Aspen Water Future Work Plan - Working Draft Item Estimated Start Date Estimated End Date Duration Public Outreach 7/1/2017 2/1/2018 215 Implementation of Reuse System 10/31/2016 4/1/2018 517 Groundwater System Strategy 10/31/2016 12/31/2017 426 Investigation of mine water/storage potential 1/27/2017 7/31/2017 185 Investigation of in-situ storage 3/27/2017 7/31/2017 126 Conservation programs 10/31/2016 6/30/2018 607 Collaborate with WRA, WW and others on conservation, reuse, agricultural transfers and other alternatives 5/1/2017 12/31/2017 244 Update climate change models 5/1/2017 12/31/2017 244 Update Streamflow and Demand Projections 3/6/2017 12/31/2017 300 Studies in support of public process 7/1/2017 12/31/2017 183 Present recommendations of public process to City Council 2/1/2018 4/1/2018 59 Additional studies as required to respond to City Council direction 4/1/2018 6/30/2018 90 10/30/2016 2/7/2017 5/18/2017 Consultant TBD Carollo HRS Deere and Ault Deere and Ault Element, others TBD TBD TBD Headwaters Corp. TBD TBD 8/26/2017 12/4/2017 3/14/2018 6/22/2018 Public Outreach Implementation of Reuse System Groundwater System Strategy Investigation of mine water/storage potential Investigation of in-situ storage Conservation programs On Going Effort Collaborate with WRA, WW and others on conservation, reuse, agricultural transfers and other alternatives Update climate change models Update Streamflow and Demand Projections Studies in support of public process Present recommendations of public process to City Council Additional studies as required to respond to City Council direction Timeframe TBD