $230,000.00 $274,873.00 $499,700.00 +$15,000.00 $0.00 -$36,808.00 $0.00 $0.00 $96.70 $0.00 $0.80 $1,187.41 $12.86 $925,000.00 $8,000,000.00 $3,000,000.00 $17,812,803.00 +$84,000.00 +$36,808.00 $0.00 $3,531.01 $0.00 $0.00 $7,788.35 This final report varies from previous bi-annual reports where we reported what had happened in the previous six - 12 months, a funds status for that timeframe, and a six-month forecast as to what we were expecting to accomplish in the next six months, by conservation action. The final report is formatted to describe how each of the conservation action was implemented by the task(s) as per the project description worksheets followed by how we accomplished each of the task(s) to meet those expectations. Figure 1 illustrates the distribution and general location of all eleven conservation actions. Additionally in Section 3.0, each conservation action has a breakdown of how the funds were spent based on funding line charges (Table 14). This breakdown is represented as a pie-chart, accompanied by a table of expenses. The Statement of Work, Section II(B) stipulated that 40% of the work was to have been accomplished by in-house DOI personnel; the overall percentage was 23%. Conservation Actions 200A, 200C, and 200G exceeded the 40% target; conservation actions 200D and 200E would have exceeded the target if 2 we account for the materials purchased required for the in-house work to be accomplished. The DOI personnel who managed each of these conservation actions have written up their accomplishments that are referenced in the relevant sections in the Appendices. Figure 1. Distribution Map of Conservation Actions 200J 200F 200C 200B 200I 200A 200H 200G 200D 200E 200K Often with government acquisition, there are modifications to the original agreement. As in this case, Custom and Border Protection (CBP) issued seven modifications to this agreement, as highlighted in Table 2. Two of the modifications were to add $13,000,000 to the original IAA, one was to reset the frequency of the DOI IPACs to CBP for reimbursement, one was to extend the POP of individual conservation actions within the IAA POP to ensure the work would be accomplished within the 5 years of the agreement, and the final type of modifications was to realign funding from one conservation action to another to ensure the funds would be spent on appropriate mitigation. 3 Table 2. IAA Modifications for IAA 1010X00180 Mod # Date 001 8/2/2011 002 003 004 005 006 007 Purpose of Modification Change frequency of IPAC from DOI to CBP from annual to monthly 2/16/2012 New conservation action (200J: CA Land Acquisition) 5/4/2012 New conservation action (200K: TX Land Acquisition) 4/13/2012 Change from Monthly to Advance for the $8M for 200J: CA Land Acquisition 12/9/2013 Adjustments to period of performance or realignment of funding on original nine conservation actions, e.g. $84K from 200B to 200I, allow $90K on 200B to include ocelot surveys. 10/31/2014 Realign funding of $110K from TX land acquisition to acquire and deploy ocelot collars 6/11/2015 Reallocation of funding from 200F to 200J -- $36,808 Reallocation of funding from 200B to 200D -- $15,000 “No Cost Mod” or add $ Mod No Cost Conservation Action(s) Affected $8,000,000 200J $3,000,000 200K No Cost 200J No Cost 200A-200I No Cost 200K No Cost 200F & 200J 200B & 200D None 2.0 STATUS OF CONSERVATION ACTIONS This section contains a short summary of what was accomplished to meet each of the conservation actions; additionally, each project lead and/or team wrote up their accomplishments over the past five years which are attached in the appendices. That information is not necessarily included in this section. Each conservation action contains a figure illustrating the project location on a map, the task(s) required under the IAA, a table of the funding breakdown, and a summary description of the work accomplished. 4 2.1 200A- Mitigation Coordinator: Figure 2. Location Map on Conservation Action 200A Task #1: Program Management 1a. Track and report project status (6-month, annual, and tri-annual reports) 1b. Contract management 1c. Coordinate and complete various procedural requirements, realty acquisition and contaminant reviews for T&E species and trust resources, as a result of CBP activities 5 Table 3. Funding Breakdown on Conservation Action 200A Budgeted Tasks Salary & Benefits Travel Office Equipment Cell Phone Vehicle PCS Totals Original Budgeted Amount $500,000.00 Actual Budgeted Amount $521,980.96 $50,000.00 $4,000.00 $22,343.88 $2,818.30 $1,500.00 ($30,000.00)1 $125,000.00 $685,500.00 Contract In-house $0.00 $521,980.96 $0.00 $2,818.30 Remaining Amount $0.00 $22,343.88 $0.00 $0.00 $0.00 $779.38 $779.38 $0.00 $0.00 $0.00 $0.00 $137,576.64 $137,576.64 $0.00 $685,499.16 $141,174.32 $544,324.84 $0.00 $0.00 $0.00 $0.84 1 Adding error so a vehicle was not leased or purchased. Mitigation Coordinator used commercial rental car as needed, and charged to Travel. The roles and responsibilities of the mitigation coordinator were clearly defined in the project description worksheet for this conservation action, also in the statement of work for the IAA. The Border Mitigation Coordinator (BMC) worked closely with all project leads to develop and implement spend plans and to achieve the intended outcomes as described in each of the conservation actions and SOW. Over the term of the IAA, CBP requested two briefings for updates to supplement the 6-month reports. For both briefings, the BMC worked closely with the CBP COR assigned to the IAA and the DOI Interagency Borderland Coordinator. The BMC drafted the format of the briefings and received approval from the DOI IBC and the CBP COR before initiating feedback from each of the conservation actions for their input into the briefing slides. The BMC coordinated the location and meeting support (IT and catering) for both meetings. The briefing slides and supporting information was provided to the DOI IBC, CBP COR and other CBP managers in attendance. In addition to the bi-annual reports, the BMC also delivered a spend plan after CBP’s concerns regarding the rate of obligations as presented in the 2012 Annual Report (dated October 2012). This FY13-FY15 Spend Plan report addressed those comments and concerns from CBP’s review of the above referenced annual report. The BMC coordinated with each of the conservation action project leads and verified that they would meet the milestones as agreed to in the spend plan. As with every process, some of the conservation actions met the milestones and some did not. In the end, all but approximately $7,788.35 was spent; when the FWS closes out the IAA, those funds will be deobligated and “returned” to CBP. As part of the BMC duties, the BMC became a certified Contracting Officer Representative (COR) and acted in that role for all Region 2 contracts and supported Region 8, as needed. The BMC assisted Organ Pipe Cactus NM with the habitat restoration contract by taking on role of Technical Evaluation Team Chair and drafted the Contractor Award Justification for the NPS Contracting Officer to sign. 6 The BMC supported the DOI IBC in two major ways, the first by attending two of the Arizona Border Forums (January 2014, and March 2015) and secondly, by participating in the monthly DOI Border Call. The BMC attended the meeting, took notes, provided an AZ project status briefing, and provided a draft of the notes and action items to the DOI IBC afterwards. The BMC participated in over 90% of the monthly border calls initiated by the DOI IBC and provided a status on each of the conservation actions, budget analysis, and timelines of milestones, as needed. 2.2 200B- Sasabe Biological Opinion (BO) (jaguar, lesser long-nosed bat, erosion control): Figure 3. Location Map on Conservation Action 200B Task #1: Survey, monitor, conserve, and recover jaguars and their habitat 1a. Jaguar survey and monitoring for 4 years, at the U.S./Mexico border where jaguars are most likely to cross; along potential, historic, and known jaguar travel corridors within the northern jaguar range; and other areas, as appropriate. 1b. Jaguar conservation includes: 1b1 development and implementation of management plans for landowner stewardship, 7 1b2 outreach and education, 1b3 landowner assistance and incentives, and 1b4 conservation planning. Task #2 Road repair – reference Modification #005. Task #3 Agave planting – reference Modification #005. Table 4. Funding Breakdown on Conservation Action 200B Budgeted Tasks Task 1.a: Jaguar Surveying and Monitoring Task 1.b.1: Land Stewardship Task 1.b.2: Outreach/education Task 1.b.3: Landowner assistance and incentives Task 1.b.4: Conservation Planning Task 2: Lesser longnosed bat foraging plant replacement Task 3: Stabilization and Revegetation of Disturbed Soils Reallocation (from Tasks 2 & 3) to 200I -Interagency Agreement with Forest Service to install roost protections Reallocation (from Task 1.b.1) to 200D – labor to build gabions (Task#3) Realignment (from Task 1.b.1) to Buenos Aries NWR– labor for habitat enhancement Totals Original Budgeted Amount $800,000 Actual Budgeted Amount $978,287.46 $978,287.46 $0.00 $0.00 $500,000 $70,067.88 $70,067.88 $0.00 $0.00 $200,000 $292,882.13 $292,882.13 $0.00 $0.00 $285,000 $330,086.00 $330,086.00 $0.00 $0.00 $250,000 $276,394.03 $197108.15 $79,285.20 $0.68 $75,000 $0.00 $0.00 $0.00 $0.00 $43,500 $0.00 $0.00 $0.00 $0.00 $84,000 $84,000.00 (Table 11) $0.00 $0.00 $15,000 $15,000.00 (Table 6) $0.00 $0.00 $73,000 $0.00 $72,282.50 $0.00 $2,119,000.00 $2,119,000.00 $1,868,431.62 $151,567.70 $0.68 8 Contract In-house Remaining Amount The tasks required under this conservation action are based on the Naco-Douglas-Sasabe Biological Opinion 22410-2007-F-04160 to meet CBP mitigation requirements. During the development of a spend plan for this work, it was decided that allocating the funds for tasks 2 and 3 would be better spent on 200I – Border-wide Bats. After receiving approval to do the reallocation under modification #005, a consultation letter from the Tucson ES FO was issued to support this decision. The remaining work, Task #1, focused on gathering and collating natural history on the jaguar within the Northern Recovery Unit as determined by the Jaguar Recovery Team. The information garnered from the contracts has assisted the biologists and the Jaguar Recovery Team in developing many tools for managing and protecting jaguars and their habitat. The draft of the jaguar recovery plan was also moved forward because of the time the field biologists were able to dedicate to its development. One key aspect of protecting jaguars is getting the correct information to the public. After the first year, we had to make adjustments as to what we were going to do and how we were going to spend these funds. For example, after the submission of the first 6-month report, we were told by CBP that we couldn’t use the funds for cooperative agreements or grants because the funding source agency could not. Under the Economy Act, one Federal agency cannot give funds to another Federal agency to spend those funds in a manner that the funding agency cannot. CBP cannot fund cooperative agreements or grants, and therefore, neither could the DOI agencies. Another change occurred during the CBP briefing in June 2012, CBP made it clear that we couldn’t spend funds in Mexico or for Mexican nationals. These two restrictions caused the Tucson ES FO to reassess how they were going to obligate and spend the funds because they had originally planned on using cooperative agreements and grants to bring in local and Mexican experts to do work in Mexico and with Mexican landowners, especially tasks 1b1, 1b2, and 1b3, and for task 1a - jaguar surveying and monitoring throughout the entire Northern Recovery Unit and not just the area north of the border. We were able to overcome these issues and focused our efforts on what could be done in the United States using American contractors and experts. A number of contracts were issued to small business contractors, universities, not-for-profit organizations, and the Tohono O’odoham Nation. We also issued two intra-agency agreements with the BLM. While most of the work was accomplished under contracts, the field biologists did spend time writing the Jaguar Recovery Plan as in-house labor. Due to the contract with Tohono O’odoham Nation completed with excess funds, we were able charge labor hours to the habitat restoration effort at Buenos Aires NWR. There were a number of contract deliverables that will greatly benefit the jaguar and ocelots along the southern border. For example, a contractor studied a number of existing corridor enhancements for roadways and provided those examples along with potential sites along AZ 9 and NM to place them for jaguar and ocelot crossings. Because the crossing recommendations were adaptable, Texas Fish and Wildlife Service used them as mitigation options for ocelots in southern Texas. The information from the jaguar survey and monitoring projects provided scientifically sound data for the outreach/education contractor to use to build an education program and to develop the recovery plan. For the landowner assistance and incentives, instead of spending those funds on Mexican landowners for habitat enhancements in Mexico, we were able to gather important information about American landowner opinions and provide them with incentive programs here in the United States. 2.3 200C- Organ Pipe Cactus National Monument (ORPI) BO: Figure 4. Location Map on Conservation Action 200C Task #1: Restore 84 acres of damaged lands and invasive species management Task #2: Sonoran pronghorn water 10 Table 5. Funding Breakdown on Conservation Action 200C Budgeted Tasks Task #1: Habitat Restoration Task #2: Sonoran pronghorn water Totals Original Budgeted Amount $955,000.00 $25,000.00 $980,000.00 Actual Contract In-house Remaining Budgeted Amount Amount $980,000.00 $537,302.56 $439,739.39 $2,958.05 $0.00 $0.00 $0.00 $980,000.00 $537,302.56 $439,739.39 $0.00 $2,958.05 The tasks required under this conservation action are based on the Lukeville Biological Opinion 22410-2008-F-0011 to meet CBP mitigation requirements. Task #1 required the Park to restore 84 acres, approximately 55 miles, for the Sonoran pronghorn antelope and the lesser long-nosed bat, and Task #2 was to create and maintain three emergency water sources for the Sonoran pronghorn antelope. Due to the timing of the release of funding, the Park determined to use other funds to install the emergency water sources, those funds were used to support Task #1. The habitat restoration task took longer than expected due to a number of reasons; nevertheless, we were able to complete all the environmental reviews (issued an Environmental Assessment and signed a FONSI, and performed and completed Section 106 Archeological Surveys of the project area) to restore more than the designated 84 acres before the end of the expiration of the IAA. During the annual PMR between the park Botanist and Natural Resources Lead and the BMC, the work to be accomplished yearly and the budget needed for implementing that work was discussed and refined. The funds were expended in a number of ways: a second nursery was built on-site to handle the number of potted native plants needed for the restoration section of this conservation action. A refrigerated cooler was needed for long-term storage of the native seeds collected by NPS field crews. These same NPS field crews also controlled invasive grasses along the major roadways and around the habitat restoration sites. A water tank on a trailer was needed for watering the newly planted seedlings in the restoration sites and can be used for filling water sources, as needed. Before the end of the agreement, the Park determined that a tractor would be best use of the $28K balance from the habitat restoration contract to continue the habitat restoration on the Park. 11 2.4 200D- San Bernardino Valley Mitigation: Figure 5. Location Map on Conservation Action 200D and 200E Task #1: Restore/revegetate 49.7 acres of temporary impact areas Task #2: Restore 1.08 acres of wetlands Task #3: Construct rock/wire erosion control gabions Task #4: Control erosion and sedimentation to improve and restore aquatic/riparian habitat 12 Table 6. Funding Breakdown on Conservation Action 200D Budgeted Tasks Task #1: 49.7 acres temporary impact restoration Task #2: San Bernardino Wetland restoration Task #3: Multiple Hay Hollow Wash erosion control gabions, multiple Black Draw erosion control gabions Task #4: Control erosion/improve fish habitat Reallocation from 200B for contracting additional gabions (Task#3) Totals Original Budgeted Amount $44,730.00 Actual Budgeted Amount $37,200.02 Contract In-house $15,480.88 $21,622.44 $96.70 $54,000.00 $44,493.85 $18,390.30 $26,103.55 $0.00 $275,000.00 $307,279.54 $174,344.77 $117,934.77 $0.00 $283,750.00 $283,506.58 $283,506.58 $0.00 $0.00 $15,000.00 $0.00 $672,480.00 $491,722.53 $180,660.77 $96.70 $15,000.00 $657,480.00 $0.00 Remaining Amount The habitat restoration portion (tasks #1 and #2) of this conservation action occurred on the Refuge itself. The nearly 50 acres of temporary impact acres were restored and continue to be monitored for invasive species and reseeded until the supply of native species seeds are depleted. Four interconnected ponds were constructed and filled with water from Black Draw; these ponds replaced the impacted wetlands and are functioning as intended, as habitat for endangered fish. The erosion control gabions (Task #3) were placed throughout and adjacent to the Refuge to reduce the sediment from further impacting the watersheds on the Refuge. A map for the location of these gabions is below. 13 Figure 6. Gabion Locations on SBNWR Task #4 was collaboration between the SBNWR and the BLM Safford Field Office with the BLM project lead to oversee the implementation of aquatic/riparian improvements on private property adjacent to the Refuge and/or within the watershed. Originally the BLM was to use BLM personnel and equipment to implement the habitat improvements on private land. Unfortunately, because the funds come from CBP under the Economy Act and not the Omnibus Consolidated Appropriations Act of 1997, Section 124 (Wyden Amendment), the DOI Solicitors opinion precluded the BLM could not go forward as planned. The BMC working closely with the Safford FO project lead was able to cancel the intra-agency agreement and issue two contracts to get the work accomplished. The BLM Project lead and the SBNWR Manager worked closely with both landowners to ensure they were accepting of the work proposed, the contractor selections, and the final work accomplished. Both land owners were pleased with the outcome. Harris Environmental was the primary contractor for both projects and subcontracted the actual field work to two local small businesses. Modification 007 allowed for the reallocation of $15,000 from 200B to 200D to continue to install rock gabions on the Refuge. 14 2.5 200E- Rio Yaqui Fish Monitoring: Task #1: Inventory and monitor Rio Yaqui fish and their habitats for impacts from sedimentation Task #2: Drill two water wells and install solar-powered submersible pumps to ensure permanent water sources Task #3: Install a fish barrier in Black Draw Table 7. Funding Breakdown on Conservation Action 200E Budgeted Tasks Task #1: Inventory Rio Yaqui fish assemblage and impacts Task #2: Drill wells and install solar pumps Task #3: Install fish barrier Totals Original Budgeted Amount $86,250.00 Actual Budgeted Amount $86,250.00 Contract In-house Remaining Amount $86,250.00 $0.00 $0.00 $105,000.00 $150,210.20 $150,210.20 $0.00 $0.00 $250,000.00 $204,789.80 $142,144.3 $62,645.50 $0.00 $441,250.00 $441,250.00 $378,604.50 $62,645.50 $0.00 All the tasks under this conservation action occurred on the Refuge. For Task #1, a contract issued to University of Arizona delivered a report on the effects of sedimentation on Rio Yaqui fish. The results from this study, “Effects of Suspended Sediment on Yaqui Chub (Gila purpura),” focused on three general areas: BP Operations and sediment load, effects of suspended sediment on life stages of chub, and macroinvertebrate abundance and diversity and relationship to suspended sediment. The biologist concluded that there was no discernible impact of current BP operations on sediment concentrations within Black Draw or Hay Hollow Wash. The Total Suspended Solids, during flood conditions, reached concentrations high enough to result in mortality of eggs and fry (young, immature fish) of Yaqui Chub. There was no correlation between Total Suspended Solids and macroinvertebrate community dynamics under base flow conditions. The erosion control practices in place on the Refuge may be the reason for the reduction of sediment in Black Draw and Hay Hollow Wash. The Refuge had two wells drilled and installed solar powered submersible pumps for each to ensure a consistent water source for the Snail Spring wetland to benefit the San Bernardino Springsnail, as well as the Yaqui chub, Yaqui topminnow and Yaqui catfish. 15 The last task (#3) was to install a fish barrier in Black Draw to prevent exotic fish from downstream from entering Black Draw reach within the Refuge which is habitat for a number of Federally protected fish species. The original plan was to have a contractor design and build the fish barrier; unfortunately after a contractor provided the initial design/build, the cost far exceeded our budget. The adjustment was to use rock gabions as the main structure and add a concrete pad above and below the gabion barrier. This approach met the requirement and stayed within budget. Most of the gabion construction was done with Refuge force labor thus saving funds for the materials. 2.6 200F- Peninsular Bighorn Sheep Study: Figure 7. Location Map on Conservation Action 200F Task #1: Aerial survey and capture/collar as many adult Peninsular bighorn sheep (Ovis canadensis nelson) (PBS) as possible in three seasons (2012-2014) to monitor sheep movement patterns and demographics in the Jacumba Wilderness. 16 Table 8. Funding Breakdown on Conservation Action 200F Budgeted Tasks Original Budgeted Amount $130,950.00 $134,200.00 Actual Contract Budgeted Amount $70587.77 $70587.77 $116,839.40 $116,839.40 In-house Remaining Amount Task #1: Collars $0.00 $0.00 Task #1: Aerial $0.00 $0.00 Survey/Monitoring Task #1: Field $850.00 $5,764.83 $5,764.03 $0.00 $0.80 Equipment Realignment to $36,808.00 $36,808.00 $0.00 $0.00 200J Totals $230,000.00* $230,000.00 $229,999.20 $0.00 $0.80 *Error from PDW of $266,000.00 vice the amount provided in IAA. The aerial surveying and monitoring was more expensive than anticipated. This was a collaborative effort between the Carlsbad Fish and Wildlife Office, California Department of Fish and Wildlife and the BLM El Centro Field Office. The BLM El Centro Field Office worked to get the environmental compliance accomplished for the aerial survey and monitoring work to be done in the Jacumba Wilderness. The FWS contracted out the aerials survey work and purchased the radio collars and accessories that the CDFW used to track and monitor the collared PBS. Due to the timing of the IAA expiring (September 2015) and the aerial survey work (typically end of October and early November 2015), there was not enough time to contract and complete a fourth aerial survey under this agreement. Therefore the balance of funds, $36,808.00, was requested to be applied to the road enhancement on the Hidden Valley tract at the SDNWF Complex to support endangered species management. Modification #007 was approved and the Refuge was able to get those funds spent prior to the end of the IAA. 17 2.7 200G- Coronado National Memorial (CORO) Agave Restoration: Figure 8. Location Map on Conservation Action 200G Task #1: Complete agave restoration on 10-acre staging area Task #2: Maintain restoration in 10-acre staging area to protect young agaves form competition 18 Table 9. Funding Breakdown on Conservation Action 200G Budgeted Tasks Task #1: Complete agave restoration on 10 acres staging area Task #2: 3-5 yrs postplanting monitoring Totals Original Budgeted Amount $224,873.00 Actual Budgeted Amount $215,478.08 $50,000.00 $59,394.92 $274,873.00 Contract In-house $95,789.96 $177,895.63 $0.00 $274,873.00 $95,789.96 Remaining Amount $1,187.41 $59,394.92 $0.00 $177,895.63 $1,187.41 Over the past five years, the 10 acre construction staging area has seen major habitat restoration activity. Firstly, the Park staff have spent innumerous hours staging and planting agave seedlings with both in-house labor and with volunteers, and have hosted a number of planting events. They also transplanted 528 larger agave from the construction zone. Twelve percent of agave seedling transplants have survived since the initial planting in July 2011. The park has performed annual census data collecting to track the survival success and growth of each planting cohort since the initial July 2011 planting. To ensure successful habitat restoration of this acrea, the park has been aggressively controlling invasive plants, i.e. Lehmann lovegrass (Eragrostis lehmanniana), and Bermuda grass (Cynodon dactylon), using both in-house staff and volunteer groups. Herbivory by deer, rodents, and javelinas have been an on-going problem utilizing staff time to implement protection measures, i.e. installing cages around the agave seedlings, and spraying the seedlings with animal deterrent chemicals. Erosion control on adjacent dirt tracks and within the construction staging area has been another issue the park staff had to address. They graded the adjacent road to direct sheet flow runoff around the restoration site and the dirt track through the staging area was blocked off and erosion control measures installed. The area was seeded with native species; erosion control wattles and rock dams were placed along the dirt track to slow down the runoff and create fill areas. These practices were very effective. 19 2.8 200H- Northern Aplomado Falcon Reintroduction and Habitat Restoration: Figure 9. Location Map on Conservation Action 200H Task #1: Restoration of native grassland habitat suitable to provide breeding, feeding, and sheltering habitat requirements for northern aplomado falcons Task #2: Monitoring and telemetry of reintroduced aplomado falcons, their habitat use, movement patterns, and survival Task #3: Reintroduction of northern aplomado falcons 20 Budgeted Tasks Task #1: Grassland Habitat Restoration Task #2: Survey and Monitoring Project Management Totals Table 10. Funding Breakdown on Conservation Action 200H Original Actual Contract In-house Remaining Budgeted Budgeted Amount Amount Amount $202,266.00 $187,454.13 $187,454.13 $0.00 $0.00 $187,500.00 $109,934.00 $499,700.00 $298,431.93 $298,431.93 $13,801.08 $0.00 $0.00 $0.00 $13,801.08 $0.00 $499,687.14 $485,886.06 $13,801.08 $12.86 It was discussed with CBP and decided early on that the $37,500 funds for task #3 the reintroduction of northern aplomado falcon would be better spent on surveying and monitoring the reintroduced birds, because this task was funded from other sources. Two intra-agency agreements with the BLM Las Cruces District Office were issued. These two agreements implemented task #1 by implementing grassland habitat restoration to over 2,805 acres of shrubland. Additionally, a rigorous habitat restoration monitoring program was implemented and groundwork set-up for long-term future monitoring efforts. The surveying and monitoring of northern aplomado falcons was covered under three options: the intra-agency agreements with BLM to implement the habitat restoration also included a surveying and monitoring component; a contract with Ecosystem Management, Inc and an interagency agreement with the Army Corps of Engineers, who subcontracted to another small environmental company. Each of these groups focused on applying the same surveying and monitoring protocol to different areas in southern New Mexico. Reference the conservation action summary (Appendix 4.8) for survey results. 21 2.9 200I- Border-Wide Bat Conservation: Figure 10. Location Map on Conservation Action 200I Task #1: Find occupied endangered Mexican long-nosed and lesser long-nosed bat (Leptonycteris spp.) roosts and monitor Task #2: Monitor movement patterns of Leptonycteris bats in the Patagonia, Perilla, Animas, and Peloncillo Mountains of Arizona and New Mexico 22 Table 11. Funding Breakdown on Conservation Action 200I Budgeted Tasks Task #1: Find, protect, and monitor occupied roosts Task #2: Monitor movement patterns Reallocation from 200B Totals Original Budgeted Amount $425,000.00 Actual Budgeted Amount $804,973.29 $500,000.00 $925,000.00 Contract In-house Remaining Amount $799,714.84 $1,709.48 $3,548.97 $120,026.71 $120,026.71 $0.00 $0.00 $84,000.00 $84,000.00 $0.00 $0.00 $1,009,000.00 $1,003,759.51 $1,709.48 $3,531.01 These two tasks were split between three contracts and an interagency agreement with the Forest Service (USDA). The field office also spent time at a couple of the roosts to do roost enhancements. The findings from the four years of bat roost locating and monitoring has lead the FWS to consider down listing the lesser long-nosed bat, since there are more active, occupied bat roosts within a larger range than previously known. One of the three contracts monitored the movement patterns (Task #2) at 19 roosts in Arizona. The information gleaned from this monitoring effort and the video recordings of the behaviors provided the biologists with information as to what the best or functional roost protections (i.e. gates) would be ideal to install. The interagency agreement with the Forest Service provided funding to close or gate roads leading to roosts at risk and to purchase the materials for installation of roost gates on Forest Service lands. The other two contracts focused on locating new occupied roosts in NM and AZ, resulting in 30 new roosts located and 5 historically know roosts verified as occupied. 23 2.10 200J – California Land Acquisition: Figure 11. Location Map on Conservation Action 200J Task #1: Purchase occupied or suitable habitat for Arroyo Toad, Quino Checkerspot Butterfly and Coastal California Gnatcatcher. Table 12. Funding Breakdown on Conservation Action 200J Budgeted Tasks Land Acquisition Totals Original Budgeted Amount $8,000,000.00 $8,000,000.00 Actual Budgeted Contract Amount $8,000,000.00 $8,000,000.00 $8,000,000.00 $8,000,000.00 Remaining Amount $0.00 $0.00 The San Diego National Wildlife Refuge working closely with SADAG and other nongovernment organizations purchased collectively over 1,000 acres in Hidden Valley within the SDNWR Approved Acquisition Boundary. The funds provided by CBP purchased 762.44 of those acres (see Figure 12). 24 Figure 12. Hidden Valley Acquisition To meet the intent of conservation action 200F, the excess funds from the original budget, approximately $36,808 was used for road improvements to reach parts of Hidden Valley property thus allowing biologists to access endangered species habitat. The Refuge Manager was able to get a contract under award and the road enhancements done prior to the end of the IAA period of performance utilizing all the remaining funds. This reallocation of funds was modification #007. 25 2.11 200K- Texas Land Acquisition: Figure 12. Location Map on Conservation Action 200K Task #1: Purchase of at least 500 acres acres of suitable habitat for jagaurundi and ocelots within the approved acquisition boundary of Lower Rio Grande Valley National Wildlife Refuge within the Approved Acquisition Boundary. Table 13. Funding Breakdown on Conservation Action 200K Budgeted Tasks Land Acquisition Ocelot Survey -Equipment Ocelot Survey - Labor Totals Original Budgeted Amount 3,000,000.00 $3,000,000.00 Actual Contract Budgeted Amount $2,889,629.00 $2,889,629.00 In-house Remaining Amount $0.00 $0.00 $98,401.80 $98,401.80 $0.00 $0.00 $11,969.20 $0.00 $11,969.20 $0.00 $3,000,000.00 $2,988,030.80 $11,969.20 $0.00 26 The RO Realty Office purchased over a 1,000 acres of the “Hunke” Property adjacent to the Lower Rio Grande NWR Complex in southern Texas. This exceeded the “at least” 500 acres as required in the Project Decsiption Worksheet for this conservation action. After discussion at the August 2014 CBP briefing, it was decided the balance of the unspent funds ($110,371.00) could be spend on ocelot surveys in southern Texas to support this conservation action, because ocelots was one of the species benefitting from the land purchase. The balance of the land purcase funds were assigned a new accounting number and provided to the ocelot recovery lead biologist. He was able to purcase a number of game cameras and radio collars to locate, and track ocelots, and utilized volunteers to deploy the cameras and download the inforamtion from both the cameras and the collars. It was accepted that bobcats would be a viable surragote to the ocelots as they were present in the study area in higher numbers and easier to trap and collar. The bobcats also behaved similarly to the ocelots regarding CBP operations and activities along the border tactical infrastructure. 27 3.0 STATUS OF PROGRAM FUNDING This section highlights the funding distribution by conservation action in relationship to the overall program. Table 14. Funding Breakdown on Initial IAA Budget Category In-house Labor Travel Contracts Agreements Supplies/Materials TOTAL Amount $804,677.57 $42,136.49 $3,189,036.11 $1,740,580.21 $1,036,372.62 $6,812,803.00 Figure 13. Funding Breakdown on Initial IAA Budget Funding Breakdown on Initial IAA 15% 12% 1% In-house Labor Travel Contracts 25% Agreements 47% 28 Supplies/Materials Table 15. Funding Breakdown on Final IAA Budget Category In-house Labor Travel Contracts Agreements Supplies/Materials Land Acq CA Land Acq TX TOTAL Amount $816,646.77 $42,136.49 $3,189,036.11 $1,740,580.21 $1,036,372.62 $8,000,000.00 $2,988,030.80 $17,812,803.00 Figure 14. Funding Breakdown on Final IAA Budget Funding Breakdown on Final IAA 0% In-house Labor 4% 17% 18% Travel Contracts 10% Agreements Supplies/Materials 45% 6% Land Acq CA Land Acq TX 29 Table 16. Amount of Funding by Contract and In-House Spent 200A 200B 200C 200D 200E 200F 200G 200H 200I 200J 200K Contract $5,232,670.86 $141,174.32 $1,868,431.62 $ 537,302.56 $ 491,722.53 $ 378,604.50 $ 229,999.80 $ 95,789.96 $ 85,886.06 $1,003,759.51 $8,000,000.00 $2,988,030.80 In-house $1,582,344.39 $ 554,324.84 $ 151,567.70 $ 439,739.39 $ 180,660.77 $ 62,645.50 $ 0.00 $ 177,895.63 $ 13,801.08 $ 1,709.48 $ 0.00 $11,969.20 Balance $ 7,788.35 $ 0.84 $ 0.68 $ 2,958.05 $ 96.70 $ 0.00 $ 0.80 $ 1,187.41 $ 12.86 $ 3,531.01 $ 0.00 $ 0.00 Initial Budget $ 6,812,803.00 $ 695,500.00 $ 2,020,000.00 $ 980,000.00 $ 672,480.00 $ 441,250.00 $ 230,000.60 $ 274,873.00 $ 499,700.00 $ 1,009,000.00 $ 8,000,000.00 $ 3,000,000.00 Figure 15. Percentages of Contract and In-House Spent Percent of Contract and In-House 0% 23% Contract In-house Balance 77% 30 Figure 16. Percentages of Contract and In-House by Conservation Action % Spent by Contract or In-House 100% % Spent 90% 80% %In-house 70% %Contract 60% 50% 40% Target 40% 30% 20% 10% 0% 200A 200B 200C 200D 200E 200F 200G 200H 200I Conservation Action 31 TOTAL 4.0 APPENDICES 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10 4.11 200A Border Mitigation Coordinator 200B Jaguar/Sasabe BO 200C Organ Pipe Cactus NM/Lukeville BO 200D San Bernardino Valley Mitigation 200E Rio Yaqui Fish Studies 200F Peninsular Bighorn Sheep Study 200G Agave Restoration 200H Northern Aplomado Falcon Reintroduction and Habitat Restoration 200I Border-wide Bats 200J California Land Acquisition (SDNWR Complex) 200K Texas Land Acquisition (LRGNWR Complex)/TX Wildcat Monitoring 32