PUBLIC SERVICE C O ~ ~ I S S I O N OF WEST VIRGINIA CHARLESTON At a session of the PUBLIC SERVICE COMMISSION OF WEST V RGINIA n the City of Charleston on the 27thday of October 2017. CASE NO. 17-0036-E-CS ESC HARRISON COUNTY POWER, LLC, Application for a Siting Certificate to authorize the construction and operation of a wholesale electric generating facility in Harrison County, West Virginia. COMMISSION ORDER GRANTING A SITING CERTIFICATE FOR A WHOLESALE ELECTRIC GENERATING FACILITY IN HARRISON COUNTY, WEST VIRGINIA Based upon its thorough review of the evidence, the public support shown for the proposed natural gas-fired electric generating facility, and the benefits that the project will provide to the State and Harrison County, the Commission approves the application filed by ESC Harrison County Power, LLC (ESC Harrison County Power) for a siting certificate to construct and operate a natural gas-fired wholesale electric generating facility of approximately 630 megawatts (MW) in Harrison County including an approximate 1.%mile 138 kV (less than 200,000 volts) related transmission support line, associated interconnection facilities, and other necessary appurtenances. I. PROJECT DESCRIPTION -On January 17, 2017, ESC Harrison County Power’ filed an application for a Siting Certificate (Application)’ pursuant to W.Va. Code §§24-2-1(d)(2) and 24-2-1 IC to authorize the construction and operation of a natural gas-fired base load combined cycle wholesale electric generating facility of approximately 630 MW (Facility or Project) approximately 0.5 miles from the municipal boundary of Clarksburg, in Harrison County, including an approximately 1.8-mile 138 kV (less than 200,000 volts) related transmission support line, associated interconnection facilities, and other necessary 1 ESC Harrison County Power, a Delaware limited liability company, is authorized to do business in West Virginia. 2 ESC Harrison County Power’s Application consisted of two large volumes, including an Appendix, multiple Exhibits, tables, figures and other documents. The Application was filed pursuant to the Commission Rules Governing Siting Certificates for Exempt Wholesale Generators (Siting Rules), 150 C.S.R. Series 30. appurtenances as more particularly described in the Application. Upon completion, the Facility will be used to generate electricity for sale in the competitive wholesale market. ESC Harrison County Power stated that the Facility will have a nominal nameplate capacity of approximately 580 MW (up to approximately 630 MW under favorable conditions), utilizing state-of-the-art clean-burning natural gas-fueled electric generating equipment consisting of one combustion turbine (CT), one steam turbine (ST), and one generator. The exhaust from the CT will be directed through one heat recovery steam generator (HRSG) that utilizes exhaust heat from the CT to generate high-quality, superheated steam to drive the ST. Application at 2. The CT and ST through a single shaft arrangement turn a common generator generating electricity which ESC Harrison County Power asserts is an efficient and environmentally friendly system, The Facility will receive natural gas fuel through existing Equitrans, L.P. (Equitrans) facilities and the construction of a lateral extending from the FERC regulated pipeline owned and operated by Equitrans’ interstate pipeline. Application Appendix3 at 10. ESC Harrison County Power has negotiated a construction and gas transportation agreement and has submitted a bid for service in an Equitrans open season for firm transportation capacity on the Equitrans system that will allow ESC Harrison County Power to purchase gas from various sellers on Equitrans and other interconnected systems. Under the terms of the agreement, Equitrans has been acquiring the rights-ofway necessary to construct a pipeline extension approximately 5.5 miles to the Facility’s location (Pipeline Extension). Application Appendix at IO; Applicant EX.^ AWD-D at 5-6; Applicant Ex. AWD-R at 5-6; July 11, 2017 Hearing Transcript (hereinafier “Tr.”) at 56-57. Equitrans plans to construct and operate the Pipeline Extension and obtain all applicable permits and permissions. Equitrans is an interstate pipeline regulated by the Federal Energy Regulatory Commission (FERC) under Section 7(c) of the Natural Gas Act of 1938. The Pipeline Extension would be constructed and operated as a prior notice project under Equitrans’ existing blanket certificate authority. Application Appendix at 10; Applicant Ex. A m - D at 6; Applicant Ex. AWD-R at 2. ESC Harrison County Power has evaluated available alternatives and has determined that the expansion of the Equitrans system to the Facility is the most economic option for the Facility to obtain secure, reliable and economically competitive 3 The Application Appendix is Attachment 3 to the Application and is a more complete description of the Application. 4 References to the pre-filed direct and rebuttal testimonies are cited to the page number of those testimonies and the exhibit identification that appears in the evidentiary transcript. 2 natural gas to allow the Facility to be successfully financed, built and operated. ESC Harrison County Power expects to enter into a transportation service agreement for firm transportation capacity on the existing Equitrans mainline system and the Pipeline Expansion at a rate which reasonably meets the plant objectives. Application Appendix at 10. The Facility will utilize the Clarksburg Water Board (CWB) as a source for cooling and potable water and will discharge cooling water blowdown and other contact and non-contact water to the Clarksburg Sanitary Board (CSB) system. Stormwater will ccntinue to be discharged into an unnamed tributary of Elk Creek. Project stormwater controls will reduce the current uncontrolled releases from the property. Application Appendix at 10, 66; Applicant Ex. MF-D at 7, 10; Applicant Ex. JPB-D at 5, 35. The power generated by the Facility will be delivered to the existing Mon Power Glen Falls substation (Glen Falls Substation), located approximately 1.8 miles from the Facility, via a transmission line of approximately 9,600 linear feet in length. Application at 2; Application Appendix at 9. The Facility site (Site) is in an unincorporated area of Harrison County, north of U.S. Route 50, which was formerly the site of the Pinnickinnick Coal Company, and subsequently was transferred to the Clarksburg Fuel Company and the Consolidation Coal Company. Application at 2. ESC Harrison County Power controls approximately 110 acres of the larger 212-acre parcel through a purchase option agreement with Harrison County Development Authority; however, after construction, the Facility will occupy a footprint of only about thirteen acres, leaving additional acreage available inside the boundaries of the 110-acre property for further commercial and industrial development. Application Appendix at 5. The Site is a portion of a formerly active surface coal mine and underground coal mine, and the Facility location on the Site was selected to allow for the redevelopment of an unused former strip-mined area. Application Appendix at 6. The thirteen-acre Site and surrounding areas have been investigated, and there are no known adverse environmental conditions that pose limitations on the development of the Site or construction of the Facility (the Site and Facility being sometimes referred to collectively as the Project). ESC Harrison County Power chose the Site for numerous reasons. The Site is in close proximity to electric transmission lines, and has abundant natural gas readily available and in close proximity to the site with redundant supply sources and transportation options. The Project will have very little adverse impact, and likely a positive impact, to the Site’s existing conditions, and will cause minimal change to the viewshed and existing noise levels for the nearby residents. There is a trained and 3 qualified local labor pool that has the requisite skills to construct and complete the Project. Application Appendix at 6-7; Applicant Ex. JPB-D at 18-19. ESC Harrison County Power asserted that neither the Facility nor the transmission line are utilities providing service to the public, and there will be no impact to West Virginia ratepayers as a result of the construction of the Facility. ESC Harrison County Power further asserted that it will be the entity responsible for the construction and operation of the Facility and for the sale of electricity generated by the Facility and will operate the Facility as an exempt wholesale generator as defined under Section 32(a) of the Public Utility Holding Company Act of 1935. Application Form 25 at 2; Application at 3. ESC Harrison County Power estimated that it will cost approximately $615 million to construct the Facility and the transmission line. Application Form 2 at 2. ESC Harrison County Power stated that the Project funding will be a combination of equity and term loan A financing. Debt to equity is anticipated at approximately fiftyseven percent to forty-three percent. ESC Harrison County Power has entered into a Payment in lieu of Taxes agreement (PILOT) with the Harrison County Board of Education (HCBOE) and the Harrison County Commission (HCC). Under the PILOT Agreement, ESC Harrison County Power will be exempt from ad valorem property tax for thirty years and will make payments in lieu of taxes for proportional distribution to HCBOE and HCC of at least $2,634,162 during a 30-year term. Application Appendix at 68-70; Application Appendix Ex. 20; Applicant Ex. MJD-D at 2-5. ESC Harrison County Power has also entered into a Lease Agreement with the HCC, and ESC Harrison County Power will make annual lease payments over a period of thirty years totaling no less than $23,707,460 under the basic rent schedule,6 along with an upfront payment of $1,000,000, resulting in a total rent agreement package of at least $24,707,460. Harrison County does not collect ad valorem taxes on the Site because it is owned currently by the HCC. Application Appendix at 69-70; Application Exhibit A; Applicant Ex. MJD-D at 4-7. The HCC has been awarded a grant of $400,000 under the West Virginia Industrial Access Road Program grant (EAR grant) for the design and construction of the proposed industrial access road to the Site and the HCC’s property for further development. ESC Harrison County Power is contributing $150,000 for the necessary 5 Application Form 2 is the Notice of Filing that was published in the Exponent Telegram on January 24,201 7, gnd the Charleston Gazette Mail on January 25,20 17. 6 The basic PILOT amount and the lease amount rent schedule provide for annual increases of a minimum of 2.5 percent; however, if the CPI exceeds 2.5 percent in any year, then the higher CPI amount will be applicable for that year. 4 matching funds for the grant and will also fund the additional amount needed (estimated to be $480,000) of the total road cost of an estimated $1,030,000. Tr. at 21-22; Applicant Hearing Ex. 3; Applicant Ex. JPB-R at 8. Tom S . Witt, Ph.D., testified for ESC Harrison County Power that the construction and operation of the Facility will have a significant economic impact on the West Virginia economy. The total Project construction costs are estimated at $616.1 million with West Virginia workers and firms providing approximately forty-five percent of all construction costs. Applicant Ex. TSW-D at 3. Additionally, third-party construction of gas interconnections is expected to cost $15 million. Id. Dr. Witt estimated, based on 2016 dollars, that the three-year construction period impacts would result in 2,543 job years, $187.4 million in employee compensation, and $306.3 million in value added. Id. at 4. The first full year of operation impacts would result in 713 full- and part-time jobs (including thirty at the plant), $47.9 million in employee compensation, and $72.8 million in value added. Id. at 6. Dr. Witt estimated that $1 11 million per year of natural gas would be sourced through long-term fuel agreements. Id. at 5. The total economic impact of the Project for West Virginia is calculated to be more than $880 million during construction and $287.4 million annually during operation. Id.at 5-6. 11. PROCEDURAL HISTORY Initial Public Notice and Comment Letters ESC Harrison County Power published the Notice of Filing of its Application on January 24, 2017, in The Exponent-Telegram (Harrison County), and on January 25, 20 17, in The Charleston Gazette (Kanawha County). Affidavits of Publication (filed Feb. 6,2017 and Feb. 13,2017). The Commission received 545 letters and postcards in support of the Project, including letters from the Harrison County Chamber of Commerce; Martin Howe, City Manager of Clarksburg; Jamie Metz, Executive Director, Harrison County Economic Development Corporation; Tim Miley, Minority Leader of the West Virginia House of Delegates; the West Virginia Oil and Natural Gas Association; and Senators Mike Romano and Doug Facemire. No letters or comments in opposition to the Project were filed except one protest from Intervenor Ohio Valley Jobs Alliance (OVJA). After intervening (see below), OVJA voluntarily withdrew from the case on July 3, 2017. See case file generally. Waiver of Certain FilinP Requirements On April 19, 2017, the Commission granted ESC Harrison County Power a request for a waiver of certain certificate application filing and informational requirements. Because Commission jurisdiction, particularly as it relates to rates is 5 limited regarding the operations of the Project, the Commission did not require ESC Harrison County Power to file information that relates to the traditional public utility model under which the Commission examines extensive financial infoAation to establish rates for service based on the cost to the utility to provide that service. Commission Order at 3 (April 19, 2017). Interventions On March 30,20 17, the Commission granted the petitions to intervene of the West Virginia State Building and Construction Trades Council, AFL-CIO (Building Trades) and OVJA. Id.at 6, 8. Motions for Protective Treatment Siting Rule 3.1.1.2 requires applicants to file certain financial statements for each year of the start-up phase and for the first five years of operation, and these financial statements must disclose all assumptions. On January 17, 2017, ESC Harrison County Power filed a redacted public version of the required financial data along with a confidential version of the same under seal, and filed a Motion for Protective Order and supporting affidavit. Because no request under the \Nv Freedom of Information Act (WV FOIA) had been filed for the information for which ESC Harrison County Power requested permanent protective treatment, the Commission deferred ruling on the Motion for Protective Order. Cornmission Order at 6-7 (March 30,2017). On May 25, 2017, OVJA filed its membership list in response to Staffs second set of data requests. OVJA filed the membership list under seal and also filed a Motion for Protective Order requesting that the membership list receive permanent protective treatment. The Commission deferred ruling on the Motion for Protective Order until the filing and review of a request under WV FOIA. Commission Order at 4 (June 2,20 17). View by the Commission On June 6, 2017, the Commission conducted a tour (View) of the project area with representatives of Cornmission Staff, Building Trades, OVJA and ESC Harrison County Power. The View began at 2:OO p.m. at Minard’s Restaurant in Clarksburg and lasted spproximately two hours, with stops at these Viewpoints: 1. 2. 3. 4. 5. 6. Pinnickinnick Street Entrance ESC Harrison County Power Proposed Plant Site Henry Ford Avenue Tibbs Avenue Free Will Baptist Church Harrison Recycling Center 6 7. 8. Glen Falls Substation Elkview Masonic and Holy Cross Cemeteries At each Viewpoint, the parties briefly described the viewpoint (Le. looking toward Clarksburg, looking toward the Facility, etc.), the relative elevations of the viewing location and the Facility, and where the Facility would be located in relation to the viewpoint. At the Plant Site, the proposed locations of the various pieces of equipment and buildings that constitute the Facility were shown on maps and drawings. The Commission and others present asked clarieing questions about the Viewpoints, but none of the questions addressed the merits of the Project. A court reporter was not present during the View, and the Commission traveled in a separate vehicle from the parties. Public Comment Hearing ESC Harrison County Power published notice of the public comment hearing on May 23, 2017, in both The Exponent-Telegram (Harrison County), and The Charleston Gazette (Kanawha County). Affidavits of Publication (Filed June 2, 2017 and June 13, 20 17). After the View, the Commission conducted a public comment hearing at 6:OO p.m., June 6, 2017, at the Harrison County Recreation Complex/4-H Center in Clarksburg, West Virginia. Six individuals spoke in support of the Project. Mr. William Parker, the Harrison County Administrator, spoke in favor of the project on behalf of the Harrison County Commission and Harrison County Development Authority. June 6, 20 17 Public Comment Hearing Transcript at 11- 12. Ms. Anne Blankenship, Executive Director of the West Virginia Oil and Natural Gas Association, spoke in favor of the many skilled construction jobs and many direct and indirect jobs that would flow from the Project. Id. at 13-15. Ms. Natalie Stone of the North Central Building and Construction Trades Council, AFL-CIO (North Central Building Trades) spoke on behalf of many members of the North Central Building Trades present at the hearing. Id. at 15-16. Mr. Sean Currey, of the Ironworkers Local 549, spoke on behalf of the Project and related his positive experience on a similar project recently completed in Ohio. Id.at 17-18. Mr. Charlie Ritter, a member of Carpenters Local 436, spoke on behalf of the project and the local jobs and clean energy it would produce. Id.at 19. Mr. Jamie Metz, Executive Director of Harrison County Economic Development Corporation, and Mr. Rob Hinerman also spoke in favor of the project. Id.at 23 and 19-20. Two persons spoke in opposition to the Project. Mr. Stephen McElroy of Bridgeport, West Virginia, questioned the ability of the project to comply with environmental regulations. Id.at 20-22. Mr. James Kotcon, Chair of the West Virginia Chapter of the Sierra Club, indicated that the Sierra Club opposed the project because of 7 its concern about the significant environmental impacts from release of greenhouse gases. Id. at 24-26. Pre-filed Testimony On Mardh 31, 2017, ESC Harrison County Power pre-filed the Direct Testimony of its witnesses: 1. 2. 3. 4. 5. 6. 7. John P. Black - sponsor of application and all technical aspects including engineering, contracting, regulatory, and permitting (Applicant Ex. JPB-D); Andrew W. Dorn, IV - qualification of ESC Harrison County Power to complete the Prqject and natural gas supply and transportation for the Project (Applicant Ex. AWD-D); Matthew J. Dorn, CPA - Project financing, PILOT and lease agreement with Harrison County Commission and economic impact (Applicant Ex. MJD-D); Timothy Kirk, P.E. -traffic report (Applicant Ex. TK-D); Carol Colby - noise study and report (Applicant Ex. CC-D); Toin S. Witt, Ph.D. - economic impact and report (Applicant Ex. TSW-D); and Matthew Fluharty, P.E. - engineering, viewshed, hydrology, SHPO, public water and sewer required (Applicant Ex. MF-D). On May 25, 2017, the Building Trades pre-filed the Direct Testimony of its witnesses: 1. 2. Steve White - local worker impact and Memorandum Agreement with ESC Harrison County Power (Building Trades Ex. SW-D); and Michael Jin - Project economic impacts on workforce (IMPLAN study) (Building Trades Ex. MJ-D). On May 26, 20 17, OVJA pre-filed the Direct Testimony of its witnesses: 1. 2. 3. 4. Emily Virginia Rockwell - concerns about Project including air emissions (OVJA EX.EVR-D); James Russel Thomas - OVJA and its concern about air emissions (OVJA EX.JRT-D); Stephen Baker McElroy - concerns about Project including air emissions (OVJA Ex. SBM-D); and Jon A. Pollack - review of application and air emissions requirements (OVJA EX.JAP-D). 8 On May 26, 20 17, the Staff pre-filed the Direct Testimony of its witnesses: 1. 2. 3. Josh Allen - financial review, economic impact and decommissioning (Staff Ex. JA-D); Eric F. deGruyter - natural gas issues (Staff Ex. EFDG-D); and Donald E. Walker - engineering and technical review and recommended conditions of any Siting Certificate (Staff Ex. DEW-D). On June 30, 2017, ESC Harrison County Power pre-filed the Rebuttal Testimony for three witnesses: 1. 2. 3. John P. Black, P.E. - responding to OVJA witness Pollack and certain Staff recommendations and conditions and providing certain clarifications (Applicant Ex. JPB-R); Andrew W. Dorn, IV - the natural gas arrangements for the Facility and responding to certain Staff recommendations and conditions (Applicant Ex. AWD-R); and William Hanna, P.E. - responding to testimony of OVJA witness Pollack regarding air permit (Applicant Ex. WH-R). OVJA Voluntary Withdrawal On July 3, 2017, OVJA filed a Notice of Voluntary Withdrawal (Without Adjudication) of Intervenor Ohio Valley Jobs Alliance’s Claims pursuant to the terms of a Joint Stipulation and Settlement of all four parties to this proceeding, filed on the same aot0 On July 6, 20 17, the Commission granted OVJA’s motion for voluntary withdrawal as a party to the case. Commission Order at 2-3 (July 6, 2017). UULCI. Joint Stipulation with OVJA On July 3, 2017, OVJA, including its unincorporated chapter known as North Central West Virginia Jobs Alliance, ESC Harrison County Power, Staff, and the Building Trades filed a Joint Stipulation and Agreement for Settlement of Ohio Valley Jobs Alliance’s Claims (OVJA Joint Stipulation). The OVJA Joint Stipulation proposed and recommended to the Commission as a full and complete resolution of all of the issues raised by OVJA in this proceeding that, as a condition of any Siting Certificate which may be issued in this case, ESC Harrison County Power should be required to obtain and file proof of having obtained an Air Quality Permit from the West Virginia Division of Air Quality. The OVJA Joint Stipulation was entered into the record as Joint Exhibit 2 at the July 1I, 2017 hearing. Tr. at 32. 9 Joint Stipulation and Agreement for Settlement On July 6, 201 7, ESC Harrison County Power, Staff and Building Trades filed a Joint Stipulation and Agreement for Settlement (Joint Stipulation), in which they recommended the Cornmission grant ESC Harrison County Power a siting certificate, subject to certain conditions. Joint Ex. 1; Tr. at 3 1. They recommended the text for the proposed conditions and asked the Commission to approve the Memorandum Agreement between ESC Harrison County Power, the North Central Building Trades, and the Building Trades that was admitted into the record of this case as Building Trades Hearing Ex. 1. Joint Ex. 1; Tr. at 46-48. Evidentiary Hearing On May 23, 20 17, ESC Harrison County Power published notice in The Exponent(Harrison County) and in The Charleston Gazette (Kanawha County) of the Telegram evidentiary hearing that would begin on July 1 1, 201 7. Affidavits of Publication (filed June 2,2017 and June 13,2017). The evidentiary hearing was concluded in one day. The parties elected not to file briefs and agreed to file a proposed Order. Tr. at 62. A proposed Order was filed with the Commission on September 29, 2017. In this case, the Commission has conducted a View of the Project area, and reviewed the two-volume Siting Certificate application and nineteen pre-filed direct and rebuttal testimonies and exhibits consisting of more than 500 pages of record evidence. The Commission also conducted a public hearing that resulted in a twenty-nine page transcript and an evidentiary hearing that resulted in a sixty-three page transcript and hundreds of pages of exhibits. 111. DISCUSSION OF ISSUES AND EVIDENCE A. Statutory and RePulatory Tests W.Va. Code 524-2-1 lc(c) provides: In deciding whether to issue, refuse to issue, or issue in part or refke to issue in part a siting certificate, the commission shall appraise and balance the interests of the public, the general interests of the state and local economy, and the interests of the applicant. The commission may issue a siting certificate only if it determines that the terms and conditions of any public funding or any agreement relating to the abatement of property taxes do not offend the public interest, and the construction of the facility or material modification of the facility will result in a substantial positive 10 impact on the local economy and local employment. The commission shall issue an order that includes appropriate findings of fact and conclusions of law that address each factor specified in this subsection. All material terms, conditions and limitations applicable to the construction and operation of the proposed facility or material modification of the facility shall be specifically set forth in the commission order. The Commission views the statute as setting forth a two-part balancing test more fully explained on page 114 of our August 27, 2004 order that partially and conditionally approved a coal-fired electric wholesale generation facility in Longview Power LLC, Case No. 03- 1860-E-CS: In Part One of the analysis, the Cornmission will perform its duty to appraise and balance: (a) an applicant’s interest to construct an electric wholesale generation facility; (b) the State’s and region’s need for new electrical generating plants; and (c) the economic gain to the State and the local economy, against: (i) community residents’ interest in living separate and apart from such facility; (ii) a community’s interest that a facility’s negative impacts be as minimally disruptive to existing property uses as is reasonably possible; and (iii) the social and environmental impacts of the proposed facility on the local vicinity, the surrounding region, and the State. The Commission performs Part Two of its analysis only if it determines in Part One that, taken as a whole, positive impacts relating to the various interests outweigh the negative impacts on the various interests. (See W.Va. Code 524-2- 11c(c)) In Part Two the Commission decides whether a project’s public funding, if any, and property tax abatement, if any, offends the public interest. (W.Va. Code 524-2- 1 1c(c)). See, Longview’Power, LLC, Case Nos. 03- 1860-E-CS & 05- 1467-E-CN (Commission Order at 102, June 26, 2006) (granting final approval of electric wholesale generating facility and transmission line, with conditions); Beech Ridge Energy LLC, Case No. 051590-E-CS (Cominission Order at 75, Aug. 28, 2006) (granting approval of electric wholesale generating facility and transmission line, with conditions); Beech Ridge Energy I1 LLC’, Case No. 12-1196-E-CS (Commission Order at 10-1 1, June 19, 2013) (granting approval of electric wholesale generating facility, with conditions). Within the second half of Part One, the Commission considers issues such as the project’s impacts on viewshed, wildlife, ambient sound levels, and water resources. AES Laurel Mountain LLC, Case No. 08-0109-E-CS (Commission Order at p. 9, November 26, 2008); AES New Creek LLC, Case No. 08-2105-E-CS (Commission Order at p. 9, September 30,2009). 11 B. 1. The Application of Part One of the Balancing Test The Interests of ESC Harrison County Power to Construct the Project ESC Harrison County Power has assembled a team of highly experienced and diverse professionals to thoroughly study and develop this Project. ESC Harrison County Power has secured an appropriate site for the Facility in an area where there will be a shortage of electric supply resulting from planned retirement of existing, mostly obsolete, coal fired plants in West Virginia and substantial retirement of plants throughout PJM. Application Appendix at 4-5, 19. ESC Harrison County Power has successfully completed the PJM feasibility study and the system impact study. Application Appendix at 38; Applicant Ex. JPB-D at 7. ESC Harrison County Power has completed its United States Fish and Wildlife Service (USFWS) Section 7 Consultation; has completed its West Virginia Department of Natural Resources Lands Inquiry; has completed its State Historic and Preservation Office Phase I archaeological survey; and is actively working with all other necessary agencies to obtain permits for the Project. Application Appendix at 11-16; Applicant Ex. JPB-D at 30-34. ESC Harrison County Power submitted a comprehensive Application for the Project that included all of the required technical reports, mapping, and studies. See generally Application, Appendix and Appendix Exhibits 1-26. It is, therefore, evident that the Applicant is interested in pursuing and completing this Project, and being a positive contributor to the economies of the State, Harrison County, and the local community. Accordingly, based on the evidence, the Commission concludes that ESC Harrison County Power has demonstrated a sufficient interest in constructing the Project. ESC Harrison County Power has a legitimate business purpose in undertaking the Project, and ESC Harrison County Power retained various technical experts and developed detailed information in support of its Application. It has expended substantial time and economic resources to apply for a siting certificate, pursued various other permits and worked to obtain the real property interests and various agreements necessary to construct and operate the Project. ESC Harrison County Power has committed to working in conjunction with the Commission and other state and federal agencies. All of these facts show that ESC Harrison County Power has a serious and sincere interest in constructing the Project. 12 2. The Need for Generating Plants in the State and Region and Capacity to Meet the Needs of the Region ESC Harrison County Power asserted that it will provide clean, low cost and reliable electricity needed to help offset the effect of coal plant closings in the area and significant generation retirements in the PJM grid. ESC Harrison County Power explained that since 2012, numerous coal-fired power plants have been closed within the region including AEP’s Kammer, Kanawha River, and Philip Sporn plants, FirstEnergy’s Albright, Rivesville, and Willow Island plants, and Dominion’s North Branch plant. These closings have retired 2,641 MW of power. The decisions to close these plants were made independently and well in advance of any natural gas power plant developments being proposed in West Virginia. Application Appendix at 4-5. In addition, the PJM grid is experiencing significant retirements of 29,192 MW of generation which started in 201 1 and is planned through 2020. Most of the retired or retiring capacity (1 8,682 MW) is from West Virginia or an immediately bordering state (Kentucky, Ohio, Pennsylvania, Maryland, and Virginia). West Virginia’s current 15,050 MW of electric generating capacity has a weighted average age of forty years and is eighty-five percent coal with no new efficient combined cycle natural gas plants in the State. There is a need to replace these generation retirements in the PJM grid, and West Virginia is an ideal location because of its proximity to the retired or retiring capacity, and its access to Marcellus and Utica natural gas supply. Applicant Ex. AWD-D at 4. Because of the available fuel supply for the Facility, it is expected to function as a base load generating plant enabling it to compete effectively with plants in Pennsylvania and Ohio in the PJM grid. The Facility will help support the local production of natural gas and help maintain West Virginia’s prominence as an electrical energy supplier. Application Appendix at 4. ESC Harrison County Power will fund significant capital upgrades to existing infrastructure as required through the PJM interconnection process and will increase utilization of a natural resource produced in West Virginia, making drilling more attractive locally. Application Appendix at 4-5, 10. PJM is a regional transmission organization (RTO) that coordinates the movement of wholesale electricity in all or parts of Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia, West Virginia and the District of Columbia. The Project is located in the PJM Interconnection. Application Appendix at 4. The broad availability of a local fuel supply will allow the Facility to function as a base load generator capable of being dispatched at full capacity and allowing it to help meet the electric service demand in the PJM Interconnection. The Facility will provide diversification to the power mix in the State. Application Appendix at 4. When the ESC Harrison County Power Facility is operating at full capacity, it will deliver approximately 13 4,800,000 MWh to the grid annually. The Facility will generate enough electricity to power approximately 424,000 homes annually. Id.at 25; Applicant Ex. JPB-D at 25. West Virginia is part of a regional integrated electricity grid. Beech Ridge, Case No. 05-1590-E-CS, Cornmission Order Aug. 28, 2006, at 76 (Concl. of Law 14: “[Ilt is not in the public interest for this Cornmission to isolate West Virginia from the region. The power grid is interconnected, and to safeguard the availability of productive, wellmaintained resources to our State’s residents, West Virginia inust participate in the interconnected electric system.”). See, Pinnacle Wind Force, LLC, Case No. 09-0360-E-CS, Commission Order Jan. 11, 2010, at 5 1 (Concl. of Law 9), and Beech Ridge Energy IT LLC, Case No. 12-1196-E-CS, Commission Order June 19, 2013, at 42 (Concl. of Law 9). It is in the public interest to develop generation capacity utilizing diversified sources of kel to generate electricity, including alternative sources extracted in West Virginia such as natural gas. Additional generation capacity will help meet PJM’s projected load forecast in light of the many coal-fired plant closures. The Project will be a base load combined cycle power plant allowing it to meet electric service demand at all times. For all of these reasons, ESC Harrison County Power has demonstrated sufficient need for this Project. 3. The Economic Gain to the State and Local Economy ESC Harrison County Power engaged Witt Economics, LLC, to perform an economic assessment which studied the economic impact of the Project on the State and local economies. Dr. Witt’s analyses included labor, value added, output, sourcing of natural gas, and tax and other revenue payments. During the construction phase of the Project, Dr. Witt calculated that 2,543 job years and $187.4 million (2016 dollars) in employee compensation are associated with the Project. Other construction-related economic impacts include value added of $306.3 million (2016 dollars) and output of $880.8 million (2016 dollars). Application Appendix Ex. 22 at 5; Applicant Ex. TSW-D at 4-5. During the first year of operation the plant will be associated with 713 jobs and over $47.9 inillion (2016 dollars) in employee payroll. Annual operating economic impacts include value added of $72.8 million and output of $287.4 million dollars (all in 2016 dollars). Application Appendix Ex. 22 at 7; Applicant Ex. TSW-D at 6. ESC Harrison County Power intends to employ thirty permanent workers at the Facility upon commencement of operation. Application at 3; Application Appendix at 8. Under the PILOT agreement, ESC Harrison County Power will make payments for proportional distribution to HCBOE and HCC of at least $2,634,162 during a 30-year term, and under the Lease Agreement, ESC Harrison County Power will make annual lease payments over a period of thirty years totaling $23,707,460 under the basic rent schedule, along with an upfront payment of $1,000,000, resulting in a total rent 14 agreement of at least $24,707,460. Application Appendix at 70; Application Appendix Ex. 20; Application Exhibit A; Applicant Ex. MJD-D at 3-4. The Site currently does not generate ad valorem tax payments. Applicant Ex. MJD-D at 9. ESC Harrison County Power will pay significant corporate income tax during the years of operation. Applicant Ex. MJD-D at 10. After reviewing the filed Application, Josh Allen, Utilities Analyst for the Utilities Division of the Cornmission, testified concerning the PILOT and lease agreements: Thus Harrison County will realize approximately $27 million in new revenues over 30 years under the Lease and Pilot Agreement, while Harrison County and West Virginia will receive benefits of approximately $287.4 million annually. Staff Ex. JA-D, at 3. Mr. Allen recommended that if the siting certificate is granted, ESC Harrison County Power be required to have a decommissioning fund in place. Id.at 5 . Steve White, the Director of the Affiliated Construction Trades Foundation, a division of the West Virginia State Building and Construction Trades Council, AFL-CIO, provided testimony on behalf of the Building Trades. He testified that the North Central Building Trades and the Building Trades were finalizing a Memorandurn Agreement with ESC Harrison County Power that ensures, to the extent reasonably possible, workers employed in the construction of the wholesale electric generating facility will be local workers, Mr. White testified that upon review of ESC Harrison County Power’s manpower estimates for the Project, and based on his experience with other power plants, more than one million craft worker hours will be needed for the construction of the Project. Mr. White concluded that the size of the project and the amount of construction employment needed will have a substantial positive impact on the local economy and local employment. Construction Trades Ex. SW-D at 2-3. At the July 11, 201 7 hearing, Mr. John Black testified that the Memorandum Agreement among ESC Harrison County Power, the Building Trades, and the North Central Building Trades had been executed. Tr. at 35; Building Trades Hearing Ex. 1. Michael Jin, who has testified before the Commission several times regarding research on the probable economic impact of various construction projects, provided direct testimony on behalf of the Building Trades. Building Trades Ex. MJ-D. Mr. Jin completed an IMPLAN Economic Study that indicated, based on the information provided by ESC Harrison County Power, that the construction of the Project on an annualized basis would create 183 full-time equivalent jobs in construction and 139 in other industries. For the entire construction of the Project would create 805 jobs for West Virginia. Id. at 6. The Study indicated that construction of the Project will generate 15 $61.5 million in wages for workers connected to the Project and $11.7 million in State tax revenues. Mr. Jin testified that the construction of the Project will result in a substantial positive impact on the local economy and local employment, and will positively impact the state economy. Building Trades Ex. MJ-D at 6-7, Exhibit 1. The Commission has reviewed the various testimonies, Dr. Witt’s report, and the report prepared by Mr. Jin. Based on the record before the Commission, there should be a significant economic gain to both the State and local economies during construction and operation of the Facility. The Project will create significant local construction jobs and numerous permanent jobs thereafter and will provide significant revenues for local governments and public education. 4. Community Residents’ Interest in Living Separate from the Project; The Project’s Negative Impacts be Minimally Disruptive to Existing Uses; and The Project’s Social and Environmental Impacts Parties in siting certificate cases fiequently differ on aspects of the project involving viewshed, noise, traffic, and water result in negative social and environmental impacts and on whether those impacts are disruptive to the local residents and will allow those residents to live separate and apart from the impacts of the project. While the Commission weighs these considerations when assessing the community concerns, an overall analysis is more helpful, and is reflective of the approach taken by the Commission in prior siting certificate orders. The Commission analysis, therefore, will be presented in a comprehensive fashion. No letters or comments in opposition to the Project were filed with the Commission except for one protest from OVJA. Only two persons voiced opposition to the Project at the public hearings held in this matter. (a) Viewshed The Project Site is approximately 111 acres, with the Facility footprint being qyxoxirnately 12.67 acres and an access road of 1.07 acres. The Project is located north of the city limits of Clarksburg, bounded by undeveloped woodland and farmland to the north, a residential community, a recycling center, U S . Route 50 to the south, and undeveloped woodland, and residential properties to the east and west. Application Appendix Ex. 17 at 3. When completed, the Facility and access road will occupy about 13.74 of the 11 1.11 acres. Id. ESC Harrison County Power completed and submitted with the Application a Visual Analysis and Geospatial Rendering Report (Visual Analysis) consisting of a narrative evaluation, project mapping, visibility analysis, geospatial renderings, and photographic renderings. Application Appendix Ex. 17. The Visual Analysis illustrates the possible view of the ESC Harrison County Power Facility for radii of one mile, five miles, and twenty 16 miles around the boundary of the Facility. The report determined that of the approximately 8 10,618 acre study area, only 0.3 to 0.6 percent of the study area would have some visibility of the Project (207 to 501 acres). Visibility analysis was conducted under both bare earth and mature cover scenarios. Visibility of the Project beyond 14 miles was not detected under either scenario. Application Appendix Ex. 17 at 7,9; Applicant Ex. MF-D at 5. The Visual Analysis concluded that visibility of the Project is limited by its location in a large concave depression surrounded by moderately steep hill slopes screening the viewshed of areas west, north and east of the Site. Application Appendix Ex. 17 at 7,9. The local topography and vegetation of the Site acts as a natural viewshed buffer and obscures the Facility from a majority of the surrounding area. Id.at 10. The closest properties to the south of the Project that are either at the same elevation as the Project or significantly elevated have the highest probability of visibility of the Project. Applicant Ex. MF-D at 5. The Project will not be visible from nearby municipal areas such as Bridgeport, Weston, Grafton, or Fairmont.; .dI Application Appendix Ex. 17 at 9, Figures 13 (A-C). The Visual Analysis includes photographic renderings of the seven project views: a residence on Henry Ford Avenue located approximately 292 feet southeast from the Site, a residence on North Tibbs Avenue located approximately 1,000 feet south of the Site, a residence on South Tibbs Avenue located approximately 1,400 feet south of the Site, the Holy Cross Cemetery located approximately 4,553 feet southeast of the Site, the Harrison County Recycling Center located approximately 0.25 miles south of the Site, a residence on Jr. Avenue located approximately 2,200 feet southeast of the Site, and a residence on Pinnickinnick Street located approximately 1,320 feet southwest of the Site. Application Appendix Ex. 17 at 8-9, Appendix C; Applicant Ex. MF-D at 4. The overall visibility of the Project from these seven locations is minor, and in many cases sloping elevation, vegetation, and density of structures in the community limit visibility. Application Appendix Ex. 17 at 10. The Facility is not likely to affect negatively the local viewshed or aesthetic qualities of the area. Id. ESC Harrison County Power has incorporated mitigation of view within its design plan through the substantial planting of trees along Henry Ford Avenue between the Facility and the residential area. ESC Harrison County Power will plant a mixture of deciduous trees and evergreens (conifers) as a visual barrier for the residential area. Applicant Ex. JPB-D at 14-15. ESC Harrison County Power will file a Federal Aviation Administration (FAA) notice of height and location of cranes and stacks, but it is not expected that a notice of aviation hazard will be issued. Flags and possibly warning lights might be required. Applicant Ex. JPB-D at 3 2 . No state parks, national wildlife preserves, state refuges, state wildlife management areas, national landmarks, national parks, national recreation areas, scenic rivers, scenic 17 highways, or other sensitive features have visibility of the Project. Application Appendix Ex. 17 at 8. There are no historic architecture points, cemeteries or National Register of Historic Places (NRHP) points within the proposed Project area. Six NRHP listings are near the Facility, but do not have visibility of the Facility. Application Appendix Ex. 17 at 9- 10, Figure 15; Applicant Ex. MF-D at 4-5. The Commission observed during its site visit to the Project that the Site has historically been a mining site and continues to be industrial in nature with the Harrison Recycling Center adjacent to the Project Site. The Commission also observed that views of the Project in the immediate area are limited. While the HRSG and stack will be visible from several locations very near the Project, after reviewing the evidence and conducting the View, it appears that there will be no interference with existing scenic or aesthetic uses, and there will be no adverse effect on the scenic character of the land within the viewshed of the Project. The impact of the presence of the Project and view of the Project will be minimally disruptive to the community and neither unreasonable nor burdensome. (b) Sound Numerous factors affect sound levels from electric generation projects, including the type of generation equipment, layout (general arrangement), building design, weather, ground cover, distance, ambient noise, leaf and foliage cover, elevation, and wind direction. With its Application, as required by Siting Rule 3.1.m.4, ESC Harrison County Power submitted a Noise Study that evaluated pre-construction, construction, and operational noise, and complied with the Siting Rules. Application Appendix Ex. 25. Behrens and Associates, Inc. prepared ESC Harrison County Power's Noise Study. Noise data were collected at five monitoring locations to the southeast, south, and southwest of the Facility: the nearest receptor, a residence owned by Mrs. Wright on Henry Ford Avenue at the crest of a hill; a residence on North Tibbs Avenue; the First Free Will Baptist Church directly south on North Ohio Avenue; a residence to the southwest on Pinnickinnick Street; and a Pike Street residence located to the southwest. Application Appendix Ex. 25 at 9-10. Any residential areas west, east, or north of the Project would be separated from the Project by steep ridgelines. Tr. at 24-25; Application Appendix Ex. 25 at 6. 1. Pre-Construction Noise Five monitoring locations were evaluated in the vicinity of the proposed Facility. The pre-construction survey indicated that road noise from U.S. Route 50 and rail noise from the nearby active CSX tracks near North Ohio Avenue were prevalent at four of the five monitoring locations in the study. Application Appendix Ex. 25 at 9-12. Other sources of noise were likely present, such as the recycling facility directly south of the Facility Site. The ambient level at the closest residence of Mrs. Wright at the crest of the hill is 49-52 dBA but then increases to as much as 60-61 dBA after cresting the hill and 18 proceeding to the south toward U S . Route 50 and closer to the active portions of the recycling facility. Id.at 9-12. 2. Construction Noise The Noise Study assessed the operation of earth moving equipment, driving of piles, erection of structures, truck or other traffic, installation of equipment, and cleanup and reclamation. at 26. No dynamiting activities are expected to occur during construction of the Facility. Application Appendix at 80. The modeling used a highly conservative method by assessing maximum noise possible with the combined pieces of equipment that might be utilized. The modeling assumed that construction equipment would operate concurrently, resulting in a maximum noise value for a condition which will not occur. Applicant Ex. JPB-R at 8. Because of the down-gradient nature of the Site, trees, the adjacent hills and recycling structures, and noise mitigation techniques, most locations near the Site will have five or more db of shielding. Applicant Ex. JPB-R at 8. With this level of shielding any potential increase in ambient noise levels during construction, if any (except at the closest receptor Mrs. Wright), should be minimal. Application Appendix Ex. 25 at 44. With respect to the closest receptor, the residence located on the crest of the hill known as Henry Ford Avenue, ESC Harrison County Power has reached an agreement with the owner to purchase the property which will then be used for additional noise mitigation. Tr. at 25. The community surrounding the Site is familiar with industrial noise from the strip mining coal operations and the various recycling activities, and the nearness of the active CSX railroad tracks in this area. Based on the information provided, and considering the existing commercial and industrial activities in the area, the ambient noise associated with 1J.S. Route 50, CSX train traffic, the industrial nature of the recycling facility, and the fact that the nearest receptor property will be purchased by ESC Harrison County Power, the noise levels associated with construction activities will cause only a minimal increase in noise exposure to the surrounding residential community. 3. Operational Noise and Noise Mitigation Measures Noise impact from the power plant was evaluated using a conservative noise model that did not consider changes in shielding. Additionally, the model was run with a conservative noise level which was the maximum level of all equipment combined. Specifically, all pieces of equipment that were sources of significant noise were included in the noise model. Application Appendix Ex. 25 at 38. The model was also conservative in that the maximum noise value was evaluated from the boundary or perimeter of the power plant. This method provides higher noise estimates than would be anticipated because several of the noise-generating features at the power plant are located within the complex and shielded by other plant buildings. 19 Specifically, the administration office building and warehouse will be between the plant and residential community. The model evaluated these features at maximum noise levels that would not be anticipated at the plant boundary. Application Appendix at 82-83. I The Study found that the closest receptor, the residence on Henry Ford Avenue at the crest of the hill, would experience an increase in sound level during operation of about seventeen to eighteen dBA. However, ESC Harrison County Power is purchasing this property and the residents are moving, and ESC Harrison County Power will be installing additional noise mitigation plantings. Tr. at 25. Beyond the crest of the hill are other residences, but the hillside provides considerable shielding of close to eight to ten db. Application Appendix Ex. 25 at 40-4 1. Even these values are conservative. It is anticipated that ESC Harrison County Power’s noise mitigation efforts will provide approximately five or more db reduced sound level at the receptors. Applicant Ex. JPB-R at 8. ESC Harrison County Power intends to plant trees along the southern and southeast side of the Facility boundary. The rows of trees will act as a dampening and buffer to noise. Id. In light of the sound evidence, the Project will not substantially increase ambient noise levels in the area. The ambient sound levels will remain relatively similar and to the extent that construction or operation noise results in negative impacts, those negative impacts are expected to be as minimally disruptive to existing property uses as is reasonably possible, and are not unreasonable. ESC Harrison County Power plans several types of mitigation measures to shield noise from the community. (e) Air ESC Harrison County Power has the potential for air emissions from several components of the Project and has thus filed the appropriate permit application with the West Virginia Department of Environmental Protection, Division of Air Quality. Application Appendix at 13, 31-32. Modeling has been conducted and an air permit application was submitted in November 2016. The permit is anticipated in advance of the date needed for design and manufacturing of the equipment. Applicant Ex. JPB-D at 29-30. 20 (d) Water The primary source of water for the Facility operations will be a dedicated pipeline from the CWB. Facility process water will consist primarily of cooling system blowdown and oil water separator effluent. The Facility Site will discharge approximately 100,000 gallons per day (gpd) of treated water to the CSB system. Treated water will be used on site for maintaining the trees and plants in the green spaces and for other non-consumptive uses in accordance with the Facility Site discharge permits. Application Appendix at 33. Potable water would be used for several Facility uses, including fire water, service water, plumbing fixtures, combustion turbine make-up water, and demineralized water system make-up. It is estimated that 100,000 gpd (average of 70 gallons per minute (gpm)) of water will be utilized for plant operations.; .dI Applicant Ex. JPB-D at 28. Wherever practical, wastewater generated by these uses will be recycled. Drains from plumbing fixtures will be collected in a sanitary sewer system and pumped or gravity fed to an existing CSB line. Application Appendix at 33. ESC Harrison County Power will obtain all required permits necessary to receive water from the CWB for the Project. Applicant Ex. JPB-D at 29. (e) Hydrology The Thrasher Group, Inc. (Thrasher) prepared a Surface and Groundwater Resources Report. Application Appendix Ex. 19. The Facility will not affect groundwater resources on the Site. Id. at 4; Applicant Ex. MF-D at 7. Surface waters will be impacted by construction of the Facility, but will be addressed with control measures that collect stormwater and best management practices to protect nearby and downstream surface waters. Applicant Ex. MF-D at 7. No aquifers will be affected by the Facility, and there will be no injection of process or other waters. Applicant Ex. MFD at 8. The Project is not anticipated to affect significantly aquatic resources within the Site. Application Appendix Ex. 19 at 5 . (f) U.S. Fish and Wildlife Service and West Virginia Department of Natural Resources ESC Harrison County Power has completed a Section 7 consultation with the United States Fish and Wildlife Service (USFWS), and the USFWS has delivered a response that no threatened or endangered species are known to exist on the Site. Application Appendix Ex. 23; Applicant Ex. JPB-D at 30-3 1. ESC Harrison County Power has completed a Lands Inquiry with the West Virginia Department of Natural Resources (DNR) for the Project. DNR has indicated 21 that they have no known records of State rare, threatened or endangered species and sensitive habitats within the Project area. Application Appendix Ex. 24; Applicant Ex. JPB-D at 3 1. (g) Traffic A. Morton Thomas Consultants (AMT) prepared a traffic study that assesses the volume of pre-construction, construction and post-construction traffic for public roads near the Facility using information from the West Virginia Division of Highways (DOH) and from peak hour turning movement counts at four nearby intersections that are anticipated to be impacted by the Project. Application Appendix Ex. 26. The Project Site is located north of the Clarksburg city boundary and north of North Ohio Avenue and an active railroad line which is crossed via an overpass from U.S. 50 on Florence Street. Most traffic, both during construction and operation, will arrive in the vicinity of the Project Site from the Florence Street overpass. Turning movement counts, conducted in accordance with DOH Traffic Engineering Directives, were performed at four signalized and nearby intersections. DOH information was also reviewed. The analysis in the AMT Traffic Study indicates that during the construction phase the Project will have only a minor impact on the operation of the existing transportation network and that the nearby intersections will also operate at an acceptable level per guidelines established by the DOH. Application Appendix Ex. 26 at 1-2. Short term recommendations were made to address any impacts during the construction phase, and ESC Harrison County Power has indicated that it will address these recommendations. Application Appendix at 83; Application Appendix Ex. 26. Furthermore, ESC Harrison County Power and its contractors will not change shifts or block roads with heavy haul deliveries while school buses are scheduled to be on roads within one mile of the Site. Applicant Ex. JPB-R at 13-14, Exhibit A at 6 . After construction is complete, the traffic associated with the Project will be limited to operational and maintenance vehicles. It is anticipated that 30 vehicles making 23 peak hour trips will enter and exit the Site each day for operational activities. According to the AMT traffic study this volume of traffic has virtually no impact to the transportation network. Application Appendix Ex. 26 at 1. ESC Harrison County Power Project will not cause any substantial problems or difficulties with respect to existing traffic patterns. After completion of the Project, the slight increase in traffic will have no impact on the transportation network. Accordingly, the Project will not have a significant or substantial impact on traffic in and around the Project area. 22 (h) Area property values and local infrastructure ESC Harrison County Power does not expect a negative impact on area property values from the Project. The Site is surrounded by an area which is primarily industrial and was operated as a coal strip mine and loading facility. It is now largely vacant with oil/gas wells and an adjacent recycling yard. The redevelopment of this brownfield site and the likely economic development on surrounding acreage by the Harrison County Redevelopment Authority should enhance, not decrease, property values. Application Appendix at 6, 76-77; JPB-D at 8. ESC Harrison County Power does not anticipate any negative impacts to the local infrastructure from either the construction or operation of the proposed Facility. There are local water and sewer utilities present with ample capacity to meet the needs of the Facility. Application Appendix at 65; Applicant Ex. JPB-D at 33-34. In addition, traffic increases from operations will be negligible and will not affect local roadways. Applicant Ex. JPB-D at 34. During construction traffic control and turning lane improvements may be needed for traffic and deliveries; however, ESC Harrison County Power is working with appropriate state and city officials to design any necessary errrblrlporaryimprovements. Applicant Ex. JPB-D at 34. 5. The Joint Stipulations and Project Conditions In its Direct Testimony, Staff recommended the Commission adopt various conditions if a Siting Certificate is granted ESC Harrison County Power in this case. Staff Ex. JA-D at 5; Staff Ex. DEW-D at 10, Ex. 3. ESC Harrison County Power witness Black, in his Rebuttal Testimony, set forth ESC Harrison County Power's suggested clarifications and revisions to several of the Staff's proposed conditions. Applicant Ex. JPB-R at 9-15, Exhibit A. ESC Harrison County Power, Staff, and the Building Trades entered into settlement discussions and have reached an agreement that they recommend the Commission adopt. Joint Ex. 1. They ask that the siting certificate requested by ESC Harrison County Power be granted subject to these conditions in the Joint Stipulation: 1. At least 30 days prior to beginning construction ESC Harrison County Power will provide the PSC notice of start of construction. 2. Prior to the Commercial Operation Date (COD) Harrison County Power shall file a verified statement that the required detailed plans for the Harrison County Power project have been completed, reviewed and approved in accordance with the appropriate codes and 23 standards and where required, under the supervision of a licensed professional engineer. 3. At least 30 days prior to beginning construction of the Project, Harrison County Power shall file a verified statement that certifies that required permits, approvals, certifications, notices, and consultations have been obtained, including the following: a. PJM Interconnection Services Agreement b. State Historic Preservation Office (SHPO) Consultation c. United States Fish and Wildlife Service (USFWS) Section 7 Consultation d. WV DNR Lands Inquiry e. Department of the Army 404 Permit(s) f. State 401 Water Quality Certification g. WV DNR Stream Activity Permit h. Air Quality Permit from the West Virginia Division of Air Quality i. West Virginia National Pollutant Discharge Elimination System (NPDES) Permit j. Groundwater Protection Plan (GPP) k. Site Plan Approval and Grading Permit 1. Federal Aviation Administration (FAA) Notice of Construction or Alteration 117. Construction Stormwater General Permit and Stormwater Pollution Prevention Plan n. West Virginia Department of Highways (WVDOH) IAR Engineering and Construction Agreement 0 . Above ground Storage Tank Water Resources Protection Act and the Public Water Supply Protection Act approvals. Provided, however, with respect to the approvals and permits set forth in p., q. and r. below it is recognized that one or more may not be available until immediately before the activity for which the approval or permit is issued, commences, in which event Harrison County Power shall within a reasonable time after receipt certifying that the approval or permit has been obtained: p. Railroad Right of Way Encroachment Approvals q. Building Permits r. Highway Heavy Haul Permits 24 At least 30 days before operation of the Facility, Harrison County Power shall file a verified statement that certifies that all required permits, approvals, certificates, notices and consultations required prior to the start of operation have been obtained, including the following: 4. a. Stormwater General Permit and Stormwater Pollution Prevention Plan b. Spill Prevention Control and Countermeasures (SPCC) Plan c. Emergency Response Plan (ERP) d. Pre-treatment/Discharge Permit - Sanitary e. Water System Connection 5. Fuel for the Project will be delivered through a pipeline to the plant, constructed, operated and owned by a third party (the “Pipeline Project”). Prior to the beginning of construction on the Pipeline Project, ESC Harrison County Power shall file a verified statement that certifies that a binding contract(s) are or will be in place for: a. Installation and construction of adequate natural gas delivery points, including Federal Energy Regulatory Commission (FERC) certificates, if required, for new delivery points on interstate pipelines. b. Construction and operation of the pipeline necessary to deliver the fuel to the plant site, including all necessary measurement and pressure regulation equipment. c. A contracted fuel supply. 6. The verified statement filed in connection with Condition 5 above shall provide a verified statement of the pipeline contractor certifying that all options for, or rights of way, and all required permits necessary for the construction and operation of the Pipeline Project have been obtained. 7. Applicant shall plant in a staggered pattern along the southern border of the property from a location just east of the onsite pond up the slope to a point between Henry Ford Avenue and the northeast corner of the plant fence, and along the Henry Ford Avenue property line, evergreen and deciduous trees in accordance with the schedule attached hereto as Exhibit A. 8. Care of the trees and shrubs planted in accordance with Condition 7 shall be incorporated into the operations and maintenance plan for the site. Any such tree or shrub that does not survive will be replaced in kind. 9. Harrison County Power shall provide an independent expert report on the amount needed to decommission the facility less market or salvage value and post a Letter of Credit (“LoC”), purchase a bond or surety, or place the present value of such an amount in an escrow fund prior to beginning operation. Harrison County Power recognizes that the plant value far exceeds the decommissioning costs in the first ten (10) years of its service life. Nevertheless, the initial LoC, bond or surety, or escrow account shall be no less than $250,000 to cover the cost of soliciting and engaging a decommissioning company. In no case shall the decommissioning amount exceed the maximum value required by the lease agreement, which is $3 million. The report shall be updated thereafter as mutually agreed between Harrison County Power and the Harrison County Commission, but no less frequently then every ten (10) years thereafter until the provision of the HCC Lease which requires a $3 million fund becomes operative. The decommissioning fund amount may vary over time depending on changes in the estimated market or salvage value of the Project, the estimated cost of dismantling the plant and the expected ongoing life of the Project. Harrison County Power will provide the report to the Harrison County Commission and request its approval or concurrence of the evaluative expert and each of the periodic reports. The decommissioning fund shall not be part of Harrison County Power’s assets. Within ninety (90) days of any report that requires a contribution to the decommissioning fund, Harrison County Power will increase the LoC, or bond or surety, or make that contribution into an escrow account held by an agent pursuant to an escrow agreement between Harrison County Power and the Harrison County Commission. Reductions to, or withdrawal from, the decommissioning fund shall not be allowed sooner than ninety (90) days after the Harrison County Commission has been offered the opportunity to review the report. The methods for deposits to and disbursements from the 26 decommissioning fund shall be established within and governed by the LoC, bond or surety, or escrow agreement. Furthermore, the LoC, bond or surety, or escrow agreement must clearly reflect the role of the Harrison County Commission and state that the obligations set forth in the agreement apply to Harrison County Power, its successors and assigns. Each report of the qualified independent third party will also be filed with the Commission as a closed entry in this matter. The Commission retains the right to hire its own evaluative expert to review any of the periodic reports and to take such further action within its jurisdiction as the Commission determines is necessary to protect the public interest. 10. Harrison County Power, and its contractors, shall not change shifts or block roads with heavy haul while school buses (elementary, middle or high school) are scheduled to be on the roads within 1 mile of the site. 11. Harrison County Power shall file proof of its exempt wholesale generator (EWG) status from FERC prior to commencing commercial operation. 12. The siting certificate shall become invalid if Harrison County Power has not commenced a continuous course of construction within five (5) years of the date the final certificate is granted or has not completed construction by the tenth year following the granting of the certificate without petitioning the Commission for approval to expand these time frames. 13. If Harrison County Power seeks to transfer its certificate, Harrison County Power is required pursuant to Siting Rule 7.1 to notify the Commission in writing of the identity of the transferee and submit an affidavit from the transferee attesting to the transferee’s willingness to abide by the terms of a siting certificate as issued. This condition applies at any time - not just in the operational stage. Joint Ex. 1 at 5-9. OVJA, ESC Harrison County Power, Staff, and the Building Trades also filed a Joint Stipulation and Agreement for Settlement of Ohio Valley Jobs Alliance’s Claims, which recommended to the Cornmission as a full and complete resolution of all of the issues raised by OVJA in this proceeding, that as a condition of any Siting Certificate 27 which may be issued in this case ESC Harrison County Power should be required to obtain and file proof of having obtained an Air Quality Permit from the West Virginia Division of Air Quality. Joint Ex. 2. Upon review of the Joint Stipulations, the Commission finds that many of the proposed conditions are typical in siting certificate orders, and finds that the conditions are reasonable, and we recognize that ESC Harrison County Power has agreed to comply with all of the conditions in Joint Ex. 1 and Joint Ex. 2. 6. Memorandum Agreement with the Building Trades ESC Harrison County Power, Staff, and the Building Trades request that the Commission approve the Memorandum Agreement between ESC Harrison County Power, the North Central Building Trades, and the Building Trades and make clear that the Commission anticipates that all representations and commitments made by the parties therein will be kept by the parties. The Commission has in previous siting cases approved the Memorandurn Agreement and ordered that "all representations and commitments made by the parties therein be kept by the parties.'' Mount Storm Wind Force, LLC, Case No. 01-1664-ECN, at 31 (Commission Order August 29, 2002). We see no reason to depart from this approach. We note, as we have in the past, that approval of the Memorandum Agreement by the Commission does not mean the Commission is the proper forum to resolve any disputes that may arise from operating under that Memorandum Agreement. C. Application of Part Two of the Balancing Test As is explained in Part One above, the Commission concludes that taken as a whole, the positive impacts relating to the various interests outweigh any negative impacts on the various interests in this matter. W. Va. Code 5 24-2-1 IC. In Part Two of the balancing test, the Commission decides whether a project's public funding, if any, and property tax abatement, if any, offend the public interest. ESC Harrison County Power provided documentation and testimony concerning PILOT and lease agreements and an Industrial Access Road agreement that are involved with this Project. Application at 3; Applicant Ex. MJD-D at 2-7; Application Appendix at 68-70 and Appendix Ex. 20; Application Ex. 2; Applicant Hearing Ex. 3. ESC Harrison County Power, Staff, and the Building Trades agreed that the terms and conditions of the PILOT agreement between ESC Harrison County Power, the HCC, the HCBOE, the Sheriff of Harrison County, West Virginia, and the Assessor of Harrison County, West Virginia, the Lease Agreement between the HCC and ESC Harrison County Power, and the Industrial Access Road Agreement between the DOH and the HCC do not offend the public interest and the construction and operation of the facility will result in a substantial positive impact on the local economy and local employment. Joint Ex. 1 at 9. Based on the record, and the 28 significant tax revenues and other economic benefits that will accrue to Harrison County and the State, these agreements do not offend the public interest. Thus, based on the entire record, ESC Harrison County Power should be issued a siting certificate for this Project, subject to the conditions discussed in this Order. FINDINGS OF FACT 1. ESC Harrison County Power filed its Application on January 17, 2017. Application at 1-2; See Case File, generally. 2. The Facility will have a nominal nameplate capacity of approximately 580 MW (up to approximately 630 MW under favorable conditions), utilizing state-of-the-art clean-burning natural gas-fueled electric generating equipment consisting of one combustion turbine, one steam turbine, and one generator. The exhaust from the CT will be directed through one HRSG that utilizes exhaust heat from the CT to generate highquality, superheated steam to drive the ST. Application at 2. The CT and ST through a sir;gle shaft arrangement turn a common generator generating electricity in an efficient and environmentally friendly manner. The Facility will receive natural gas fuel through existing Equitrans 3. facilities and the construction of a lateral extending from the FERC regulated pipeline owned and operated by Equitrans’ interstate pipeline. Application Appendix at IO. 4. ESC Harrison County Power has negotiated a construction and transportation agreement and has submitted a bid for service in an Equitrans open season for firm transportation capacity on the Equitrans system that will allow ESC Harrison County Power to purchase gas from various sellers on Equitrans and other interconnected systems. Under the terms of the agreement, Equitrans has been acquiring the rights-ofway necessary to construct a pipeline extension approximately 5.5 miles to the Facility’s location (Pipeline Extension). Application Appendix at 10; Applicant Ex. AWD-D at 5-6; Applicant Ex. AWI3-R at 5-6; Tr. at 56-57. Equitrans, an interstate pipeline regulated by the FERC under Section 7(c) 5. of the Natural Gas Act of 1938, will construct and operate the Pipeline Extension and obtiiin all applicable permits and permissions. The Pipeline Extension would be constructed and operated as a prior notice project under Equitrans’ existing blanket certificate authority. Application Appendix at 10; Applicant Ex. AWD-D at 6; Applicant Ex. AWD-R at 2. ESC Harrison County Power has evaluated available alternatives and has 6. determined that the expansion of the Equitrans system to the Facility is the most economic option for the Facility to obtain secure, reliable and economically competitive 29 natural gas to allow the Facility to be successfully financed, built and operated. Application Appendix at 10. 7. The Facility will utilize the CWB as a source for cooling and potable water and will discharge cooling water blowdown and other contact and non-contact water to the CSB system. Stormwater will continue to be discharged into an unnamed tributary of Elk Creek. Application Appendix at 10, 66; Applicant Ex. MF-D at 7, 10; Applicant Ex. JPR-D at 5, 35. 8. The power generated by the Facility will be delivered to the existing Mon Power Glen Falls Substation, located approximately 1.8 miles from the Facility, via a transmission line of approximately 9,600 linear feet in length. Application at 2; Application Appendix at 9. 9. The Facility Site is in an unincorporated area of Harrison County, north of 1J.S. Route 50, which was formerly the site of the Pinnickinnick Coal Company, and subsequently transferred to the Clarksburg Fuel Company, and the Consolidation Coal Company. Application at 2. 10. ESC Harrison County Power controls approximately 110 acres of the larger 2 12-acre parcel through a purchase option agreement with Harrison County Development Authority; however, the Facility will occupy a footprint of only approximately thirteen acres after construction, leaving additional acreage available inside the boundaries of the 110-acre property for further commercial and industrial development. Application Appendix at 5 . 11. The thirteen acre Site and surrounding areas have been investigated and there are no adverse environmental conditions that would pose limitations on the development or constructability of the Project. ESC Harrison County Power chose the Site for numerous reasons, including that the Site is in close proximity to electric transmission lines, abundant natural gas is readily available in close proximity to the site with redundant supply sources and transportation options, the Project will have very little adverse impact to the Site’s existing conditions and minimal change to the viewshed and existing noise levels for the nearby residents, and the availability of a trained and qualified local labor pool that has the requisite skills to construct the Project. Application Appendix at 6-7; Applicant Ex. JPB-D at 18-19. 12. ESC Harrison County Power will be the entity responsible for the construction and operation of the Facility and for the sale of electricity generated by the Facility, and will operate the Facility as an exempt wholesale generator as defined under Section 32(a) of the Public Utility Holding Company Act of 1935. Application Form 2 at 2; Application at 3. 30 13. ESC Harrison County Power estimates that construction of the Facility and the transmission line will cost approximately $6 15 million. Application Form 2 at 2, 14. The Project funding will be a combination of equity and term loan A financing. ESC Harrison County Power has entered into a PILOT agreement with the HCBOE and the HCC whereby ESC Harrison County Power will be exempt from ad valorem property tax for 30 years, and will make payments in lieu of taxes for proportional distribution to HCBOE and HCC of at least $2,634,162 during a 30-year term. Application Appendix at 68-70; Application Appendix Ex. 20; Applicant Ex. MJD-D at 2-3, 8. 15. ESC Harrison County Power has also entered into a Lease Agreement with the HCC and will make annual lease payments over a period of thirty years totaling no less than $23,707,460 under the basic rent schedule, along with an upfront payment of $1,000,000, resulting in a total rent agreement package of at least $24,707,460. Presently Harrison County does not collect ad valorem taxes on the Site because it is owned by the HCC. Application Appendix at 69-70; Application Exhibit A; Applicant Ex. MJD-D at 3-5, 8. 16. The HCC has been awarded a grant of $400,000 under the West Virginia Industrial Access Road Program for the design and construction of the proposed industrial access road to the Site and the HCC’s property for further development. ESC Harrison County Power is contributing $150,000 for the necessary matching funds for the grant, and will also fund the additional amount needed ($480,000) of the total road cost of $1,030,000. Tr. at 2 1-22; Applicant Hearing Ex. 3; Applicant Ex. JPB-R at 8. 17. The total economic impact for West Virginia is estimated to be more than $880 million in output during construction and more than $287 million in output annually during operation. Application at 3. 18. On June 6, 2017, the Commission conducted a View of the project area with representatives of Commission Staff, Building Trades, OVJA and ESC Harrison County Power. 19. The Commission received 545 letters and postcards in support of the Project, and one protest from OVJA. See generally case file. On July 3, 2017, OVJA, including its unincorporated chapter known as 20. North Central West Virginia Jobs Alliance, ESC Harrison County Power, Staff, and the Building Trades filed a Joint Stipulation and Agreement for Settlement of Ohio Valley Jobs Alliance’s Claims, in which they recommended to the Commission that as a condition of any Siting Certificate which may be issued in this case that ESC Harrison 31 County Power should be required to obtain and file proof of having obtained an Air Quality Permit from the West Virginia Division of Air Quality. Joint Ex. 2; Tr. at 32. 21. On July 6, 2017, ESC Harrison County Power, Staff and Building Trades filed a Joint Stipulation and Agreement for Settlement, in which they recommended the Commission grant ESC Harrison County Power a siting certificate, subject to certain conditions. Joint Ex. 1; Tr. at 3 1. 22. ESC Harrison County Power, the North Central Building Trades, and the Building Trades entered into a Memorandum Agreement. Building Trades Hearing Ex. 1; Tr. at 46-48. 23. ESC Harrison County Power has secured a site for the Facility in an area where there will be a shortage of electric supply resulting from planned retirement of existing, mostly obsolete, coal fired plants in West Virginia and substantial retirement of plants throughout PJM. Application Appendix at 4-5, 19. 24. ESC Harrison County Power has successfully completed the PJM feasibility study and the system impact study. Application Appendix at 3 8; Applicant Ex. JPB-D at 7. 25. ESC Harrison County Power has completed its United States Fish and Wildlife Service (USFWS) Section 7 Consultation, its West Virginia Department of Natural Resources Lands Inquiry, its State Historic and Preservation Office Phase I archaeological survey, and is actively working with all other necessary agencies to obtain permits for the Project. Application Appendix at 11-16; Applicant Ex. JPB-D at 30-34. 26. ESC Harrison County Power explained that since 2012, seven power plants have closed, representing a loss of approximately 2,641 MW of generating capacity. Application Appendix at 4-5. 27. ESC Harrison County Power will fund significant capital upgrades to existing infrastructure as required through the PJM interconnection process and will increase utilization of a natural resource produced in West Virginia making drilling more attractive locally. Application Appendix at 4-5, 10. 28. The Project is located in the PJM Interconnection. Application Appendix at 4. 29. The broad availability of local fuel supply will allow the Facility to function as a base load generating facility capable of being dispatched at full capacity thus allowing it to help meet the electric service demand in the PJM Interconnection. Id. 32 30. When the ESC Harrison County Power Facility is operating at full capacity, it will deliver approximately 4,800,000 MWh to the grid annually. The Facility will generate enough electricity to power approximately 424,000 homes annually. Id.at 25; Applicant Ex. JPB-D at 25. 31. During the construction phase of the Project, 2,543 job years and $187.4 million in employee compensation are associated with the plant. Other constructionrelated economic impacts include value added of $306.3 million and output of $880.8 million. Application Appendix Ex. 22 at 5; Applicant Ex. TSW-D at 4-5. 32. Using 2016 dollars, during the first year of operation the plant will be associated with 713 full and part-time jobs and $47.9 million in employee payroll. Additionally, annual operating economic impacts include value added of $72.8 million and total economic impact of $287.4 million dollars per year. Application Appendix Ex. 22 at 7; Applicant Ex. TSW-D at 6. 33. ESC Harrison County Power intends to employ up to thirty permanent workers at the Facility upon commencement of operation. Application at 3; Application Appendix at 8. 34. The PILOT and Lease Agreements will cause Harrison County to realize approximately $27 million in new revenues over thirty years, and Harrison County and West Virginia will receive benefits of approximately $287.4 million annually. Staff Ex. JA-D at 3. 35. More than one million craft workers hours will be needed to construct the Project, and the size of the project and the amount of construction employment needed will have a substantial positive impact on the local economy and local employment. Construction Trades Ex. SW-D at 2-3. 36. The entire construction of the Project would create 805 jobs for West Virginia, and generate $61.5 million in wages for workers connected to the Project and $1 1.7 million in State tax revenues. Construction Trades Ex. MJ-D at 6, Exhibit 1. 37. The Visual Analysis concluded that visibility of the Project is limited by its location in a large concave depression surrounded by moderately steep hill slopes screening the viewshed of areas west, north and east of the Site. Application Appendix Ex. 17 at 7,9. The closest properties to the south of the Project that are either at the same 38. elevation as thc; Project or are significantly elevated will have the highest probability of visibility of the Project. Applicant Ex. MF-D at 5. 33 39. The Project will not be visible from nearby municipal areas such as Bridgeport, Weston, Grafton, or Fairmont. ; .dI Application Appendix Ex. 17 at 9, Figures 13 (A-C). Of the approximately 810,618 acre study area, only 0.3 to 0.6 percent have 40. some visibility of the Project (207 to 501 acres). Visibility analysis was conducted under both bare earth and mature cover scenarios. Visibility of the Project beyond 14 miles was not detected under either scenario. Application Appendix Ex. 17 at 7, 9; Applicant Ex. MFD at 5. The Project is not visible from any state parks, national wildlife preserves, 41. state refuges, state wildlife management areas, national landmarks, national parks, national recreation areas, scenic rivers, scenic highways, or other sensitive features. Application Appendix Ex. 17 at 8. There are no historic architecture points, cemeteries or NRHP points within 42. the proposed Project area. Six NRHP listings are near the Facility, but do not have visibility of the Facility. Application Appendix Ex. 17 at 9- IO, Figure 15; Applicant Ex. MF-D at 4-5. ESC Harrison County Power has incorporated mitigation of view within its 43. design plan through the substantial planting of trees along Henry Ford Avenue between the Facility and the residential area. Applicant Ex. JPB-D at 14-15. ESC Harrison County Power will file a Federal Aviation Administration 44. Notice of Construction or Alteration. Applicant Ex. JPB-D at 32. ESC Harrison County Power does not expect that a notice of aviation 45. hazard will be issued, but flags and possibly warning lights might be required. Noise data were collected at five monitoring locations to the southeast, south, 46. and southwest of the Facility: the nearest receptor, a residence owned by Mrs. Wright on Henry Ford Avenue at the crest of a hill; a residence on North Tibbs Avenue; the First Free Will Baptist Church directly south on North Ohio Avenue; a residence to the southwest on Pinnickinnick Street; and a Pike Street residence located to the southwest. Application Appendix Ex. 25 at 9-10. Any residential areas west, east, or north of the Project would be separated 47. from the Project by steep ridgelines. Tr. at 24-25; Application Appendix Ex. 25 at 6. Road noise from U.S. Route 50 and rail noise from the nearby active CSX 48. tracks near North Ohio Avenue were prevalent at four of the five monitoring locations in the study. Application Appendix Ex. 25 at 9-12. 34 The ambient level at the closest residence of Mrs. Wright at the crest of the 49. hill is 49-52 dBA but then increases to as much as 60-61 dBA after cresting the hill and proceeding to the south toward U. S . Route 50. Application Appendix Ex. 25 at 11-12. 50. The Noise Study assessed the operation of earth moving equipment, driving of piles, erection of structures, truck or other traffic, installation of equipment, and cleanup and reclamation. Id. at 26. No dynamiting activities are expected to occur during construction of the Facility. Application Appendix at 80. 51. The modeling used a highly conservative method by assessing maximum noise possible with the combined pieces of equipment that might be utilized, resulting in a maximum noise value for a condition which will never occur. Applicant Ex. JPB-R at 8. 52. Because of the nature of the Site, trees, the adjacent hills and recycling structures, and noise mitigation techniques, most locations near the Site will have five or more db of shielding. Applicant Ex. JPB-R at 7-8. 53. The Study found that the closest receptor, which is the residence on Henry Ford Avenue at the crest of the hill, would experience an increase in sound level during operation of about seventeen to eighteen dBA. ESC Harrison County Power, however, is purchasing this property and the residents are moving. ESC Harrison County Power will be installing additional noise mitigation plantings on this property. Tr. at 25. 54. The operational noise model was conservative in that the maximum noise value was evaluated from the boundary or perimeter of the power plant. This method provides higher noise estimates than what would be anticipated as several of the noisegenerating features at the power plant are located within the complex, shielded by other plant buildings. Application Appendix at 82-83. 55. Beyond the crest of the hill are other residences but the hillside provides considerable shielding of close to eight to ten db. Application Appendix Ex. 25 at 40-4 1 , 56. It is anticipated that noise mitigation efforts will provide approximately five or more db reduced sound level at the receptors. Applicant Ex. JPB-R at 8. 57. ESC Harrison County Power intends to plant trees along the southern and southeast side of the Facility boundary. The rows of trees will act as a dampening and buffer to noise. Id. In November 2016 ESC Harrison County Power filed an appropriate permit 58. application with the West Virginia Department of Environmental Protection, Division of Air Quality. Application Appendix at 13, 31-32. 35 59. The primary source of water for the Facility operations will be a dedicated pipeline from the CWB. Facility process water will consist primarily of cooling system blowdown and oil water separator effluent. Application Appendix at 33. 60. Following treatment, the Facility will discharge approximately 100,000 gallons per day of treated water to the CSB system. Treated water will also be used onsite for maintaining the trees and plants in the green spaces and for other nonconsumptive uses in accordance with the Facility Site discharge permits. Id. 61. Potable water will be used for several Facility uses, including fire water, service water, plumbing fixtures, combustion turbine make-up water, and demineralized water system make-up. It is estimated that 100,000 gpd (average of 70 gpm) of water will be utilized for plant operations.; .dI Applicant Ex. JPB-D at 28. Wherever practical, wastewater generated by these uses will be recycled. 62. Drains from plumbing fixtures will be collected in a sanitary sewer system and pumped or gravity fed to an existing CSB line. Application Appendix at 33. The Facility will not affect groundwater resources on the Site because all 63. construction activities will be located several feet above known aquifers and groundwater with the exception of foundations for the piles used for the heavy equipment. Heavy equipment will penetrate the shallow groundwater system within the surface mine fill but wi!! not affect its flow. Id.at 4; Applicant Ex. MF-D at 7. Surface waters will be impacted by construction of the Facility but will be 64. addressed with control measures that collect stormwater and best management practices to protect nearby and downstream surface waters. Applicant Ex. MF-D at 7. 65. No aquifers will be affected by the Facility, and there will be no injection of process or other waters. Applicant Ex. MF-D at 8. 67. The United States Fish and Wildlife Service has stated that no threatened or endangered species are known to exist on the Site. Application Appendix Ex. 23; Applicant Ex. JPB-D at 30-3 1. 68. The West Virginia Department of Natural Resources has indicated that they have no known records of State rare, threatened or endangered species and sensitive habitats within the Project area. Application Appendix Ex. 24; Applicant Ex. JPB-D at 31. 69. The Traffic Study indicates that during the construction phase the Project will have only a minor impact on the operation of the existing transportation network and 36 that the nearby intersections will also operate at an acceptable level per guidelines established by the DOH. Application Appendix Ex. 26 at 1-2. ESC Harrison County Power will address short-term recommendations 70. made in the Traffic Study to address any impacts during the construction phase. Application Appendix at 83; Application Appendix Ex. 26. 7 1. ESC Harrison County Power and its contractors will not change shifts or block roads with heavy haul deliveries while school buses are scheduled to be on roads within one mile of the Site. Applicant Ex. JPB-R at 13-14, Exhibit A at 6. During operation, the traffic associated with the Project will be limited to 72. operational and maintenance vehicles. It is anticipated that 30 vehicles making 23 peak hour trips will enter and exit the Site each day for operational activities, which will have vir iually no impact to the transportation network. Application Appendix Ex. 26 at 1. 73. Redevelopment of the Site should enhance property values. Application Appendix at 76. 74. The CWB has excess capacity and will supply water to the plant. Application Appendix at 35. 75. at 34-35. The Facility will connect to the CSB sewer system. Application Appendix CONCLUSIONS OF LAW The Project will provide wholesale electric service, and there will be no 1. direct financial impact to West Virginia retail ratepayers. ESC Harrison County Power filed a complete Application that satisfied the 2. requirements of the Siting Rules of the Commission. 3. ESC Harrison County Power demonstrated a sufficient interest in constructing the Project. First, ESC Harrison County Power has demonstrated that it has a legitimate business purpose in undertaking the Project and ESC Harrison County Power retained various technical experts and developed detailed information in support of its Application. Second, it has expended substantial time and economic resources to apply for a siting certificate, and to pursue various other required permits, and to obtain the property interests necessary to construct and operate the Project. Third, ESC Harrison County Power has committed to coordinating its activities with the Commission and other state and federal agencies. 37 Need for this Project has been established because it is in the public interest 4. to develop diversified sources of fuel to generate electricity, including alternatives such as natural gas; &additionalgeneration capacity is needed to meet PJM’s projected load forecast in light of the many coal-fired plant closures; it is in the public interest for West Virginia to participate in the interconnected electric system; and the ESC Harrison County Power’s base load combined cycle fully dispatched generating facility will assist in meeting the daily demand for electric service. 5. It is not in the public interest for this Commission to isolate West Virginia from the region. The power grid is interconnected, and to safeguard the availability of productive, well-maintained resources to our State’s residents, West Virginia must participate in the interconnected electric system. Different economic simulation models provided consistent and uncontested 6. results that there will be a significant economic gain to both the state and local economy from the operation of the Project. While approximately 0.3 to 0.6 percent (207 to 501 acres) of the area within 7. 20 miles of the Project will have some limited visibility of the Project, the impact of the presence of the Project and view of the Project will be minimally disruptive to the community. 8. The ESC Harrison County Power noise study complied with Commission requirements, and accurately portrayed ambient sound levels for the community near the Facility. Based upon the totality of the evidence presented to us, the Project’s 9. construction and operational sound levels are expected to be similar to existing ambient sound levels and noise impacts are not expected to be objectionable. 10. The Commission is satisfied that the ESC Harrison County Power Project will not cause any substantial problems or difficulties with respect to existing traffic patterns. 11. Because the Traffic Study shows only a slight increase in traffic after completion of the Project, the Commission concludes the Project will not have a significant or substantial impact on traffic in and around the Project area. 12. The Joint Stipulations, including the conditions contained therein, are reasonable and will be adopted. 38 13. Taken as a whole, the positive impacts of the Project relating to the various interests outweigh any negative impacts on the various interests in this matter. W.Va. Code 524-2- 11c. 14. In light of the significant tax revenues and other economic benefits that will accrue to Harrison County and the State from the Project, the Commission concludes that the PILOT and Lease agreements do not offend the public interest. W.Va. Code $24-2- 11c(c). 15. The record is clear that the construction of the facility will have a substantial positive impact on the local economy and local employment. Id. 16. Based on the entire record and the analysis contained in this Order, the Commission concludes that ESC Harrison County Power should be issued a siting certificate for this Project with the conditions adopted in this decision. ORDER IT IS THEREFORE ORDERED that ESC Harrison County Power is granted a siting certificate, pursuant to W.Va. Code 524-2-1 IC, for the construction and operation of a natural gas-fired wholesale electric generating facility of approximately 630 MW approximately 0.5 miles from the municipal boundary of Clarksburg, in Harrison County, including an approximately 1.8-mile 138 kV (less than 200,000 volts) related transmission support line, associated interconnection facilities, and other necessary appurtenances as fully described in the Application and discussed in this Order, subject to the following conditions: 1. At least 30 days prior to beginning construction ESC Harrison County Power shall provide the PSC notice of start of construction. 2. Prior to the Cominercial Operation Date (COD) Harrison County Power shall file a verified statement that the required detailed plans for the Harrison County Power project have been completed, reviewed and approved in accordance with the appropriate codes and standards and where required, under the supervision of a licensed professional engineer. 3. At least 30 days prior to beginning construction of the Project, Harrison County Power shall file a verified statement that certifies that required permits, approvals, certifications, notices, and consultations have been obtained, including the following: 39 a. PJM Interconnection Services Agreement b. State Historic Preservation Office (SHPO) Consultation c. United States Fish and Wildlife Service (USFWS) Section 7 Consultation d. WV DNR Lands Inquiry e. Department of the Army 404 Permit(s) f. State 401 Water Quality Certification g. WV DNR Stream Activity Permit h. Air Quality Permit from the West Virginia Division of Air Quality i. West Virginia National Pollutant Discharge Elimination System (NPDES) Permit j. Groundwater Protection Plan (GPP) k. Site Plan Approval and Grading Permit 1. Federal Aviation Administration (FAA) Notice of Construction or Alteration m. Construction Stormwater General Permit and Stormwater Pollution Prevention Plan n. West Virginia Department of Highways (WVDOH) IAR Engineering and Construction Agreement 0. Above ground Storage Tank Water Resources Protection Act and the Public Water Supply Protection Act approvals. Provided, however, with respect to the approvals and perinits set forth in p., q., and r. below it is recognized that one or more may not be available until immediately before the activity for which the approval or permit is issued, commences, in which event Harrison County Power shall file verified statements within a reasonable time after receipt certifying that the approval or permit has been obtained: p. Railroad Right of Way Encroachment Approvals q. Building Permits r. Highway Heavy Haul Permits 4. At least 30 days before operation of the Facility, Harrison County Power shall file a verified statement that certifies that all required perinits, approvals, certificates, notices and consultations required prior to the start of operation have been obtained, including the following: a. Stormwater General Permit and Stormwater Pollution Prevention Plan 40 b. c. d. e. 5. Spill Prevention Control and Countermeasures (SPCC) Plan Emergency Response Plan (Em) Pre-treatment/Discharge Permit - Sanitary Water System Connection Fuel for the Project will be delivered through a pipeline to the plant, constructed, operated and owned by a third party (the “Pipeline Project”). Prior to the beginning of construction on the Pipeline Project, ESC Harrison County Power shall file a verified statement that certifies that a binding contract(s) are or will be in place for: a. Installation and construction of adequate natural gas delivery points, including Federal Energy Regulatory Commission (FERC) certificates, if required, for new delivery points on interstate pipelines. b. Construction and operation of the pipeline necessary to deliver the fuel to the plant site, including all necessary measurement and pressure regulation equipment. e. A contracted fuel supply. 6. The verified statement filed in connection with Condition 5 above shall provide a verified statement of the pipeline contractor certifying that all options for, or rights of way, and all required permits necessary for the construction and operation of the Pipeline Project have been obtained. 7. Applicant shall plant in a staggered pattern along the southern border of the property from a location just east of the onsite pond up the slope to a point between Henry Ford Avenue and the northeast corner of the plant fence, and along the Henry Ford Avenue property line, evergreen and deciduous trees in accordance with the schedule attached hereto as Exhibit A. 8. Care of the trees and shrubs planted in accordance with Condition 7 shall be incorporated into the operations and maintenance plan for the site. Any such tree or shrub that does not survive will be replaced in kind. 9. Harrison County Power shall provide an independent expert report on the amount needed to decommission the facility less market or salvage value and post a Letter of Credit (“LoC”), purchase a bond 41 or surety, or place the present value of such an amount in an escrow fund prior to beginning operation. Harrison County Power recognizes that the plant value far exceeds the decommissioning costs in the first ten (IO) years of its service life. Nevertheless, the initial LoC, bond or surety, or escrow account shall be no less than $250,000 to cover the cost of soliciting and engaging a decommissioning company. In no case shall the decommissioning amount exceed the maximum value required by the lease agreement, which is $3 million. The report shall be updated thereafter as mutually agreed between Harrison County Power and the Harrison County Commission, but no less frequently then every ten (IO) years thereafter until the provision of the HCC Lease which requires a $3 million fund becomes operative. The decommissioning fund amount may vary over time depending on changes in the estimated market or salvage value of the Project, the estimated cost of dismantling the plant and the expected ongoing life of the Project. Harrison County Power shall provide the report to the Harrison County Commission and request its approval or concurrence of the evaluative expert and each of the periodic reports. The decommissioning fund shall not be part of Harrison County Power's assets. Within ninety (90) days of any report that requires a contribution to the decommissioning fund, Harrison County Power shall increase the LoC, or bond or surety, or make that contribution into an escrow account held by an agent pursuant to an escrow agreement between Harrison County Power and the Harrison County Commission. Reductions to, or withdrawal from, the decommissioning fund shall not be allowed sooner than ninety (90) days after the Harrison County Commission has been offered the opportunity to review the report. The methods for deposits to and disbursements from the decommissioning fund shall be established within and governed by the LoC, bond or surety, or escrow agreement. Furthermore, the LoC, bond or surety, or escrow agreement must clearly reflect the role of the Harrison County Commission and state that the obligations set forth in the agreement apply to Harrison County Power, its successors and assigns. Each report of the qualified independent third party shall also be filed with the Commission as a closed entry in this matter. The 42 Commission retains the right to hire its own evaluative expert to review any of the periodic reports and to take such further action within its jurisdiction as the Commission determines is necessary to protect the public interest. 10. Harrison County Power, and its contractors, shall not change shifts or block roads with heavy haul while school buses (elementary, middle or high school) are scheduled to be on the roads within 1 mile of the site. 11. Harrison County Power shall file proof of its exempt wholesale generator (EWG) status from FERC prior to commencing commercial operation. 12. The siting certificate shall become invalid if Harrison County Power has not commenced a continuous course of construction within five (5) years of the date the final certificate is granted or has not completed construction by the tenth year following the granting of the certificate without petitioning the Commission for approval to expand these time frames. 13. If Harrison County Power seeks to transfer its certificate, Harrison County Power is required pursuant to Siting Rule 7.1 to notify the Commission in writing of the identity of the transferee and submit an affidavit from the transferee attesting to the transferee’s willingness to abide by the terms of a siting certificate as issued. This condition applies at any time - not just in the operational stage. These conditions are also set forth at pages 5-9 of the Joint Stipulation attached to this Order as Appendix A. IT IS FURTHER ORDERED that the Joint Stipulation and Agreement for Settlement submitted by ESC Harrison County Power, Staff, and the Building Trades is adopted and attached to this Order as Appendix A. IT IS FURTHER ORDERED that the Joint Stipulation and Agreement for Settlement of Ohio Valley Jobs Alliance’s Claims submitted by OVJA, ESC Harrison County Power, Staff, and the Building Trades also filed is adopted and attached to this Order as Appendix B. IT IS FURTHER ORDERED that, pursuant to W.Va. Code §24-2-11c(h), all of the terms and conditions of this Order apply to any subsequent owners or operators of the ESC Harrison County Power Project. 43 IT IS FURTHER ORDERED that the Memorandum Agreement dated July 7, 2017, between ESC Harrison County Power, the North Central Building and Cnmtruction Trades Council, AFL-CIO, and the West Virginia State Building and Construction Trades Council, AFL-CIO is approved in relation to the ESC Harrison County Power Project. The Commission anticipates that all representations and commitments made by the parties therein will be kept by the parties. Approval of the Memorandum Agreement by the Commission does not mean the Cornmission is the proper forum to resolve any disputes that may arise under the Agreement. IT IS FURTHER ORDERED that upon entry hereof, this case shall be removed from the Commission's open docket. IT IS FURTHER ORDERED that the Executive Secretary of the Commission serve a copy of this Order by electronic service on all parties of record who have filed an e-service agreement, by United States First Class Mail on all parties of record who have not filed an e-service agreement, and on Staff by hand delivery. A Trite Copy, 'Teste, Ingrid Ferrell Executive Secretary SMSIsm 170036cf.doc 44 Appendix A PUBLIC SERVICE COMMISSION OF WEST VIRGINIA CHARLESTON ESC H A W S O N COUNTY POWER, LLC Application for a Siting Certificate to Authorize the Construction and Operation of a Wholesale Electric Generating Facility in Harrison County, West Virginia JOINT STIPULATION AND AGREEMENT FOR SETTLEMENT Pursuant to W, Va. Code $9 24-1-7, 24-2-1(c) and 24-2-1 I C and Rules 12 and 13 of the Public Service Commission of West Virginia’s (the “Commission”) Rules of Practice and Procedure, Harrison County Power, LLC (“Harrison County Power”), the Staff of the Public Service Commission of West Virginia (“Staff’), the West Virginia State Building and Construction Trades Council, AFL-CIO (“Building Trades,” and together with Harrison County Power, Staff,and the Building Trades, the “Stipulating Parties”) join in this Joint Stipulation and Agreement for Settlement (“Joint Stipulation”) and propose and recommend to the Commission that it approve and adopt this settlement among the Stipulating Parties of all issues raised in Case No. 17-0036-E-CS, on the terms and conditions set forth below, The Joint Stipulation resolves all of the issues in this proceeding, and recommends that the Commission grant Harrison County Power its requested electric generating facility siting certificate and any and all other necessary approvals required by the Commission for the construction and operation of a wholesale electric generating facility, including the related transmission support line, associated interconnection facilities, and other necessary appurtenances, subject to the conditions set forth in this Joint Stipuiation, In support of the Joint Stipulation, the Stipulating Parties submit the following: I. I. PROCEDURAL HISTORY On January 17, 2017, Harrison County Power filed with the Commission an Application for a Siting Certificate pursuant to West VirFinia Code $9 24-2-lIc) and 24-2-1 I C to authorize the construction and operation of a natural-gas fired wholesale electric generating facility of approximately 630 MW (the “Facility” or the “Project”) in Harrison County including an approximately 1.8 mile 138 kV (less than 200,000 volts) related transmission support line, associated interconnection facilities, and other necessary appurtenances as more particularly described in the Application and attached documents. 2. On January IS, 201 7, the Commission issued an Order requiring Harrison County Power to publish a Notice of Filing one time in a newspaper of general circulation in Harrison and Kanawha Counties. Harrison County Power caused the Notice of Filing to be published in The Charleston Gazette on January 25, 2017, and in The Exponent Telegram on January 24, 201 7, and tiIed the corresponding affidavits of publication with the Commission on February 6, 2017, and February 13, 2017, respectively. 3. On February 13, 201 7, the Building Trades filed a petition to intervene, 4. On February 21, 2017, Staff filed its Initial Joint Staff Memorandum, and on February 22,2017, Staff filed its Further Staff Memorandum. 5. On February 23, 2017, Ohio Valley Jobs Alliance (”OVJA”) fled a Protest, Petition to Intervene, and Request for Formal Hearing. 6. By Order dated March 30, 2017, the Commission granted the Building Trades’ and OVJA’s petitions to intervene and established a procedural schedule for the matter which called for the filing of Harrison County Power’s direct testimony on March 31, 2017, the filing of Staff and Intervenor direct testimony and rebuttal testimony to Harrison County Power on May 26, 2017, a site visit and public comment hearing on June 6, 2017, the filing of Harrison 2 County Power’s rebuttal testimony, and the filing of Staffs and Intervenors’ rebuttal testimony to each other on June 30, 2017, a deadline to file a proposed order of witnesses for the evidentiary hearing and any motion(s) to excuse witnesses on July 7, 2017, and an evidentiary hearing to begin on July 1 1, 20 17, and coritinuing on July 12 and I 3, 201 7, if necessary. The Order also required Harrison County Power to cause to be published, one time in Harrison and Kanawha Counties, a Notice of Public Comment and Evidentiary Hearing. The Order also granted the waiver of certain certificate filing requirements and certain other Commission filing, reporting, and other requirements that are specific to regulated public utilities. 7. Harrison County Power filed the Direct Testimonies of John P. Black, P.E., Andrew W. Dorn, IV, Matthew J. Dom, CPA, Tom S. Witt, Ph.D., Matthew Fluharty, P.E., Timothy S. Kirk, P.E., and Carol Colby on March 31,2017. 8. On various dates, the Ststf’f filed discovery requests to Harrison County Power, and Harrison County Power answered the same, on various dates, by discovery responses. 9. On May 25, 201 7, the Building Trades filed the Direct Testimony of Steve White and the Direct Testimony of Michael Jin. 10. On May 26, 2017, Staff filed the Direct Testimonies of Josh Allen, Eric F. deCruyter, and Donald E. Walker, In its Direct Testimony, Staff recommended the Commission adopt various conditions to a Siting Certificate granted Harrison County Power in this case. 11. Also on May 26, 2017, OVJA filed the Direct Testimonies of Jon A. Pollack, James Russel Thomas, Stephen Baker McElroy, and Emily Virginia Rockwell. 3 12. On May 3 I , 201 7, and June 1, 201 7, the Parties jointly filed the Joint Viewpoint List, and the Joint Viewpoints and Viewpoint Descriptions, respectively, for the Conmission Site visit. 13. On June 2, 2017, Harrison County Power filed an affidavit of publication reflecting that publication of the Notice of Public Comment and Evidentiary Hearing occurred on May 23, 2017, in The Charlesfon Gazelle (Kanawha County); on June 13, 2017, Harrison County Power filed an affidavit ofpubIication reflecting that publication of the Notice of Public Comment and Evidentiary Hearing occurred on May 23, 2017, in The Exponent Telegram (Harrison County). 14. The site visit was conducted as scheduled on June 6, 2017, and the public comment hearing was also held as scheduled on June 6,201 7. IS. Harrison County Power fiied the Rebuttal Testimonies of John P. Black, P.E., Andrew W. Dom, IV, and William Hanna, P.E. on June 30,2017. 16, On July 3, 2017, OVJA, Harrison County Power, Staff and the Building Trades filed a "Joint Stipulation and Agreement for Settlement of Intervenor Ohio Valley Jobs Alliance's Claims" which proposed and recommended to the Commission the settlement of the claims OVJA had made in its Protest, Petition to Intervene and Request for Formal Hearing and other documents filed in this proceeding. Also on July 3, 2017, OVJA filed a "Notice of Voluntary Withdrawal (Without Adjudication) of Intervenor Ohio Valley Jobs Alliance's Claims" in this proceeding. 17. During the pendency of this case, over 537 letters and postcards in support of the Project have been filed with the Commission, with only one letter or postcard in opposition to the Project having been filed, The single letter or postcard in opposition was by intervenor OVJA that has voluntarily withdrawn. 4 18, The Stipulating Parties have engaged in settlement discussions encompassing the issues raised in this case. Based on those discussions, the Stipulating Parties have reached agreement that a siting certificate for the Project should be granted to Harrison County Power with the conditions being proposed to the Commission herein, and have reached the settlement embodied in this Joint Stipulation which they recommend to the Commission for adoption. 11. 19. SETTLEMENT The Stipulating Parties agree that the Cornmission should approve the Memorandum Agreement that Will be filed in the near future between Harrison County Power, I L C , the North Central West Virginia Building and Construction Trades Council, AFL-CIO, and the Building Trades (collectively the “Signatories”), and make clear that the Cornmission anticipates that all representations and commitments made by the Signatories therein shall be kept by the Signatories. The Signatories further agree that the Commission should make clear that its approval of the Memorandum Agreement does not mean the Commission is the proper forum to resolve any disputes that may arise from operating under such Agreement. 20. The Stipulating Parties agree and recommend to the Commission that the Siting Certificate requested by Harrison County Power in this case be granted to Harrison County Power, and that the Siting Certificate be subject to the following conditions: I . At least 30 days prior to beginning construction ESC Harrison County Power will provide the PSC notice of start of construction. 2. Prior to the Commercial Operation Date (COD) Harrison County Power shall file a verified statement that the required detailed plans for the Harrison County Power project have been completed, reviewed and approved in accordance with the appropriate codes and standards and where required, under the supervision of a licensed professional engineer. 5 3. At least 30 days prior to beginning construction of the Project, Harrison County Power shall file a verified statement that certifies that required permits, approvals, certifications, notices, and consultations have been obtained, including the following: a. PJM [nterconnection Services Agreement b. State Historic Preservation Office (SHPO) Consultation C. United States Fish and Wildlife Service (IJSFWS) Section 7 Consultation d. CVV DNR Lands Inquiry e. Department of the Army 404 Permit(s) f. State 401 Water Quality Certification g, WV DNR Stream Activity Permit h. Air Quality Permit from the West Virginia Division of Air Quality West Virginia National Pollutant Discharge Elimination System 1. (NPDES) Permit j. Groundwater Protection Plan (GPP) k. Site Plan Approval and Grading Permit 1. Federal Aviation Administration (FAA) Notice of Construction or A 1terat i on m. Construction Stormwater General Permit and Stormwater Pollution Prevention Plan n. West Virginia Department of Highways (WVDOH) IAR Engineering and Construction Agreement 0. Above ground Storage Tank Water Resources Protection Act and the Public Water Supply Protection Act approvals. Provided, however, with respect to the approvals and permits set forth in p., q. and r. below it is recognized that one or more may not be available until immediately before the activity for which the approval or permit is issued, commences, in which event Harrison County Power shall file verified statements within a reasonable time after receipt certifying that the approval or permit has been obtained: p. Railroad Right of Way Encroachment Approvals q. Building Permits r. Highway Heavy Haul Permits 4. At least 3 0 days before operation of the Facitity, Harrison County Power shall file a verified statement that certifies that all required permits, approvals, certificates, notices and consultations required prior to the start of operation have been obtained, including the following: 6 a. Storrnwater Generaf Permit and Stormwater Pollution prevention Plan b. Spill Prevention Control and Countermeasures (SPCC) Pian c. Emergency Response Plan (ERP) d. Pre-treatmentlDischge Permit - Sanitary e. Water System Connection 5 . Fuel for the Project will be delivered through a pipeline to the plant, constructed, operated and owned by a third party (the “Pipeline Project”). Prior to the beginning of construction on the Pipeline Project, Harrison County Power shall file a verified statement that certifies that a binding contract(s) are or will be in place for: a. Installation and construction of adequate natural gas delivery points, including Federal Energy Regulatory Commission (FERC) certificates, if required, for new delivery points on interstate pipelines. b. Construction and operation of the pipeline necessary to deliver the fuel to the plant site, including all necessary measurement and pressure regulation equipment. c. A contracted fuel supply. 6. The verified statement filed in connection with Condition 5 above shall provide a verified statement of the pipeline contractor certifying that all options for, or rights of way, and all required permits necessary for the construction and operation of the Pipeline Project have been obtained. 7. Applicant shall plant in a staggered pattern along the southern border of the property from a location just east of the onsite pond up the slope to a point between Henry Ford Avenue and the northeast corner of the plant fence, and along the Henry Ford Avenue property line, evergreen and deciduous trees in accordance with the schedule attached hereto as Exhibit A. 8. Care of the trees and shrubs planted in accordance with Condition 7 shali be incorporated into the operations and maintenance plan for the site. Any such tree or shrub that does not survive will be replaced in kind. 9. Harrison County Power shall provide an independent expert report on the amount needed to decommission the facility less market or salvage value and post a Letter of Credit (“LoC”), purchase a bond or surety, or place the present value of such an amount in an escrow fund prior to beginning operation. Harrison County Power recognizes that the plant value far exceeds the decommissioning costs in the first ten (10) years of its service life. Nevertheless, the initial LoC, bond or surety, or 7 escrow account shall be no less than $250,000 to cover the cost of soliciting and engaging a decommissioning company. In no case shall the decommissioning amount exceed the maximum value required by the lease agreement, which is $3 million. The report shall be updated thereafter as mutually agreed between Harrison County Power and the Harrison County Commission, but no less frequently then every ten ( I 0) years thereafter until the provision of the HCC Lease which requires a $3 million fund becomes operative. The decommissioning fund amount may vary over time depending on changes in the estimated market or saIvage value of the Project, the estimated cost of dismantling the plant and the expected ongoing life of the Project. Harrison County Power will provide the report to the Harrison County Commission and request its approval or concurrence of the evaluative expert and each of the periodic reports. The decommissioning fund shall not be part of Harrison County Power's assets. Within ninety (90) days of any report that requires a contribution to the decommissioning fund, Harrison County Power will increase the LoC, or bond or surety, or make that contribution into an escrow account held by an agent pursuant to an escrow agreement between Harrison County Power and the Harrison County Commission, Reductions to, or withdrawal from, the decommissioning h n d shall not be atlowed sooner than ninety (90) days after the Harrison County Commission has been offered the opportunity to review the report. The methods for deposits to and disbursements from the decommissioning fund shall be established within and governed by the LoC, bond or surety, or escrow agreement. Furthermore, the LoC, bond or surety, or escrow agreement must clearly reflect the role of the Harrison County Commission and state that the obligations set forth in the agreement apply to Harrison County Power, its successors and assigns, Each report of the qualified independent third party will also be filed with the Commission as a closed entry in this matter. The Commission retains the right to hire its own evaluative expert to review any of the periodic reports and to take such further action within its jurisdiction as the Commission determines is necessary to protect the public interest. 10. Harrison County Power, and its contractors, shall not change shifts or block roads with heavy haul while school buses (elementary, middle or high school) are scheduled to be on the roads within 1 mile of the site. 11. Harrison County Power shall file proof of its exempt wholesale generator (EWG) status from FERC prior to commencing commercial operation. 8 12. The siting certificate shall become invalid if Harrison County Power has not commenced a continuous course of construction within five (5) years of the dare the final certificate is granted or has not completed construction by the tenth year following the granting of the certificate without petitioning the Commission for approval to expand these time frames. 13, if Harrison County Power seeks to transfer its certificate, Harrison County Power is required pursuant to Siting Rute 7.1 to notify the Commission in writing of the identity of the transferee and submit an affidavit from the transferee attesting to the transferee's willingness to abide by the terms of a siting certificate as issued. This condition applies at any time - not just in the operational stage. 21. The Stipulating Parties agree that the terms and conditions of the PILOT agrccmcnt between Harrison County Power, the County Cornmission of Harrison County, West Virginia (Harrison County Commission), the Board of Education of Harrison County, West Virginia, the Sheriff of Harrison County, West Virginia, and the Assessor of Harrison County, West Virginia, the Lease Agreement between the Harrison County Commission and Harrison County Power, and the Industrial Access Road Agreement between the West Virginia Department of Transportation, Division of Highways and the Harrison County Commission do not offend the public interest and the construction and operation of the facility will result in a substantial positive impact on the local economy and local employment, 22. The Stipulating Parties agree that nothing in this Joint Stipulation shall be interpreted to preclude any of the Stipulating Parties from taking any position it may choose on any of the issues discussed herein in other siting certificate cases, 23. This Joint Stipulation is entered into subject to the acceptance and approval of the Commission, and will have no effect whatsoever until and unless approved by the Commission in at1 of its material terns. It results from a review of all filings in this case, the Stipulating Parties' prefiied testimony, and discovery and discussion. 9 It reflects compromises by the Stipulating Parties and the withdrawal of their respective positions asserted in this case, and is being proposed to avoid costly litigation between the Stipulating Parties. The Stipulating Parties propose this Joint Stipulation without adopting any of the compromise positions [hat may be set forth herein as regulatory principles applicable to future proceedings. The Stipulating Parties support and recommend this Joint Stipulation as being in the public interest and as a fair, reasonable, and complete resolution of all the issues raised in this proceeding. The Stipulating Parties acknowledge that it is the Commission’s prerogative to accept, reject, or modify MY stipulation. In the event that the Joint Stipulation is modified or rejected by the Commission, it is expressIy understood that the Stipulating Parties are not bound to accept the Joint Stipulation as modified or rejected, and that they may avail themselves of whatever rights are available to them under law and the Commission’s Rules of Practice and Procedure. WHEREFORE, the Stipulating Parties, on the basis of the foregoing, respectfully request the Commission issue findings of fact and conclusions of law granting Harrison County Power LLC its Siting Certificate consisting of a natural-gas fired wholesale electric generating facility of approximately 630 M W in Harrison County including an approximately 1.8 mi[e 138 kV (less than 200,000 volts) related transmission support line, associated interconnection facilities, and 10 other necessary appurtenances as more particularly described in Harrison Count) I'o\icer's Application. subject t o the conditions set forth in this Joint Stipulation. I;+V Respectfully submitted this day of July, 20 1 7. _- -- Susan J. Riggs(lbV State Bar #5246). SPILMAN THOMAS & BATTLE, PLLC Spiiman Center 300 Kannwha Boulevard, East Charleston, West Virginia 25301 { 304) 3.10-383 1 Ifeinberr~~spiImsnlau..coin s&g&?spi Iii~anlaiv.corn STAFF OF TIE PUBLlC COMMISSION OF WEST 'I'IRGmI.4 SERVICE N1 Brooks Street Charleston, West Virginia 25301 (304) 330-0763 Ibuin t'tiecdpsc.st;ltc.~ ~ 1 . 5 WES7 VIRGINIA STATE Bt'll-DIN<; ANI) CON STRtf CTION TRADES COI.JNC1L {AFL-CIO) Vincent Trivelli (WV Statc Bar k8015) The Law Oftice of Vincent 'frivclli, PLLC 178 Chancery Row Murpantown, WV 26505 (504) 29 1-5223 \. mtr1\