Plateau Remediation Contract Section Contract No. Attachment J.4-2017, Modi?cation No. 544 ATTACHMENT J.4 PERFORMANCE EVALUATION AND MEASUREMENT PLAN (PEMP) Fiscal Year 2017 Performance Evaluation and Measurement Plan For Plateau Remediation Company Performance Period: October 1, 2016, through September 30, 2017 J.4-1 Plateau Remediation Contract Section Contract No. DE-ACOS-OBRL 14788 Attachment J.4-2017, Modification No. 544 Allocated Available Fee: $51,057,421 Objective: Demolish Plutonium Finishing Plant (PFP) complex facilities to slab?on?grade and stabilize the site for surveillance and maintenance. Complete demolition of PFP facilities to slab-on-grade and stabilize the site for surveillance and maintenance. Fee is reduced in a linear declining method from $51,057,421 to $43,450,000 for each day from January 9, 2015, to June 30, 2016; and fee is then reduced in a linear declining method from $43,350,000 to $30,000,000 for each day from June 30, 2016, to May 31, 2018; and finally fee is reduced in a linear declining method from $30,000,000 to $12,000,000 for each day from May 31, 2018, to September 30, 2018. The linear declining method is defined in the following table: Date Available Fee Fee Reduction Davs ReductionlDay Start of Curve (after 100 day adj) 119/201 5 $51,057,421 (7,607,421) 538 (14,140) Step 1 0f Curve 6/30/2016 $43,450,000 $(13,450,000) 700 (19,214) Step 2 0f Curve 5/31/2018 $30,000,000 {ii $(147,541) End of Curve 9/30/2015" $112,000,000 I Any portion of Provisional Fee, as defined by Clause Fee Structure, paragraph may become earned through a final fee determination as defined by Clause 8.8, Fee Determination and Payment, paragraph Conversion of fee from Provisional to earned is at the unilateral discretion of the Fee Determining Official. On an annual basis no more than $3,000,000 in Provisional Fee may be converted to earned fee at the final fee determination, as defined by Clause 8.8, Fee Determination and Payment, paragraph Allocated Available Fee not earned at the end of the multi-year performance period is unavailable in accordance with Clause B.7, Fee Structure, paragraph Completion Criteria: Complete execution of Alternative 4 in approved EECA Achieve the PFP Complex slab-on-grade end point criteria in Handle, package, label, store, and ship waste low-level, low-level mixed, RU mixed wastes) out of the PFP facilities for treatment or disposal. Waste shipments completed in accordance with the Hanford waste shipping criteria, other waste site criteria, and in compliance with applicable state and federal regulations for treatment and disposal at an approved facility. Complete turnover of the PFP site for surveillance and maintenance.