Attachment #5 SCHEDULE OF PRICES - PRICE SUMMARY FORM (Rev 2) I: BASE CONTRACT Big EL Description of Item M92 1, 10 Streetcars 4,475,130 44,751,300 2. Lump Sum System Support (from Total - Schedule A) 4 438 095 3. Lump Sum Allowance for Spare Parts, Special Tools and Test Equipment 3 000 000 4- Total Base Contract Price (Sum Section I, Items No. 1- 3) l OPTIONS Option Unit Price Description of Item Before Escalation 1, 1 1O Streetcar, ordered 6 18 months after NTP 4 551 813 1 2 2_ per order Streetcar, ordered 18 36 months after NTP 3 5 3_ per order Streetcar, ordered 18 36 months after NTP 5,341,251 6 1O 4_ per order Streetcar, ordered 18 36 months after NTP RFP N0. TRN-3681 BASIS FOR PRICE PROPOSAL EVALUATION Total Base Contract Price 1' Equal to line 4 from Table above 2. Weighted Price for Option Streetcars Equal to the sum of Unit Prices in lines 1,2, 3 and 4 from Table II above 3. Weighted Price for Optional Spare Parts, Special Tools and Test Equipment Equal to two (2) times the Total from Schedule B, Spare Parts, Special Tools and Test Equipment 52,189,395 21,480,571 5,801,786 Basis for Price Proposal Evaluation Sum of Lines 1, 2 and 3 above 79,471,752 RFP N0.