Administrator From: James Reilly Sent: Friday, July 12, 2013 10:51 AM To: Jon Clay; Ralph Leslie; Steve Haemmerle; Richard Oldshue Subject: Cash Flow Issues There is a somewhat complicated series of cash ?ow issues that we need to get a handle on between the City, MPEA and with regard to the in Tiff funds that will come from the City to MPEA to reimburse MPEA for the purchase of land forthe headquarters hotel and the event center which in turn will enable MPEA to grant to NPI for its reconstruotion project. I don?t have any doubt that this can be worked out. As a ?rst step, it might be helpful to Richard and ion to collaborate on something that shows side by side the City?s plan for timing on the TIF funds flowing to MPEA, construction spending schedule and NPl?s construction spending schedule. Once we have that homework done we can meet and ?gure out how to manage any problems that the dates and numbers might show.