20180917-3025 FERC PDF (Unofficial) 09/17/2018 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C. 20426 OFFICE OF ENERGY PROJECTS In Reply Refer To: OEP/DG2E/Gas Branch 4 Atlantic Coast Pipeline, LLC Atlantic Coast Pipeline Dominion Energy Transmission, Inc. Supply Header Project Docket Nos. CP15-554-000, CP15-554-001, and CP15-555-000 September 17, 2018 Mr. Matthew R. Bley Director, Gas Transmission Certificates Dominion Energy Transmission, Inc. 707 East Main Street Richmond, VA 23219 Re: Lifting of Stop Work Order Dear Mr. Bley: On August 10, 2018, Commission staff directed Atlantic Coast Pipeline, LLC (Atlantic) and Dominion Energy Transmission, Inc. (DETI) to cease construction of the Atlantic Coast Pipeline (ACP) and Supply Header Project (SHP) as a consequence of the United States Court of Appeals for the Fourth Circuit’s order vacating certain federal authorizations required for the projects. Specifically, the court vacated a right-of-waypermit by the Department of the Interior’s National Park Service (NPS) authorizing the construction of the ACP across the Blue Ridge Parkway, and the court provided rationale for its May 15, 2018 order vacating the Incidental Take Statement issued by the U.S. Fish and Wildlife Service (FWS). On September 11, 2018, the FWS issued a revised Biological Opinion (BO), which included a modified Incidental Take Statement, for the ACP and SHP.1 Additionally, on September 14, 2018, the NPS issued a new right-of-way permit for crossing the Blue Ridge Parkway.2 1 2 See FERC accession no. 20180917-3001. See FERC accession no. 20180917-5034. 20180917-3025 FERC PDF (Unofficial) 09/17/2018 Construction activities along project areas which had previously received a notice to proceed may now continue. Atlantic and DETI are required to comply with the Reasonable and Prudent Alternatives, Terms and Conditions, Monitoring and Reporting Requirements, and Conservation Recommendations set forth in the BO. Further, prior to resuming previously authorized construction activities across federal lands or waters of the United States, Atlantic and DETI shall provide written concurrence from the Forest Service and U.S. Army Corps of Engineers that the revised BO is consistent with those agencies’ respective authorizations for the ACP and SHP. Sincerely, Terry L. Turpin Director, Office of Energy Projects cc: Docket Nos. CP15-554-000, CP15-554-001, and CP15-555-000 2 20180917-3025 FERC PDF (Unofficial) 09/17/2018 Document Content(s) CP15-554 and CP15-555 Letter_signed.PDF...............................1-2