Sidewalk Project Plan and Progress Blocks identified for sidewalk repair through 311 request backlog Began with 1,471 locations from 311 request backlog (received prior to December 31, 2016). Project underway Full block inspections have been done for approximately 75% of the locations, and identified two types of conditions: Future projects  Blocks where spot repair would be pursued for the full block due to overall good or fair conditions  Blocks where full replacement is recommended in the future due to overall poor condition The City issued an RFP for inspections to assist in completing the systematic inspections and is pursuing contracts with three engineering design firms. 262 79 132 Blocks identified for Blocks identified for full spot repair replacement Source: Public Works 42 Curb Ramps Projects Underway •117 corners were completed by March 2018 •120 corners began in August 2018 Remaining Volume •1,830 unramped corners remain to be reconstructed •Estimated timeframe for completion is 4 years 43 Source: Public Works Sidewalk Repair Requests Backlog Requests (Prior to 12/31/16) Spot Repair Blocks Underway (Year 1 GO Bond) Spot Repair Blocks Remaining Blocks Identified for Future Replacement 111 11 North of the river 232 River to 39th Street 502 32 38 67 39th Street to 85th Street 653 47 74 52 South of 85th Street 84 39 2 44 Source: Public Works Sidewalk Repair Progress: Year 1 Track the progress of current backlogged spot repairs at: KCMO.gov/sidewalks 45 Source: Public Works