NO. LND CV 15 60566378 SUPERIOR COURT LANDMARK DEVELOPMENT . GROUP LLC, ET AL. JUDICIAL DISTRICT OF HARTFORD V. LAND USE DOCKET EAST LYME WATER AND SEWER COMMISSION NOVEMBER 27, 2018 MOTION FOR JUDGMENT1 Plaintiffs Landmark Development Group LLC and Jarvis of Cheshire LLC (collectively, ?Landmark?) hereby move for the entry of judgment in this matter, speci?cally an order to the defendant Commission to conditionally grant Landmark's 2012 sewer capacity application for 118,000 gallons per day, with the ?nal, actual allocation being the gallons per day needed to support a Preliminary Site Plan, when approved by the East Lyme Zoning Commission. This Motion is made at this time because (1) this Court?s July 6, 2016 decision, that the Commission must grant Landmark ?suf?cient capacity to further the development of their project" is now ?nal; (2) the Appellate Court, 184 Conn. App. 303, 306 n.2, held that the Commission on remand "must grant" (original emphasis) the application; (3) as a matter of law, ?suf?cient capacity to further the development? has only one meaning the sewer capacity to support whatever development plan is approved by East Lyme's land use (wetlands and zoning) process not the land use or residential density that the defendant Sewer Commission deems acceptable; (4) there is, therefore, only one legal remedy that this Court can grant at this time in this administrative appeal; and (5) in the past several weeks, the Commission has expressly stated its disagreement with and intent to resist this Court?s order, defy this Court again, and continue to violate Landmark's rights. 1 Attorney Roger Reynolds, representing intervenors Friends of the Oswegatchie Hills Nature Preserve, Inc. and Save the River?Save the Hills, Inc, has not appeared in this docket number, but in a companion case, and is copied in the Certi?cation of Service. 7123541 Recited below, supported by an Affidavit of Glenn Russo and public record exhibits and the record of this appeal as on ?le, are the relevant facts and a legal analysis regarding why this Court must enter judgment at this time. I. RECAP OF RELEVANT COMMISSION ACTIONS SEPTEMBER 17 TO NOVEMBER 13, 2018. This Court is fully familiar with the facts of this matter, from the early 2000's, when East Lyme officials ?rst stated their intent to block multi-farnily/ affordable housing development by Landmark by denying sewer access;2 through the town's denial that any of Landmark?s property was in the sewer service district (overruled by DEEP in 2004); the 2005 denial of any sewer service (overruled by Judge Frazzini in 2011); the Commission?s contention in 2012 that it had no capacity for Landmark because all of the town's available sewer capacity was already allocated to others (overruled by this Court); the allocation in March 2014 of 13,000 GPD, based on the towns? three acre lot size zoning which had already been repealed (invalidated by this Court); the October 2014 allocation of 14,434 GPD, based on a supposedly ?scienti?c formula" but using manipulated data to yield a patently absurd and illegal result (invalidated by this 2 The record of this appeal (Commission's Appellate Court Record, p. A421, contains minutes of a February 1, 2001 phone call between Town officials and land use attorney Robert Fuller. Those minutes state in part: 1. NO AVAILABILITY FOR WATER AND SEWER Not in sewer shed, commitment elsewhere for availability. This plan would consume a lot of sewer and would require an extension. Without water and sewer, cannot get affordable housing project through. WATER AND SEWER COMMISSION HAS NO OBLIGATION TO EXTEND TO PROPERTY DOES NOT FALL UNDER AFFORDABLE HOUSING ACT. Atty. Fuller stated that the Zoning Commission needs a basis for denial. He suggested including the water and sewer report, addressing traf?c and environmental, and the Flaming Commission's report in the record. Court); and ?nally through three years, 2013~l6, when the Commission repeatedly lied to this Court, claiming its available capacity was 130,000 to 225,000 GDP, while simultaneously, and without public notice, allocating 166,000 GPD to the nearby Gateway development and then justifying that action by asserting that the Town plainly had such ample capacity that a capacity study and an application were unnecessary. Enough. On July 6, 2016, this Court held, based on the Commission?s Gateway subterfuge, that the I October 2014 allocation of 14,434 GPD to Landmark was an abuse of discretion and ordered the Commission to grant Landmark ?suf?cient capacity to further" its development. Exh. A. In August 2018, the Appellate Court af?rmed this Court's decision, 184 Conn. App. 303, Exh. B. On October 31, 2018, the Supreme Court denied further review, Exh. C, making this Court's decision a final order. The following undisputed facts have occurred since the Appellate Court decision, and are supported by attached public records exhibits and Mr. Russo's Af?davit: 1. In September 2018, while the Commission's certi?cation petition in the Supreme Court was pending, Landmark became concerned again that the Commission would try to undermine the Appellate Court ruling by continuing to allocate sewer capacity to Gateway and other users, and then asserting that it had insufficient capacity for Landmark. As a result, on September 17, 2018, Landmark ?led with the Commission a letter asking that the Commission approve Landmark?s application. Exh. D. 2. In response, at its meeting on September 25, 2018, the Commission, without any notice or hearing, adopted an "Interim Sewer Connection Procedure," Exh. E, which in relevant part states (emphasis added): WHEREAS, on August 21, 2018, the Appellate Court issued its decision (?Decision") on the Commissions? appeal, which upheld the Trial Court Memorandum of Decision, and held that the Commission is required to perform a sewer capacity analysis when considering applications to connect to the East Lyme sewer system;3 and WHEREAS, the Commission disagrees with the Decision and has ?led a petition for certi?cation to the Connecticut Supreme Court, which is currently pending; and WHEREAS, by a letter dated September 17, 2018, Landmark requested that the Commission approve an allocation for its full 118,000 sewer capacity request, pending ?nal resolution of its appeal; and WHEREAS, neither the Trial Court nor the Appellate Court held that Landmark was entitled to the hill amount of its capacity request, and the proceedings are stayed until the Supreme Court acts on the Commission's petition for certi?cation. While reserving all of its rights set forth during the appeal process, the Commission nevertheless does not want to ignore the Trial Court and the Appellate Court holding that require a sewer capacity analysis by done in conjunction with a sewer connection permit application. BE IT THEREFORE RESOLVED, that the East Lyme Water and Sewer Commission, acting as the Town?s Water Pollution Control Authority, hereby enacts the following interim procedure: 1. An application to connect to the East Lyme sewer system for a project that either requests a connection for more than 20 residential units or requires more than 5,000 gallons per day of sewage treatment capacity, shall also require an application for determination of sewer capacity pursuant to General Statues 7?246a;4 2. Said application for determination of sewer capacity shall be submitted either prior to or contemporaneously with a sewer connection application; 3. An application to connect to the East Lyme sewer system may not be granted if the Commission determines that there is not adequate sewer capacity for the proposed use of land. BE IT FURTHER RESOLVED that the above procedure does not re?ect o?icial policy or procedure of the Commission or the Town of East Lyme. 3 In fact, the Appellate Court opinion says nothing of the kind, and the Resolution contains no citation. 4 General Statutes 7~246a already requires an application for a sewer capacity allocation. Rather, it is adopted on an interim basis only in direct response to the Appellate Court Decision, and shall be in place only during the pendency of the Landmark sewer capacity appeal process. In enacting this interim procedure, the Commission does not agree with the holdings of the Trial Court Memorandum of Decision or the Appellate Court Decision. Any ?ndings made pursuant to this interim procedure available sewer capacity, etc.) shall be for the purposes of that sewer capacity application only, and shall not be adopted, incorporated or made part of the record in the pending Landmark sewer appeal. 3. in September 2018, Commission Chair Mark Nickerson was quoted in The Day newspaper as saying that, "The judges can't force us to put sewer in there," and that extending sewer to Landmark would constitute "an unsuitable use." Exh. F. 4. On October 24, 2018, Landmark ?led a renewed Freedom of Information Act request, seeking disclosure of all applications or requests for more than 5,000 GPD of sewer capacity, see Exh. G. 5. In response to Landmark's 01A request, the Commission provided an application ?led by Gateway for the commercial use portion of its development, a Costco store, requiring 7,650 GPD of capacity; the application was ?led under General Statutes 7-246a, and the ?interim procedure." 6. Also in response to the OIA request, the Commission provided a copy of an ?application? ?led by Pazzaglia Construction, Exh. H, for 86,250 GPD, for a [sic] development. This application was not accompanied by any site plan or any documents demonstrating that it is an actual development plan, or any evidence of compliance with General Statues 8?30g. 7. At a Commission hearing on November 13, 2018, Landmark ?led the attached letter, Exh. I, clarifying that if the local land use process results in a site plan approval that requires less than 118,000 GPD, Landmark will accept that allocation. 8. The Commission ignored Landmark's request, processed the Costco application under its interim procedure, and approved the Costco application without making any ?nding, as required by 1] 3 of its own interim procedure (Exit. E), as to the town?s overall available sewer capacity. Exh. (minutes of Commission hearing, November 13, 2018). 9. At its regular meeting on November 13, 2018, the Commission scheduled a special meeting for December 11, to consider what criteria it will devise and use to act on Landmark?s application on remand. Russo Af?davit, Exh. L, 11 4. 10. During the November 13 discussion, Chair Nickerson stated that action on Landmark would be based on "What is fair, given the size of our town. Russo Af?davit, Exh. L, 5. 11. During the discussion, Town Attorney Zamarka told the Commission that it had "wide discretion" in acting on Landmark, and that the Commission's only obligation is to grant capacity ?between 14,000 and 118,000. . . Exh. at 3. 12. At the November 13 meeting, contradicting this Court's 2016 ruling that sewer commissions do not control land use, Attorney Roger Reynolds, representing environmental intervenors, advocated that the Commission base the sewer allocation on controlling land use, by granting capacity for 110 residential units (about 20,000 GPD), that being the "average size? of a 8~30g affordable housing development. Russo Affidavit, Exh. L, 11 6. 13. At the November 13 meeting, the Commission discussed action in January 2019 on other sewer capacity applications, including 120 additional residential units for Gateway (and thus above its 275 units 166,000 and the above?mentioned Pazzaglia application. Russo Af?davit, Exh. L, 11 7. 14. In this discussion, none of the Commissioners or the Town Attorney discussed giving Landmark's application, which dates to 2012, priority over applications ?led later, much less in 2018. Russo Af?davit, Exh. L, 1] 9. 15. At this time, the Town of East Lyme has ample sewer capacity to conditionally grant Landmark's application without impacting other users: the Appellate Court decision, 184 Conn. App. at 317, based on data to 2014, found that the Town has at least 358,000 GPD, minus the Gateway allocation, estimated at 166,000 GPD, leaving 200,000; however, on November 13, Sewer Administrator Kargl stated that the Gateway residential portion is actually only using "about half" of its allocated capacity (Russo Af?davit, Exh. L, 1] 8), which would add more than 50,000 GPD to the Town's available capacity, making nearly 300,000 GPD available; this Court may take judicial notice of Exh. M, which shows that in 2016, the Town's total average discharge was 785,390 GPD, down from 1,089,279 in 2013, and the Town was using only 50.1 percent of total New London treatment plant capacity; and in November 2017, the total state facility ?ow was only 164,009, which under the formula accepted by Sewer Administrator Kargl in his 2015 deposition would result in: Town capacity after State set aside (1.5 million - 468,000) 1,022,000 Total ?ow, October 2017 running average 822,550 State use 164,000 Town use (822,550 - 164,000) 658.550 Available to Town 363,450 However, this calculation is very conservative, because the State facility use 0f164, 000 GPD is actually part of the 468,000 deducted??om the 1.5 million GPD available to the Town. So if this adjustment is made, the own?s current available capacity is 52 7, 45 0 GPD. 16. In addition, this Court should bear in mind that the State of Connecticut has a contract to use 468,000 of East Lyme's available 1,500,000 GPD at the New London treatment plant, but historically has used no more than 60 percent of this amount, and in recent years, between 30 and 40 percent. As a result, East Lyme is in no danger of exceeding its total treatment plant capacity. 17. The record of this appeal, supplemented by facts of the past 60 days, demonstrate that Landmark's land is in the Town's sewer service district; the Town has approved an extension of the public sewer line to two locations which abut Landmark's land, such that Landmark does not need new permission to extend the sewer system to connect to the sewer system; (0) there is ample capacity to grant Landmark's application, without disenfranchising others; through six years of hearings and remands, the Commission has never identi?ed any engineering issue with respect to Landmark physically connecting to the public system; Landmark has a ?nal court order to the Commission that it grant Landmark "suf?cient capacity? to proceed with its development; and the Commission disagrees with and intends to violate this court order. 11. BASES FOR ENTRY OF JUDGMENT 1. This case is an administrative appeal. It is axiomatic that in an administrative appeal, if the record makes it clear that there is only one remedy that will remedy the defendant?s violation, the trial court is empowered and obligated to grant that remedy. See, e. g, home v. Zoning Commission, 178 Conn. 198 (1979). 2. The Appellate Court, 184 Conn. App. at 306 n.2, held that the Commission "must grant" Landmark's application, and without need for further evidentiary determination or discretionary action. 3. This Court has ruled that the so-called "Forest Walk" factors are inapplicable to this case, given the Commission's conduct. Thus, at this point, the Commission cannot act on Landmark's application by devising a new formula or ratio based on acreage, proportionality, or similar factors. 4. It is also clearly established that the Commission cannot allocate sewer capacity based on controlling land use, such as density. 5. This Court's order to the Commission is not to pick a number between 14,434 and 118,000 GPD, but to grant Landmark what it needs to proceed with its land use applications. At this time, "suf?cient capacity" for Landmark?s development is not a matter of Commission discretion because the Town has ample capacity to grant Landmark's application, and may not use the allocation to control density. 6. At this time, Landmark's application, pending since 2012, must be given priority as against Gateway's application for sewer, which occurred after Landmark's, as well as newly- ?led applications. The Commission cannot undermine Landmark's rights by giving away capacity while this case proceeds.5 7. Landmark is entitled to be treated equally with Gateway, but in fact requests substantially less gallonage than Gateway even though Landmark's parcel is much larger: while Gateway has been approved (166,000 GPD) for 11.0 percent of the Town's total allocation, Landmark (at 118,000) seeks only 7.8 percent, and thus Landmark's application is for 30 percent less than Gateway. 8. Sewer Administrator Kargl, in 2015, testi?ed that the Town had so much available capacity that Gateway?s application did not even require a review process; Landmark is now entitled to equal treatment. 9. This court has inherent authority to enforce its own orders. The Commission is poised to Violate this Court's order. For these reasons, Landmark moves that this Court enter judgment, directing the defendant Commission to grant Landmark's sewer capacity application, and preserve that allocation until Landmark obtains Preliminary Site Plan approval, at which time the allocation shall be modi?ed to the amount needed to support that Site Plan. 5 Landmark?s appeal of the East Lyme Zoning Commission's 2015 denial of a zone change and Preliminary Site Plan is pending before Judge Berger. PLAINTIFFS, LANDMARK DEVELOPMENT GROUP LLC AND JARVIS OF CHESHIRE LLC By ?fw?fq 1M4 Timothy S. Hollister thollister@goodwin.com Shipman Goodwin LLP One Constitution Plaza Hartford, CT 06103w1919 Tel.: (860) 251-5000 Fax: (860) 251-5318 Juris No. 057385 Their Attorney CERTIFICATION OF SERVICE I hereby certify that a copy of the foregoing Motion for Judgment and attached Exhibits were electronically delivered this 27th day of November, 2018, to all counsel of record and written consent for electronic delivery has been received from all counsel. Mark S. Zamarka, Esq. Waller Smith Palmer, PC. 52 Eugene O'Neill Drive New London, CT 06320 Roger F. Reynolds, Esq. rreynolds@ctenvironment.org Connecticut Fund for the Environment 900 Chapel Street Suite 2202 New Haven, CT 06510 Paul M. Geraghty, Esq. Geraghty Bonnano, LLC 38 Granite Street P. O. Box 231 New London, CT 06320 Timothy S. Hollister Commissioner of the Superior Court 10 Exhibit A Landmark ?evelopment Group, LLC v. East Lyme Water Not Reported in 62 Conn. L. Rptr. 693 2016 WL 4497652 Only the Westlaw citation is currently available. UNPUBLISHED OPINION. CHECK COURT RULES BEFORE CITING. Superior Court of Connecticut, Judicial District of Hartford. Landmark Development Group, LLC et al. v. East Lyme Water 8: Sewer Commission July 6, 2016 Opinion COHN, J.T.R. *1 Prior to the commencement of the present action, the plaintiff, Landmark Deveiopment Group, LLC, brought an appeal against the defendant, East Lyme Water and Sewer Commission, regarding a sewer capacity determination. Before rendering a decision, the court reviewed the record, including the methodology for the grant of capacity. On June 26, 2014, the court ruled that the defendant must reconsider the allocation of sewer capacity in the amount of 13,000 gallons per day to the plaintiff, Landmark Development Group, LLC. See Landmark Development Group, LLC v. East Lyme Water d: Sewer Commission, Superior Court, judicial district of Hartford, Docket No. (June 26, 2014, Cohn, J.). In so ruling, the court indicated that the defendant must consider the Forest Walk. LLC Water Polluiion Control Authority, 29E Conn. 271, 968 A.2d 345 (2009) factors. More specifically, in regard to capacity, the defendant must ?consider the remaining capacity for the entire town, the land area represented by the property versus the available iand area in the town the safe design standards for the public sewer, and the percentage of the allocation versus the total remaining capacity.? Landmark Development Group, LLC v. East Lyme Water Sewer Commission, supra, Superior Court, Docket No. CV-13-6040390-S. On 29, 2014, the court denied the defendant's motion to reargue. See Landmark Development Group, LLC v. East Lyme Water Sewer Commission, Superior Court, judicial district of Hartford, Docket No. CV-13-6040390-S (June 29, 2014, Colin, 1.). In the present action, which was commenced on November 24, 2014, the plaintiffs, Landmark Development Group, LLC, and Jarvis of Cheshire, LLC, ask the court to review a grant of capacity of 14,434 gallons per day to the plaintiffs by the Board. On February 19, 2015, the plaintiffs fried their appeal brief. On March 16, 2015, the defendant, East Lyme Water and Sewer Commission, filed its appeal brief. 1 On March 30, 2015, the plaintiffs filed a motion for permission to suppiement the record in administrative appeal. The court heard oral argument on Aprii 2, 2015. On the same day, the court granted the plaintiffs? request, but only as to exhibit C, a letter from Mark S. Zamarka. On July 23, 2015, the plaintiffs flied a motion to conduct further discovery/deposition, and to supplement the record. Speci?cally, the plaintiffs asked the court for permission to take the deposition of the Board?s administrator, Bradford Kargl, regarding approval of the connection application by Gateway (a similarly~situated apartment complex being developed) where over 160,000 gailons per day capacity was contemplated. The motion was granted by the court on September 8, 2015. The deposition revealed that although Kargl was aware of the Gateway capacity need (Plaintiffs Exhibit 1, Deposition of Kargl, pp. and had the duty to monitor this need (Plaintiffs' Exhibit 1, pp. i5/A9, i7/A10, 6i~63lA49?51, he approved the connection appiication without making a capacity determination (Plaintiffs' Exhibit 1, pp. 66-7i/ A54-58, and without further reference to the Board (Plaintiffs? Exhibit 21). 3 *2 The court, as indicated in prior rulings, does not believe that a capacity determining action is ministerial, but is instead a matter of discretion for the Board. See Forest Walk, LLC v. Water Pollution Control Authority, supra, 291 Conn. 282 municipality has wide discretion in connection with the decision to suppiy Although this discretion is not absolute, [t]he date of construction, the nature, capacity, location, number and cost of sewers and drains are matters within the municipai discretion with which the courts will sewerage not interfere, unless there appears fraud, oppression or arbitrary action? [internal quotation marks omitted] see also Straw Pond Associates, LLC v. Water Pollution Control Authority, Superior Court, judicial district of Waterbury, Docket No. (March 8, 3 9 axis in: littigiatsigti tinnli it? Landmark Development Group, LLC v. East Lyme Water Not Reported in 62 Conn. L. Rptr. 693 2011, Gallagher, J.) (discretionary standard of review applied to determination of availability of sewer capacity). The defendant's actions are discretionary even where there is a request for a sewer extension permit See Landmark Development Group, LLC v. East Lynn: 374 FedApr. 58, 60 (2d Cir. 2010) (?Plaintiffs had no legitimate claim of entitlement to a sewer?extension permit. Defendants plainly have discretion to deny such permits?). In light of the supplemental evidence, the court concludes that there is at least 200,000 gallons per day capacity (358,000 gallons per day less 160,000 gallons per day to Gateway) for the entire sewer system.3 The defendant had broad discretion in determining capacity, but the defendant was obligated to consider capacity when it approved the connection application for Gateway. As to the plaintiff, the court ?nds that with the large amount of capacity remaining, the capacity figure of 14,434 gallons per day is excessively low. There is an abuse of discretion4 that the Board must correct. Although the Board is not required to grant the plaintiffs their request for 118,000 gallons per day, the capacity figure of 14,434 gallons per day is insufficient in View of the Footnotes present remaining capacity of at least 200,000 gallons per day, and in view of the 160,000 gallons per day that was approved for Gateway. In reconsidering the allocation of the sewer capacity, the Board must comply with applicabie sewer statutes, regulations and ordinances, and the Board should take into account the demands of the plaintiffs? sewer project and the effect on remaining capacity. Nevertheless, the Board must provide the plaintiffs with suf?cient capacity to further the development of their project, and, as such, the Board may not settle on a figure for capacity that would completely foreclose the development of the plaintiffs? project. *3 This matter is remanded to the Board for a further ruling and is a final decision for purposes of appeal. SO ORDERED. All Citations Not Reported in A.3d, 2016 WL 4497652, 62 Conn. L. Rptr. 693 1 The two intervening entities, Friends of the Oswegatchie Nature Presetve, inc., and Save the River-Save the Hills, Inc., have also ?led briefs in this action. 2 The fact that Kargl failed to even review capacity as to Gateway distinguishes this case from the Forest Walk factors which have guided the court to this point. 3 In its prior June 26, 2014 decision, this court noted that, as to remaining capacity, "[tjhe record before the court shows a range of 130,000 to 225,000 gpd. At the meeting of the commission on February 25, 2014, the ?gure of 177,000 was used as a compromise. in court on May 27, 2014, the commission's attorney conceded that the commission would not object to a figure of 250,000 gpd. Finally, Landmark points to a reduced usage by the town and state facilities so that the correct ?gure is between 308,000 god and 358,000 god." Landmark Development Group, LLC v. East Lyme Water Sewer Commission, supra, Superior Court, Docket No. More recently, during the commission's October 2014 remand proceeding and resolution, the commission applied the plaintiff?s ?gure of 358,000 gallons per day. (Amended Return of Record, Exhibit D, Post?proceeding Exhibits 2, 3.) 4 ?When a water pollution control authority performs its administrative functions, a reviewing court?s standard of review of the {authority?s} action is limited to whether it was illegal, arbitrary or in abuse of [its] discretion MoreOVer, there is a strong presumption of regularity in the proceedings of a public agency, and we give such agencies broad discretion in the performance of their administrative duties, provided that no statute or regulation is violated." (Citation omitted; internal quotation marks omitted.) Forest Walk, LLC v. Water Pollution Control Authority, supra, 291 Conn. 285?88. End of Beaumont 2018 "i?homson Reuters. No claim to original US. Government Works. 5- "the? wt in in . Exhibit Landmark Development Group, LLC v. Water and A.3d (2018) 184 Conn.App. 303 184 Conn.App. 303 Appellate Court of Connecticut. LANDMARK DEVELOPMENT GROUP, LLC, et a1. V. WATER AND SEWER COMMISSION OF the TOWN OF EAST LYME (AC 39804), (AC 39806) Argued April 10, 2018 Of?cially released August 21, 2018 Synopsis Background: Property owners sought judicial review of a decision of town's water and sewer commission allocating only 14,434 gallons per day in sewer treatment capacity to owners? housing development. The Superior Court, Judicial District of Hartford, Colin, Judge Trial Referee, 2016 WL 4497652, sustained owners? appeal and ordered commission to grant owners' application for determination of sewer treatment capacity. Commission appealed. Holdings: The Appellate Court, Bear, ., held that: trial court properly allowed owners to supplement record with evidence of allocation to another apartment complex; trial court prior ruling regarding factors for allocating capacity was not law of the case; and trial court properly sustained owners' appeal. Af?rmed. Attorneys and Law Firms Mark S. Zamarka, with whom, on the brief, was Edward B. O'Connell, New London, for the appellant in AC 39804 (defendant). Roger F. Reynolds, with whom were John M. Looney, Hartford, and, on the brief, Andrew W. Minikowski, for the appellants in AC 39806 (intervenors). la- Timothy S. Hollister, with whom was Beth Bryan Critton, Hartford, for the appellees in both appeals (plaintiffs). DiPentima, C.J., and Alvord and Bear, 33. Opinion BEAR, J. *306 This chapter of the protracted dispute between the town of East Lyme (town), and the plaintiffs, Landmark Development Group, LLC, and Jarvis of Cheshire, LLC, involves the plaintiffs' application to the defendant,1 the town's Water and Sewer Commission (commission), for a determination of sewer treatment capacity. The commission appeals from the judgment of the Superior Court sustaining the plaintiffs' appeal and ordering the commission to grant the plaintiffs' application. 2 On appeal, the commission argues *307 that the court (1) abused its discretion by allowing the plaintiffs to submit supplemental evidence to the court, and (2) improperly concluded that the commission abused its discretion by allocating to the plaintiffs 14,434 gallons per day in sewer treatment capacity. We af?rm the judgment of the court. M2 The following facts and procedural history are relevant to our disposition of this appeal. 3 The plaintiffs own a 236 acre parcel of land in the Oswegatchie Hills area of the town, on which the plaintiffs sought to construct an 840 unit housing development. Giving rise to the present appeal is the plaintiffs? application to the commission for a determination of sewer treatment capacity, which the plaintiffs filed on June 1, 2012. In this application, the plaintiffs requested that 118,000 gallons per day of the town's sewer treatment capacity be reserved for its proposed housing development in the Oswegatchie Hills. In a December, 2012 resolution, the commission found that the plaintiffs had requested a disproportionately large amount of the town's remaining sewer treatment capacity and, therefore, denied the plaintiffs? application. The plaintiffs appealed the commission's decision to the Superior Court, which, on January 16, 2014, remanded the case to the commission for a clarification of its 2012 resolution (first remand). Specifically, the court sought clari?cation as to the amount of capacity the commission was willing to allocate to the plaintiffs and a justification *398 for that amount. The court also ordered that the parties report back to court on March 17, 2014. :1 ?Wham: M3., ,wwm Ewi" f? {Iii 3: rival/E 2; :ate?zatius (4:13 {:25an 1.2: wt tags: a 3 Landmark ?evelopment Group, LLC v. Water and A.3d (2018) 184 Conn.App. 303 Pursuant to the court's January, 2014 order, the commission addressed the plaintiffs' application at its February, 2014 regular meeting. Following the meeting, the commission allocated to the plaintiffs 13,000 gallons per day in sewer treatment capacity. The parties appeared before the court in May, 2014, to resolve, inter alia, whether the commission's allocation of 13,000 gallons per day was an abuse of discretion. On June 23, 2014, the court sustained the plaintiffs? appeal and remanded the matter to the commission (second remand). In reaching this conclusion, the court relied on Forest Walk, LLC v. Water Pollution Control Authority, 291 Conn. 271, 968 A.2d 345 (2009),4 and Dauti Construction, LLC v. Water Sewer Authority, 125 Conn. App. 652, 10 A.3d 84 (2010), cert. denied, 300 Conn. 924, is A.3d 629 (20l1). The court found that the commission's allocation of 13,000 gallons per day was ?inappropriately low? for the following reasons: (1) the record did not indicate a speci?c amount of available capacity before considering the plaintiffs? application; (2) the commission made no ?nding regarding the area of the plaintiffs' development versus the land area of the town; (3) the commission based its decision on data that was not current; (4) none of the commission's capacity for possible future development had been requested since the reserve for future development was created in 2004; and (5) the plaintiffs requested only a small amount of the commission's remaining capacity. *309 At its October 28, 2014 regular meeting, the commission again considered the plaintiffs' application. On the basis of the factors set out in Forest Walk, LLC v. Water Pollution Control Authority, supra, 291 Conn. at 29596, 968 A.2d 345 (Forest Walk factors); see footnote 4 of this opinion; the commission derived a formula to determine what it considered to be an appropriate sewer capacity allocation for the plaintiffs. The formula provided: 358,000 gallons per day of available capacity divided by 5853 total acres of the town, is equal to divided by 236 acres owned by the plaintiffs, where equals the appropriate capacity to allocate to the plaintiffs. Application of this formula determined that 14,434 gallons per day of sewer treatment capacity was an appropriate allocation. The plaintiffs again appealed the commission's decision to the Superior Court. M3 On July 6, 2016, the court issued a memorandum of decision again remanding the matter to the commission (third remand). In its memorandum of decision, the court noted the following relevant procedural history: ?In the present action, which was commenced on November 24, 2014, the plaintiffs ask the court to review a grant of capacity of 14,434 gallons per day to the plaintiffs by the [commission]. On February 19, 2015, the plaintiffs filed their appeal brief. On March 16, 2015, the [commission] filed its appeal brief. On March 30, 2015, the plaintiffs ?led a motion for permission to supplement the record in an administrative appeal. The court heard oral argument on April 2, 20l5. On the same day, the court granted the plaintiffs' request, but only as to exhibit C, a letter from Mark S. Zamarka. ?On July 23, 2015, the plaintiffs filed a motion to conduct further discovery [including the taking of a] deposition and to supplement the record. Speci?cally, the plaintiffs asked the court for permission to take the *310 deposition of the [commission's] administrator, Bradford Kargl, regarding the approval of the connection application by Gateway (a similarly?situated apartment complex being developed) where over 160,000 gallons per day capacity was contemplated. The motion was granted by the court on September 8, 2015. The deposition revealed that although Kargl was aware of the Gateway capacity need and had a duty to monitor this need he approved the connection application without making a capacity determination and without further reference to the [commission].? Thereafter, the court stated: ?In light of the supplemental evidence, the court concludes that there is at least 200,000 gallons per day capacity (358,000 gallons per day less 160,000 gallons per day to Gateway) for the entire sewer system. The [commission] had broad discretion in determining capacity, but the [commission] was obligated to consider capacity when it approved [Gateway's] connection application As to the plaintiffs, the court ?nds that with the large amount of capacity remaining, the capacity figure of 14,434 gallons per day is excessively low. There is an abuse of discretion that the [commission] must correct. Although the [commission] is not required to grant the plaintiffs their request for ll8,000 gallons per day, the capacity ?gure of 14,434 gallons per day is insufficient in view of the present remaining capacity of at least 200,000 gallons per day, and in View of the 160,000 gallons per day that was approved for Gateway. In reconsidering the allocation of the sewer capacity, the [commission] must comply with 3' y: i. 531' 73?: w: ?Win is? at}? ?53.3: it}: its Landmark Development Group, LLC v. Water and A.3d (2018) 184 Conn.App. 303 applicable sewer statutes, regulations and ordinances, and the [commission] should take into account the demands of the plaintiffs' sewer project and the effect on remaining capacity. Nevertheless, the [commission] must provide the piaintiffs with suf?cient capacity to further the development of their project, and, as such, the {commission} may *311 not settle on a figure for capacity that would completely foreclose the development of the plaintiffs' project.? (Footnotes omitted.) This appeal foliowed. The first issue that we must resolve is whether the court abused its discretion by allowing the plaintiffs to submit supplemental evidence (Gateway evidence) pursuant to General Statutes The commission argues that the Gateway evidence concerned a sewer connection permit, which does not require a determination of sewer treatment capacity and is a matter that the commission does not handle, rendering the evidence irrelevant and unnecessary for the equitable disposition of the appeal. The abuse of discretion standard governs our review of a trial court's decision to admit supplemental evidence under See Parslow v. Zoning Board of Appeals, 110 Conn. App. 349, 353?54, 954 A.2d 275 (2008). ?When reviewing claims under an abuse of discretion standard, the unquestioned rule is that great weight is due to the action of the triai court and every reasonable presumption should be given in favor of its We will reverse the trial court's ruling only if it could not reasonably conclude as it Reversal is required only where an abuse of discretion is manifest or where injustice appears to have been We do not determine whether a conclusion different from the one reached could have been reached.? (Citations omitted; internal quotation marks omitted.) Id., at 354, 954 A.2d 275. Section 8?8(k) provides in relevant part: ?The court shall review the proceedings of the board and shall aliow any party to introduce evidence in addition to the contents of the record if (2) it appears to the court that additionai testimony is necessary for the equitable disposition of the appeal.? See also *312 Cli?brd v. Planning Zoning Commission, 280 Conn. 434, 447, 908 A.2d 1049 (2006) appeal from an administrative tribunal should ordinarily be determined upon the record of that tribunal, and only when that record fails to present the hearing in a manner suf?cient for the determination of the merits of the appeal, or when some extraordinary reason requires it, should the court hear evidence? [internal quotation marks omitted] ?[A]llowance at trial of additional evidence under the concept of evidence ?necessary for the equitable disposition of the appeal,? under has generaily received a restrictive interpretation to avoid review of the agency's decision based in part on evidence not presented to the agency initialiy.? 68136118? v. Planning Zoning Commission, 94 Conn. App. 478, 489, 892 A.2d 979 (2006). Here, the Gateway evidence was necessary for the equitable disposition of the appeal. The Gateway evidence established that, even though the commission conciuded, after it applied the Forest Walk factors, that it did not have sufficient capacity to grant the plaintiffs? application for up to 118,000 gallons per day, Gateway had, in effect, been granted, without application of the Forest Walk factors, 5 an allocation of approximately 166,000 galions per day following the approvai of its connection permit. The Gateway evidence, therefore, was relevant for the court to be able to determine that the plaintiffs, when compared to Gateway, had been treated inequitably by the commission. Unlike Gateway, which had been able to build its development, the plaintiffs, because of the commission's 14,434 gallon per day allocation, did not have suf?cient capacity to satisfy the estimated sewage requirements of their projected 840 unit development, despite the existence of adequate *313 available capacity to grant the plaintiffs? request of up to 118,000 gallons per day. 6 Moreover, the piaintiffs did not have the opportunity to present the Gateway evidence to the commission during the initial hearing, the ?rst remand, or the second remand. Our review of the record shows that the events concerning Gateway occurred in 2014 and 2015, and that the plaintiffs became aware of the Gateway evidence in 2015. Therefore, when the plaintiffs ?led their motion under in March, 2015, it was their ?rst reasonable opportunity to bring the Gateway evidence to the court's and the commission's attention. Accordingly, because the Gateway evidence could have in?uenced the commission?s decision regarding the piaintiffs' application, and the plaintiffs sought to introduce this evidence at the earliest opportunity, the court did not abuse its discretion by ?ftibflhiir My} tonsil l. 3.x: an atom tron, intact-atenant Landmark Development Group, LLC v. Water and A.3d m- (2018) 184 Conn.App. 303 granting the plaintiffs' motion to supplement the record. See Clif/brd v. Planning Zoning Commission, supra, 280 Conn. at 449, 908 A.2d 1049 penalize the plaintiff for the absence in the record of documents that could have affected the commission's decision on the site plan application, when the plaintiff had no reasonable opportunity to bring such documents to the attention of the commission, would be simply *314 unfair and not in accordance with basic principles of equity?). 7 II The commission's second claim on appeal is that the court improperly concluded that it abused its discretion by allocating to the plaintiffs 14,434 gallons per day of sewer treatment capacity. Speci?cally, the commission argues that the court erred because it disregarded its ruling from a prior remand concerning the application of the Forest Walk factors. See footnote 4 of this opinion. The commission also argues that the court erred by basing its decision, at least in part, on the supplemental evidence admitted pursuant to and by holding that the commission was obligated to consider the Gateway evidence in reaching its decision on the plaintiffs? application. We address those arguments in turn. *315 A The commission argues that the trial court?s ruling regarding application of the Forest Walk factors ?constitutes an interlocutory ruling that should have been treated as the law of the case in subsequent proceedings.? We disagree. ?We consider whether a court correctly applied the law of the case doctrine under an abuse of discretion standard. The law of the case doctrine provides that [w]here a matter has previously been ruled upon interlocutorily, the court in a subsequent proceeding in the case may treat that decision as the law of the case, if it is of the opinion that the issue was correctly decided, in the absence of some new or overriding circumstance.? (Emphasis added; internal quotation marks omitted.) Perugini v. Giuliano, 148 Conn. App. 861, 879-80, 89 A.3d 358 (2014). Here, the court did not abuse its discretion by disregarding the Forest Walk factors in reaching its decision to sustain the plaintiffs? second appeal and remand the matter, for the third time, to the commission. In the court's June 23, 2014 remand order, it acknowledged that Forest Walk, LLC, ?indicate[s]? that, ?with regard to capacity, under the substantial evidence test, the commission must consider? the four factors. At the time the court issued its June, 2014 remand order, however, it was not aware of the Gateway evidence. In light of the Gateway evidence-m- which established new or overriding circumstances?aha court properly exercised its discretion in disregarding the Forest Walk factors, sustaining the plaintiffs' appeal, and remanding the matter to the commission. 8 *316 The commission next argues that the court improperly concluded that it abused its discretion by allocating to the plaintiffs l4,434 gallons per day of sewer capacity. Speci?cally, the commission argues that the court improperly (1) concluded that it was obligated to consider the Gateway evidence in deciding the plaintiffs' application, and (2) based its decision, at least in part, on the Gateway evidence. ?in considering an application for sewer service, a water pollution control authority performs an administrative function related to the exercise of its When a water pollution control authority performs its administrative functions, a reviewing court's standard of review of the [authority's] action is limited to whether it was illegal, arbitrary or in abuse of [its] discretion Moreover, there is a strong presumption of regularity in the proceedings of a public agency, and we give such agencies broad discretion in the performance of their administrative duties, provided that no statute or regulation is ?With respect to factual ?ndings, at reviewing court is bound by the substantial evidence rule, according to which, [c]onclusions reached by [the authority] must be upheld by the trial court if they are reasonably supported by the record. The credibility of the witnesses and the determination of issues of fact are matters solely within the province of the The question is not whether the trial court would have reached the same conclusion, but whether the record before the [authority] supports the a; r1 2? Merritt? a: 323% r? Landmark {Development Gmup, LLC v. Water and A.3d w- (2018) 184 ConnApp. 303 decision *317 If a trial court ?nds that there is substantial evidence to support a [water poliution control authority?s] ?ndings, it cannot substitute its judgment as to the weight of the evidence for that of the if there is con?icting evidence in support of the [authority?s] stated rationale, the reviewing court cannot substitute its judgment for that of the The [authority?s] decision must be sustained if an examination of the record discloses evidence that supports any one of the reasons Accordingly, we review the record to ascertain whether it contains such substantial evidence and whether the decision of the defendant was rendered in an arbitrary or discriminatory fashion.? (Citations omitted; footnote omitted; internal quotation marks omitted.) Forest Walk, LLC v. Water Pollution Control Authority, supra, 291 Conn. at 285?87, 968 A.2d 345. We review the court's decision to determine if, when reviewing the decision of the administrative agency, it acted unreasonably, illegally, or in abuse of its discretion. See Was]? v. Dept. of Public Health, 60 Conn. App. 775, 781, 761 A.2d 257 (2000), cert. denied, 255 Conn. 932, 767 A.2d 106 (2001). On the basis of our previous conclusions in this opinion?Le, that the court did not abuse its discretion by (1) supplementing the record with the Gateway evidence and (2) disregarding the Forest Walk factors mwe conclude that the court did not act unreasonably, illegally, or in abuse of its discretion when it sustained the plaintiffs' appeal and remanded the matter to the commission. Because the court property admitted the Gateway evidence, it was free to consider that evidence in reaching its decision on the plaintiffs' appeal. That evidence demonstrated that the record, as supplemented, Footnotes did not reasonabiy support the conclusion of the commission to grant a ?4,434 gallon daily allocation. The evidence in the record as supplemented established that the commission had an availabie capacity of 358,000 gallons per day, less the 166,000 gallons per day that was effectively allocated to Gateway. There also was evidence that an administrator of the commission, Kargl, was aware of Gateway's capacity need and *318 the existence of the plaintiffs then pending application. Kargl, however, approved Gateway's application without making a determination of the impact of the grant to Gateway on the plaintiffs' application in light of the remaining capacity available to the town. On the basis of this evidence, the court properly determined that the commission abused its discretion when it granted to the piaintiffs only 14,434 galions per day of its 118,000 gallons per day request, deSpite aliowing, without applying the Forest Walk factors, Gateway's 166,000 gallons per day connection permit application. On the basis of the record as suppiemented, the court, in the exercise of its discretion, could reasonably conclude that the commission treated the plaintiffs inequitably and that an injustice had been done. See Parslow v. Zoning Board of/lppeuls, supra, 110 Conn. App. at 354, 954 A.2d 275. The judgment is af?rmed. In this opinion the other judges concurred. All Citations A.3d 184 Conn.App. 303, 2018 WL 3966966 1 On February 20, 2015, two entities, Friends of the Oswegatchie Hills Nature Preserve, ll?lC., and Save the River~Save the Hills, submitted a veri?ed petition to intervene, pursuant to General Statutes 22a?19, in the appeal between the plaintiffs and the commission. In the petition, the entities argued, inter alla, that the plaintiffs application involves conduct which is reasonably likely to have the effect of unreasonably poltuting, impairing, or destroying the public trust in the air, water and other natural resources of the State of Connecticut." The petitionhighlighted several environmental considerations and noted that the Superior Court had found previously that the plainti?s? development posed a risk of considerabte harm to the Oswegatchie Hills. On March 18, 2015, the court granted the petition to intervene. Both the commission and the intervenors have appealed from the court's judgment sustaining the appeal. The commission's appeal is assigned docket number AC 39804. The intervenors' appeal is assigned docket number AC 39806. The lntervenors did not appear in the proceedings before the commission to determine the sewer treatment capacity available for the use of the plaintiffs, and did not submit any evidence in support of their claims. Because the intervenors' claims on appeal essentialty are the same as the claims raised by the commission, and reEy on the record of the proceedings before the commission made by the plaintiffs and the commission witnesses, we address both appeals in a single opinioninns twat; int-t; it; Landmark (Development Group, LLC v. Water and A.3d (2018) 184 Conn.App. 303 2 initially, the plaintiffs contended that the judgment of the trial court was not an appealable ?nal judgment, while the commission argued that it was. At orai argument before this court, the pialntiffs? counsel conceded that the court?s July, 2018 decision was an appealaple ?nal judgment. We agree and note that judgment of remand is ?ne] if it so concludes the rights of the parties that further proceedings cannot affect A judgment of remand is not ?nal, however, if it requires [the agency to make] further evidentiary determinations that are not merely ministerial." (Citations omitted; internal quotation marks omitted.) Kaufman v. Zoning Commission, 232 Conn. 122, 130, 653 A.2d 798 (1995). Here, the court's judgment so conciuded the rights of the parties because it ordered that the commission must grant the piaintiffs? appiication. The dispute between the plaintiffs and the town has been ongoing for approximately eighteen years. Most of the facts and procedural history related to the protracted dispute are not relevant to the issues in this appeal. In its memorandum of decision, the court noted that Forest Walk, LLC, ?indicate[s] the following to the court with regard to this appeal With regard to capacity, under the substantial evidence test, the commission must consider the remaining capacity for the entire town, the land area represented by the property versus the available land area in the town, the safe design standards for public sewers, and the percentage of allocation versus the totai remaining capacity." We refer to these as the Forest Walk factors. Gateway, unlike the plaintiffs, did not make an aliocation application prior to constructing its development. The court found "that with the large amount of capacity remaining, the capacity figure of 14,434 gallons per day is excessively low. There is an abuse of discretion that the [commission] must correct. Although the [commission] is not required to grant the plaintiffs their request for 118,000 gailons per day, the capacity ?gure of 14,434 gallons per day is insuf?cient in view of the present remaining capacity of at least 200,000 gallons per day, and in View of the 160,000 gailons per day that was approved for Nevertheless, the [commission] must provide the plaintiffs with sufficient capacity to further the development of their project, and, as such, the [commission] may not settle on a ?gure for capacity that would completely foreclose the development of the plaintiffs' project." From this ?nding, we can infer that the court also found that the grant of 14,434 gailons per day foreclosed the plaintiffs from moving forward with their development. Our Supreme Court?s decision in Clifford v. Planning 8 Zoning Commission, supra, 280 Conn. at 434, 908 A.2d 1049, informs our resotution of this issue. in Clifford, the defendant commission (defendant) approved the proposal of the defendant construction company (company) to store dynamite on the company?s property. Id, at 437, 908 A.2d 1049. The plaintiff, Thomas Clifford, appealed to the trial court, and moved under to introduce supplemental evidence. id., at 437-38, 908 A.2d 1049. Speci?cally, Clifford sought to introduce prior site plan approvals forthe property at issue, which established, inter alia, that the storage of hazardous and demolition materials on the property was expressly prohibited and that before any further development could take place on the property, the company would need the approval of the inlands wetlands commission. Id., at 445?46, 908 A.2d 1049. The trial court denied the motion. id, at 438, 908 A.2d 1049. On appeal, our Supreme Court concluded that the trial court's denial of Clifford's motion under was an abuse of discretion. id, at 445, 908 A.2d 1049. The court held that the additional evidence was necessary for the equitable disposition of the appeal for two reasons. Id, at 448, 908 A.2d 1049. First, ?the evidence that [Clifford] sought to introduce consisted of information that, viewed on its face, could weli have affected the [defendant?s] consideration of [the company's] site pian application if it had been brought to the [defendant?s] attention, because the [evidence] revealed conditions that the [defendant] itself previousiy had imposed upon [the company] id. Second, the motion under was Clifford's ?first reasonabie opportunity to bring to the court?s attention the limitations on the use of [the company's] property that may well have affected the approval of the site plan application." Id., at 448?49, 908 A.2d 1049. The court expressly stated that part of the Gateway evidence, speci?cally, the deposition of Kargl, estabiished facts that made this case distinguishable from Forest Walk, LLC. End. of Document (1:3 2018 Thomson Reuters. No claim to originai US. Government Works. Exhibit Landmark Development Group, LLC v. Water and Sewer. Slip Copy (2018) 330 Conn. 937 330 Conn. 937 Supreme Court of Connecticut. LAN DMARK DEVELOPMENT GROUP, LLC, et al. v. WATER AN SEWER COMMISSION OF the TOWN OF EAST LYME Decided October 31, 2018 Attorneys and Law Firms Mark S. Zamarka, in support of the petition. Timothy S. Holiister, in opposition. Opinion *1 The defendant's petition for certi?cation to appeal from the Appellate Court, 384 Conn. App. 303 (AC 39804), is denied. 1., did not participate in the consideration of or decision on this petition. All Citations Slip Copy, 330 Conn. 937, 2018 WL 5925i81 (Table) ?led of ?oeoment 2918 Themeori Reutere. No ele?m to origieai US. Worke. i?i?gi L?tgwif .1 git: E23. iizfifzir?xl? Me 5:21.: Landmark Deveiopment Group, LLC v; Water and Siip Copy (2018) 330 Conn. 937 Opinion 330 Conn. 937 . *1 The petition by the intervening defendants Friends of Supreme Court Of Connecticut. the Oswegatchie Hills Nature Preserve, Inc, and Save the River-Save the Hills, Inc., for certi?cation to appeal from LANDMARK DEVELOPMENT GROUP, LLC, et a1. the Appeilate Court,x 184 Conn. App. 303 (AC 39806), is V. denied. WATER AN SEWER COMMISSION OF the TOWN OF EAST LYME Decided October 31, 2018 ., dict not participate in the consideration of or decision on this petition. Attorneys and Law Firms Ail Citations Roger F. Reynotds, in support of the petition. Slip Copy, 330 Conn. 937, 2018 WL 5920545 (Table) Timothy S. Hollister, in opposition. End of Decument 23818 Thomsen Renters: No cfa?m te orig?nal U5, Government Works. newteftfj star :3 rep .u an.? are; m; 2 a. t? rigor,? stgilt w; gage-s 3::3 i ?313: 3 int)? he; thirtii :3 ME #332; 26:2; game-.3: We A SHIPMAN a GOODWIN COUNSELORSAT LAW Timothy S. Hoilister Phone: (860) 251-5601 Fax: (860) 251?5318 thollister@goodwin.com September 17, 2018 VIA PDF T0 ATTORNEY ZAMARKA Mr. Mark Nickerson, Chair, Mr. Bradford C. Kargl and Commission Members Municipal Utility Engineer Water and Sewer Commission Water and Sewer Utilities Town of East Lyme Town of East Lyme 108 Avenue 108 Avenue P. O. Box 519 Niantic, CT 06357-0519 Niantic, CT 06357?0519 Re: Landmark Development Group, LLC, et al. 12. East Lyme Water and Sewer Commission Dear Chair Nickerson, Commission Members, and Mr. Kargl: It has come to our attention that the Commission will be meeting in executive session on September 18, 2018 to consider Landmark's sewer capacity allocation application, and will conduct its regular meeting on September 25, 2018. The purpose of this letter is to request that the Commission, at its next regular meeting, approve an allocation of sewer capacity to Landmark of 118,000 gpd, until such time as the parties obtain a ?nal and unappealable decision regarding Landmark's sewer capacity application. At this time, a trial court judgment, af?rmed by the Appellate Court, requires the Commission to grant Landmark "suf?cient capacity to further the development of [Landmark's] project," and ?may not settle on a ?gure for capacity that would completely foreclose the development of [Landmark's] project.? Moreover, in its court ?lings, the Commission has conceded that it ?mugs; grant Landmark's application. 6981881 ONE PLAZA HARTFORD, 06103?1919 860-251?5000 September 17, 20l8 Page 2 Landmark has a right to ensure that the Town of East Lyme does not undercut Landmark?s judgment by allocating sewer capacity to others, especially those whose applications or administrative requests were ?led after 2012. Meanwhile, Landmark has become aware of applications made to Mr. Kargl or the Commission that will require sewer allocations or commitments. The Town cannot defeat Landmark's rights to sewer capacity by allocating capacity to others, or at some future time deny Landmark's application due to third-party allocations that occurred while Landmark's court case was pending. Landmark is prepared to seek a court order to enforce its rights, but hopes that the Commission will at least recognize Landmark's right to an interim protection of its position, as well as avoid Town expense of opposition to this request. We request an answer to this request no later than the Commission's regular meeting of September 25, 2018, with implementation subject to counsel drafting a mutually acceptable resolution. Thank you for your attention. Very truly yours, MIA Timothy S. Hollister TSHzekf (3: Mark S. Zamarka, Esq. att.) Glenn Russo att.) Exhibit RESOLUTION REGARDING INTERIM SEWER CONNECTION PROCEDURE SEPTEMBER 25, 2013 WHEREAS, on June 1, 2012, Landmark Development Group, LLC and Jarvis of Cheshire (?Applicant?) filed with the East Lyme Water and Sewer Commission ("Commission"), acting as the East Lyme Water Pollution Control Authority, an application ?pursuant to ?7?246a(1) of the General Statutes, seeking confirmation of the availability of 237,090 gallons per day of sewage disposal capacity in the Town?s sewer system to serve Landmark Development?s proposed residential development adjacent to Caulkins Road"; and WHEREAS, at the public hearing on the application held on August 24, 2012, Landmark amended its application to request availability of 118,000 gallons per day of sewage disposal capacity in the Town of East Lyme's (?Town") sewer system; and WHEREAS, the Commission held three public hearings on the application and listened to hours of testimony during these hearings. Numerous exhibits were submitted by Landmark, the Commission, and individuals for consideration during the hearing process. in making its decision the Commission is considering and taking into account all of the testimony and exhibits submitted at the three hearings; and WHEREAS, the Commission has wide discretion in connection with the decision to supply sewer service to particular properties; and WHEREAS, the Commission found that as of Landmark?s application in 2012, the Town had between 130,000 and 225,000 gallons per day of remaining sewage treatment capacny;and WHEREAS, Landmark appealed the Commission?s capacity allocations to the Connecticut Superior Court; and WHEREAS, the New Britain Superior Court (Cohn, J.) (the ?Trial Court?) allowed Landmark to conduct discovery regarding a sewer connection permit for a different development project, known as ?Gateway,? and allowed Landmark to supplement the record on appeal with documents related to the Gateway connection application; and WHEREAS, on July 6, 2016, the Trial Court issued a Memorandum of Decision holding in part that: 1. The Commission is not required to grant the plaintiffs their request for 118,000 gallons per day 2. The Commission .. must provide the plaintiffs with sufficient capacity to further development of their project, and may not settle on a figure that would completely foreclose the development of the plaintiffs? project." renews 1; I 3. The Commission was obligated to consider capacity when it approved the connection application for Gateway.? WHEREAS, the Commission appealed the Memorandum of Decision to the Connecticut Appellate Court; and WHEREAS, on August 21, 2018, the Appellate Court issued its decision (?Decision?) on the Commission's appeal, which upheld the Trial Court Memorandum of Decision, and held that the Commission is required to perform a sewer capacity analysis when considering applications to connect to the East Lyme sewer system; and WHEREAS, the Commission disagrees with the Decision and has filed a petition for certi?cation to the Connecticut Supreme Court, which is currently pending; and WHEREAS, by a letter dated September 17, 2018, Landmark requested that the Commission approve an allocation for its full 118,000 sewer capacity request, pending ?nal resolution of its appeal; and WHEREAS, neither the Trial Court nor the Appellate Court held that Landmark was entitled to the full amount of its capacity request, and the proceedings are stayed until the Supreme Court acts on the Commission's petition for certification. While reserving all of its rights set forth during the appeal process, the Commission nevertheless does not want to ignore the Trial Court and Appellate Court holdings that require a sewer capacity analysis be done in conjunction with a sewer connection permit application. BE IT THEREFORE RESOLVED, that the East Lyme Water and Sewer Commission, acting as the Town?s Water Poliution Control Authority, hereby enacts the following interim procedure: 1. An application to connect to the East Lyme sewer system for a project that either (3) requests a connection for more than residential units or requires more than ?5 gallons per day of sewage treatment capacity, shall also require an application for determination of sewer capacity pursuant to General Statutes ?7~246a; 2. Said application for determination of sewer capacity shall be submitted either prior to or contemporaneously with a sewer connection application; 3. An application to connect to the East Lyme sewer system may not be granted if the Commission determines that there is not adequate sewer capacity for the proposed use of iand. 4620394440 i 3 Ix.) BE iT FURTHER RESOLVED that the above procedure does not reflect official policy or procedure of the Commission or the Town of East Lyme. Rather, it is adopted on an interim basis only in direct response to the Appellate Court Decision, and shall be in place only during the pendency of the Landmark sewer capacity appeal process. in enacting this interim procedure, the Commission does not agree with the holdings of the Trial Court Memorandum of Decision or the Appellate Court Decision. Any ?ndings made pursuant to this interim procedure (Le. available sewer capacity, etc.) shall be for the purposes of that sewer capacity application only, and shall not be adopted, incorporated or made part of the record in the pending Landmark sewer appeal. :0911344423 1 i 3 Exhibit Appellate court rules against East Lyme in sewage capacity case Published September 06. 2018 1 Updated September 06. 2018 By Martha Shanahan In the latest step of a protracted legal battle between East Lyme?s Water and Sewer Commission and the developer of a proposed housing development, an appellate court in Hartford has ruled that the commission must grant the developer more access to the town's sewer system than the commission wants to give it. The town's lawyers plan to petition the state Supreme Court to appeal the Aug. 21 ruling, which af?rms a state Superior Court judge?s 2016 order that the commission must reconsider the amount of sewage capacity it is willing to grant for a pmposed 840-unit residential development adjacent to the Oswegatchie Hills Nature Preserve along the Niantic River. Over more than a decade, Landmark DevelOpment has sought to develop houses on the 236 acres it owns in the Oswegatchie Hills. The plan has generated local opposition, which in recent years has taken the form of a coalition between Connecticut Fund for the Environment and two local groups arguing that the deveIOpment would pollute the Niantic River and degrade wetlands on the property. Landmark Development and its president, Glenn Russo, also have hit speedbumps before the town's Water and Sewer Commission, which regulates new connections to the pipes and pumps that bring sewage from East Lyme buildings through Waterford to a sewage treatment plant in New London. A deal between East Lyme, Waterford and New London allows each town to send a certain amount of sewage to the New London sewage treatment plant 15 percent of the plant's capacity, or about 1 million gallons a month in East Lyme's case and limits the towns' ability to grant permission to build new sewer lines or allow new developments to connect to the existing ones. In 2014, the Water and Sewer Commission denied Landmark's request for a guaranteed 118,000 gallons of sewage capacity per day for the development. Landmark appealed that decision in New London Superior Court in 2014, kicking off the ?ve- year ongoing debate in several courts over the commission's claims that the town's sewage system can't handle the amount of wastewater that a development the size of the Landmark proposal would generate. The commission's members said that year that it could allow Landmark to generate only 14,434 gallons per day in sewage for the proposed houses, a fraction of the 118,000 gallons per day Landmark asked for in 2014. Landmark's lawyers have argned that the commission granted the developer of a different housing complex in East Lyme, Gateway Commons, about 70,000 gallons of sewage capacity per day and told Gateway developers that the town had the capacity to handle about 100,000 additional gallons per day from the deveIOpment. The commission's decision to grant that capacity to the Gateway development shows the town has "ample" sewage capacity for the Oswegatchie Hills preposal, they said. Hartford Superior Court Judge Henry S. Cohn said in his 2016 ruling that 14,434 gallons per day is ?excessively low" in light of the allocation to Gateway, and remanded the issue to the commission. Town lawyers say the Gateway development's sewer capacity has no bearing on the Landmark case, because Gateway Commons is near one of the town's existing sewer lines and was relatively easy to connect to the system, whereas Landmark's proposal would require the construction of a new line. The two development projects are "like apples and oranges," said East Lyme First Selectman Mark Nickerson, who is also the chairman of the Water and Sewer Commission as directed by the town's charter. "There?s a difference between a connection and an extension," he said. The appeals court dismissed that argument last month. "Although the commission concluded that it did not have suf?cient capacity to grant the plaintiffs application for up to 118,000 gallons per day, (Gateway) had effectively been granted an allocation of approximately 166,000 gallons per day,? the court wrote in its ruling. "At the end of the day that's not a valid argument," said Timothy Hollister, an attorney with the Hartford law firm Shipman Goodman representing Landmark in the case. "The Water and Sewer Commission determined that the town as a whole has so much capacity that they can grant 166,000 gallons to Gateway but they have fought Landmark tooth and nail on every gallon of our request." Nickerson said he is con?dent in the town's appeal. The commission should have the ability to oversee management of its sewage systems without court interference, he said. He added that the extension of the sewer lines to the Oswegatchie Hills would constitute an unsuitable use of the town's increasingly limited capacity for adding new inputs to the sewer system and would eat up sewage capacity the town is saving for other neighborhoods where the houses still use septic systems. The Department of Energy and Environmental Protection has put pressure on the town to expand sewer capacity to those neighborhoods to alleviate pressure on aging septic systems, which takes priority over development proposals like the Landmark plan, Nickerson said. "If we had unlimited capacity and unlimited funds, we would give out all sorts of capacity," he said. m.shanahan@thedav.com Exhibit A SHIPMAN a GOODWIN COUNSELORSAT LAW Timothy S. Hollister Phone: (860) 251-5601 Fax: (860) 251-5318 thollister@goodwin.com October 24, 2018 VIA PDF AND U.S. MAIL Mr. Bradford C. Kargl Municipal Utility Engineer Town of East Lyme 108 Avenue P. O. Box 519 Niantic, CT 06357-0519 Re: Freedom of Information Act Request Dear Mr. Kargl: We represent Landmark Development Group LLC and Jarvis of Cheshire, LLC (together, "Landmark"). This letter is a Freedom of Information Act request made under Chapter 14 and 1-210 of the General Statutes. We request a copy of all documents dated or created January 1, 2018 or after that relate in any way to the Water and Sewer Commission or the Town of East Lyme providing sewer capacity or connection in excess of 5,000 GPD. This request covers all uses such as residential, commercial, industrial, and institutional development and in particular, the development on Flanders Road known as "Gateway," and its Phase commercial development, including a possible Costco store. The undersigned will pay, in advance if requested, for reasonable c0pying charges for the provision of these documents. Please bear in mind the statutory deadline for the Commission's response to this request as stated in General Statutes but also that this is a continuing request after the initial disclosure. The undersigned will be happy to answer any questions about the scope of this request and otherwise to expedite the response. Very truly yours, at: MA. Timothy S. Hollister TSHzekf c: Mark S. Zamarka, Esq. (via pdt) Glenn Russo, Landmark Development Group LLC (via pdi) 7037875 ONE CONSTITUTION PLAZA HARTFORD, 860-251-5000 . Exhibit - constructi Pazz Construction, LLC 172 Boston Post Rd East Lyme, Ct 06333 Town of East Lyme Water and Sewer Commission, Pursuant to East Lyme Water Sewer Commission Regular Meeting Tuesday, September 2018 Minutes 1. An application to connect to the East Lyme sewer system for a project either requests a connection for more than 20 residential units or requires more than 5,000 gallons per day of sewage treatment capacity, shall also require an application for determination of sewer capacity pursuant to General Statues 7-2463. This letter is to serve as an application to connect for more than 20 residential units. We are currently in progress working towards an 8306 project located at 90 North Bride Brook Rd. The property is an ideal location for an 8306, the property is located within the sewer shed and is identified on the sewer mapping provided by the Town of East Lyme Water and Sewer Commission. The property has been assessed by the Sewer Department for such a connection. This letter is to serve as notification of such project and the need for sewer capacity for this project. Our current estimate for sewer capacity is 86,250 gallons per day. We estimate the project will consist of 575 bedrooms. Regards, Jason uaglia Pazz Construction LLC EAST LYME WATER sewers Hes-aeglia pazzconstruction.com 860.739.0863 Exhibit I A SHIPMAN a GOODWIN COUNSELDRS AT LAW Timothy S. Hollister Phone: (860) 251-5601 Fax: (860) 251-5318 thoilister@goodwin.com November 13, 2018 VIA HAND DELIVERY Mr. Mark Nickerson, Chair, Mr. Bradford C. Kargl and Commission Members Municipal Utility Engineer Water and Sewer Commission Water and Sewer Utilities Town of East Lyme Town of East Lyme 108 Avenue 108 Avenue P. O. Box519 P. O. Box 519 Niantic, CT 06357-0519 Niantic, CT 06357?0519 Re: Landmark Development and Application of Gateway Commercial LLC for Sewer Allocation for Costco Store Dear Chair Nickerson, Commission Members, and Mr. Kargl: As you know, we represent Landmark Development Group LLC and Jarvis of Cheshire LLC ("Landmark"). Landmark has a legal and property right interest in the Costco application because Landmark now has a ?nal court order directing the Commission to allocate sewer capacity to Landmark's proposed residential development on its property adjacent to the ?Golden Spur" residential area; and because the Connecticut Appellate Court?s August 2018 opinion speci?cally referenced the sewer capacity allocated to Gateway as an encroachment on Landmark?s rights. Thus Landmark has a legally protected interest in this Costco application. Landmark?s rights, which stem ?om a 2012 application, need to be recognized and given priority over any later-?led sewer capacity application, such as Costco?s. The courts have now con?rmed that this Commission violated Landmark's rights by first denying that Landmark's property was not in the town?s sewer district; then asserting that sewer was unavailable; then denying any sewer capacity, claiming it was already allocated to others; then allocating 13,000 then allocating 14,434 and then granting capacity it told the 7105448 ONE PLAZA HARTFORD, CONNECTICUT 06103?1919 860?251-5000 November 13, 2018 Page 2 Court it did not have to Gateway. In issuing these rulings, the courts have rejected this Commission's assertions of limited capacity, and have directed that this Commission must be transparent and accurate in calculating available capacity; may not use sewers to control land use; and must grant Landmark what it needs to proceed with its land use applications. What Landmark needs will be determined by the [and use permit process, not by this Commission. In response to the court rulings, East Lyme of?cials have been quoted as saying that "a judge can't force us" to give Landmark sewer access. Such a statement, if enforced by this Commission, will constitute contempt of court. Therefore, in considering and before acting on the Costco application, this Commission must do the following: 1. Grant Landmark's 2012 application by allocating 100.000 GPD, conditioned upon Landmark receiving Preliminary Site Plan approval for its proposed residential development. At this time, Landmark is willing to reduce its capacity allocation application from 118,000 GPD to 100,000 GPD, in an effort to resolve the matter. It is important to recognize that this is a maximum that will likely be reduced by the land use permit process. This Commission must grant Landmark?s application conditionally and allow the land use permitting process to determine what portion of the allocation will actually be used. Moreover, another public hearing on Landmark's application is unnecessary, because the Commission?s obligation is clear. 2. Recapture, and regard as available for town use, the capacity reserved to State that will never be used. At this time, although the Town has ample capacity to grant Landmark?s application, the Town needs to request that the State of Connecticut to release the capacity, contracted for in 1990, that has never been used and will never be used. Several hundred thousand GPD reserved for state facilities plainly will never be used. The Town has a legal obligation to request the State to release this capacity; the 1990 contractual reservation is now factually and legally unsupportable. In a recent, similar case, the New Jersey Supreme Court held that a town's refusal to recapture contracted but never-to-be?used capacity was an illegal sewer system management practice. See 388 Route 22 Readington Realty Holdings, LLC v. Township of Readington, 221 NJ. 318, 113 A.3d 744 (2015) (copy enclosed). This recapture requirement may also apply to other overstated, unused allocations such as the Point O'Woods allocation. In summary, this Commission, in considering the Costco application, must at this time conditionally grant Landmark 100,000 GPD of sewer discharge capacity, and protect this grant November 13, 2018 Page 3 against other applications ?led after 2012. This allocation should be set aside and preserved until such time as Landmark obtains Preliminary Site Plan approval of its development plan, at which time the Commission will approve the actual amount to be used. Very truly yours, ML, Timothy S. Hollister TSHiekf Enclosure 0: Mark S. Zamarka, Esq. enc.) Landmark Development Group LLC enc.) 1 Exhibit asst it?i?d? WAQTER gt SEWER. HEARIMG Teasda?g?, N?tiE?gE? 33th. E?i? idEidi?TES The East Lyme Water Sewer Commission held a Public Hearing on November 13, 2018 at Town Hall, 108 Avenue, Niantic, Connecticut on the Application of GDEL Commerciai for determination of sewer capacity for a Costco Retail Store at 284 Flanders Road, Map 31.3, Lot 1. Chairman Nickerson called the Public Hearing to order at 6:32 PM. PRESENT: Mark Nickerson, Chairman, Steve DiGiovcnno, Dove Jacques, Dove Murphy, Joe Mingo, Carol Russell, Roger Spencer, Dove Zoller ALSO PRESENT: Attorney Theodore Harris, Representing the Applicant Attorney Edward O'Connell, Town Counsel Attorney Mark Town Counsel Joe Brcgew, Public Works Director Bred Municipal Utility Engineer EAST LYME ABSENT: Dove Bond . Pledge of Allegiance The Pledge was observed. Public Hearing 9 Application of GDEL Commercial, LLC for determination of sewer capacity for at Costco Retail Store at 284 Flanders Road, Map 31.3, Lot 1. Chairman Nickerson called the Public Hearing to order at 6:32 PM. He noted that the Notice of Public Hearing had been published in the New London Day on November 1, 2018 and November 8. 2018. He then called upon the applicant or the applicant?s representative to present their request. Attorney Theodore Harris, representing the applicant said that the Costco would be located to the west side of Flanders Road along l?95. Costco is the large format store under the Master Plan for the Gateway District that was approved by the Zoning Commission in 2008. Design and approvals for the Costco have been in process over the last several years and currently all local, State and Federal permits have been obtained. The application for a building permit has been filed and should be approved within these next few weeks. There was a demand for residential housing and that component was developed; during that time the Costco interest developed. He noted the spreadsheet comparatives on other Costco stores sewer demand that he had presented. This was entered as Exhibit 1. He said that the actual is less than what was calculated and that they had atso found the same to be true with the residential component the actual is less than what was originally calculated. This is anticipated to be the same. Ms. Russell asked about statistics for the Food Court, Meat department and why the bathrooms were not included. Attorney Harris said that the Food Courts and Meat Departments are constants and maximum demand areas ?just as they would he with the store in East Lyme. Mr. Jacques asked where the 99 GM came from in the email. Mr. Kargl and Mr. Harris said that it is from an actual meter reading. Mr. Spencer noted that the calculation would not come out correctly. Mr. Nickerson said that they have provided very real data from actual comparative stores. Mr. Murphy asked if it would have a brown water system. Mr. Harris said that he was not sure. Mr. Nickerson said that they would be using well water for irrigation, etc. Mr. Niokerson asked if there were any comments from the public - Attorney Timothy Hollister, place of business, Hartford, representing Landmark Development said that he had a letter that he submitted and would like to read into the record. (Exhibit 2) He noted that Landmark has a legally protected interest in the Costco application as outlined in his letter. He asked where the capacity study was for the Costco request as he had not heard anything on it. He noted that Gateway did not begin until late 2012 and that Landmark?s application preceded it. Attorney Roger Reynolds, place of business not identi?ed, - representing Friends of Oswegatchie Hills and Save the River, Save the Hills as interveners with regard to the Landmark application said that he objected to what Attorney Holiister had said with regard to the Courts on the capacity issue in relation to the remaining capacity and what they should allow Landmark. Mr. Nickerson said that while he is trying to give some leeway here that he wants to stay focused on the Costco application as there are other applications that will also be coming before them in the future. Mr. Reynolds said that Landmark?s assessment is not related to Costco. Mr. Harris said that he did read the Court memorandum and noteci that Gateway was already granted 160,000 god and that they really could use some of that. His letter to the Commission was submitted and entered as Exhibit 3. Mr. Nickerson asked if there were other comments. (1) Mr. Mingo moved to close the Public Hearing. Mr. DiGiovanna seconded the motion. Mr. Nickerson noted that they would have other applications coming before them for sewer capacity. Mr. Kargl said that information was based on the Weston Sampson study of 2012 and that since that time he has taken the data and come up with an analysis on available (262,000 gpd) based on the maximum average over six (6) years. He noted that the New London plant has 10M god of maximum capacity which they cannot exceed. Mr. Nickerson noted that the 262,000 god is a moving target and that the 7,650 request is approximately 3% of our capacity. Attorney Hoilister said that what Mr. Kargl just explained is the essence of the capacity study. He would like him to circulate his analysis and for them to postpone closing the public hearing as they have a right to review that information. A vote was called for the motion and second on the floor. Vote: 8 -- 0 0. Motion passed. Mr. Nickerson closed this Public Hearing at 7:14 PM. Reapectfully submitted, Karen Recording Secretary (Exhibits 1, 2 3 attached) East Lyme Water Sewer Commission Public Hearing I Minutes .. November 13, 2018 2 Exhibit Egg? Li?iis?ig Ea SEWER RE?i?i?iR is?iEgi?dQ NGVEMSER 2913 The East Lyme Water Sewer Commission heid a Regular Meeting on Tuesday, November 18, 2018 at the East Lyme Town Hall, 108 Avenue. Niantic, CT. Chairman Nickerson called the Regular Meeting to order at 7:15 PM immediately following the previously scheduled Public Hearing. PRESENT: Mark Nickerson, Chairman, Steve Dislovanno. Dove Jacques, Dave Murphy, Joe Mingo, Carol Russell. Roger Spencer, Dove Zoller ALSO PRESENT: Attorney Theodore Harris, Representing the Applicant Attorney Edward O'Connell. Town Counsel Attorney Mark Zomorko, Town Counsel Joe Brogow, Public Works. Director FILED IN EAST LYME Brod Ker-gt, Municipal U?ll?l?y Engineer COMMECTISUT Anna Johnson, Finance Director Ny?/Woj?ei? Wig?mm ?swam CLERK ABSENT: Dove Bond 1. Call to Order! Pledge of Allegiance Chairman Nickerson called the Regular Meeting of the East Lyme Water Sewer Commission to order at 7:15 PM immediately following the previously scheduled Public Hearing which was closed at 7:14 PM. The Pledge was previously observed. 2. Approval of Minutes a Public Hearing Meeting Minutes October 23, 2018 - Regular Meeting Minutes October 23, 2018 Mr. Nickerson called for a motion or any discussion or corrections to the Public Hearing Meeting Minutes or Regular Meeting Minutes of October 23. 2018. (1) Mr. DiGiovanna moved to approve the Public Hearing Meeting Minutes and the Regular Meeting Minutes of October 23, 2018 as presented. Mr. Zoller seconded the motion. Vote: 6 - 0 2? Motion passed. Abstained: Mr. Nickerson, Mr. Jacques 3. Delegations Mr. Nickerson called for delegations. There were no delegations. 4. Consider Allocation of Sewer Capacity for Costco Mr. Mingo said that the 160,000 that was approved for Gateway does not necessitate going any further as the Costco can get capacity from there. Mr. Nickerson said that they should go through the process anyways they are looking for 7,650 from the approximate 262,000 available. Mr. Mingo asked for the Attorney to rule on it. Attorney Zamarka, Town Counsel said that the 160,000 is a court analysis. He noted that they are here by Resolution and added that Attorney Hollister is correct that Landmark does have an interest in the Costco application as the Landmark application is also out there for capacity. Costco does need to be analyzed for available capacity. Mr. DiGiovanna asked if that isn?t what Brad came up with in his analysis. Mr. Kargl said that he woutd feel more comfortable with his analysis once he has conversation with the DEEP on it and receives their input. Mr. Mingo asked if he would be correct that they should not put a motion on the ?oor and asked Counsel if that is within the parameters. Attorney Zamarka said that it would not be out of order as long as it would not exceed the 118,000 that Landmark is seeking. (2) Mr. Mingo moved to grant Costco sewer capacity in the amount of 7,650 GPD as requested. Mr. DiGiovanna seconded the motion. Ms. Russell said that she has a concern with going with an estimate on the 262,000 rather than a more definitive number. Mr. Nickerson said that he has enough con?dence in Mr. Kargi that he is pretty accurate and further the Court is aware of the number of 160,000 given to Gateway. Further, he added that he would love to pursue the State capacity that is sitting out there unused even though they claim that they wiil use it. Ms. Russell said that she feels that it is difficult to wrap yourself around as the ?gures ?uctuate. Mr. Kargl said that is exactly why he took an average. Mr. Mingo said that based on the new resolution that those below 5,000 can just have it two of those added together wiit have eaten up the 7.650 and them some so it is a moot point. Mr. Jacques asked Mr. Kargl what he woutci be asking the DEEP. Mr. Kargt said that he would be asking what they would be looking at as it states that we have 15% of the 10M but what is the metric that is being used and is that the starting number. Mr. Mingo asked Mr. Kargl what the next step would be. Mr. Kargi asked that he be allowed to complete the process that he has started. Mr. Nickerson called for a vote on the motion. Vote: 7 1 0. Motion passed. Against: Ms. Russell (Note: a brief break was taken here) 5. Set Public Hearing Dates for Sewer Capacity Applications Mr. Nickerson asked Attorney Zamarka for input. Attorney Zamarka said that in fotlowing the iand use statutes for time frames that he would suggest that any new application public hearings are set towards the farther and. Mr. Nickerson said that they woutd have to set more meetings as there are a number in the pipeline so the parameters will have to be set. They would have to determine if they woutd give sewer capacity ?tickets? and if they would have an expiration date. They have specific meeting dates to establish procedures. Attorney Zamarka said that he is not aware of other applications that were speci?c to this and not a zoning application. He suggested that perhaps as of this date that they have 65 days to schedule. East Lyme Water a Sewer Commission Regular Meeting Minutes -- November 13, 2018 2 Mr. Mingo asked for a legal opinion regarding what would stop the Old Lyme beaches from going to Waterford or New London for sewer capacity and bypassing as completely. Attorney O'Connell, Town Counsel said that the DEEP does not recognize beach communities as a WPCA agency. Those communities are a quasi-municipality and are communities that are setup by special act. Mr. Nickerson suggested that they set the public hearing for JAG, Gateway ii (120 apartments) and Pazzaglia for January before their regular meeting on that same evening as long as it falls within the 65 days. it was determined that they would have to hold that public hearing on January 8. 2019. Mr. Nickerscn asked Mr. Kargl to have the capacity information for them for their December meeting. 6. Landmark Remand Hearing Procedure Attorney Zamarka noted the current status of the case for Landmark and that it was remanded a number of times. The latest being that in August the Judge upheld the decision of Judge Cohen's ruling. They petitioned the Supreme Court and the Supreme Court denied their petition so Judge Cohen?s decision stands. He explained that while the 14,0009pd ?gure was low that is does not mean that the 118,0009pd that they requested has to be granted. The Commission has to grant somewhere between the 14,000 and 118,000 while taking into consideration that they cannot deny use of the property or make it non?usable. He noted that the New Jersey case that was cited in Attorney Hollister?s letter would not be relevant here. He added that Attorneys Hollister and Reynolds have requested to address the remand process in the Landmark case. Mr. Nickerson asked if he would suggest how/when they should proceed. Should they set up special meetings. Attorney Zamarka said that he feels that it would be in their best interest to reach a decision on the Landmark capacity prior to the other applications. They have more than suf?cient information to work with on that and would concur that special meetings should be set. Mr. Mingo said that he takes issue with listening to anymore attorneys this evening and that without the capacity figure that it is a waste of time. Mr. Nickerson said that he would allow them only three (3) minutes each and asked that they focus on the remand issue. Attorney said that he mostly agrees with Mr. Mingo especially on the capacity issue/DEEP as otherwise they are ?ying blind. He cautioned that their decision cannot be on controlling land use and that the decision is between 14,000 and the figure that they provided this evening of 100,000 but should be no where near the 14,000 gpd. They need to get a fair number and that legally they should be granted the 100,000 and then let the land use arena make their determination. Attorney Reynolds said that Attorney Hollister has said that they have to allow the project to proceed but that is not what was said. While they cannot shut down the project, 814 units are not reasonable as there has not been an 800 unit project in this area. Gateway may in the end be 400 units but that would have been the maximum number so 814 units are just unreasonable. Further they haven't actually seen projects of more than 100 units so to do that size project would be far less than for the 800 that they are seeking. Mr. Nickerson said that they would have their Regular Meeting on December 11, 2018 and a Special Meeting on December 18, 2018 for the Landmark remand. Mr. Mingo noted that they need to remember that they are m; a land use agency. 7. Waterfordn?hree Beaches Letter Mr. Nickerson asked Attorney O?Connell to review this. Attorney O?Connell explained that they had received a letter from Chairman Green of the Waterford Utility Commission stating that they object to East Lyme contracting with three (3) beach communities East Lyme Water Sewer Commission Regular Meeting Minutes -- November 13, 2018 3 (Old Lyme) to take their sewer flow as that fiow will affect Waterford's sewer system infrastructure without Waterford approving the terms and conditions of use. Mr. Nickerson sent a letter in response stating that they could not ?nd anything prohibiting it and that in fact they were ordered by the CT DEEP to accept sewage flow from the beach communities and to enter into an agreement with them. This was imposed upon East Lyme and the DEEP did not order Waterford to do anything. Also, East Lyme paid Waterford a substantial sum for the right to transmit sewage (up to 8M gpd) through Waterford?s mains. 8. Billing Adjustments There were none. 9. Approval of Bills Mr. Nickerson called for a motion on the Niantic Pattagansett Pump Station PER bill. (3) Mr. DiGiovanna moved to approve payment of the following Niantic Pattagansett Pump Station PER biil: Weston Sampson, lnv, #485250 in the amount of $58,605.00. Mr. Zolier seconded the motion. Vote: 8 - 0 0. Motion passed. Mr. Nickerson called for a motion on the Booster Station Upgrades bills. (4) Mr. DtGiovanna moved to approve payment of the following Booster Station Upgrades bills: Integrated Control Systems tnv. #3202 in the amount of $5,700.00 and Integrated Control Systems lnv. #3203 in the amount of $710.00. Mr. Zoller seconded the motion. Vote: 8 - 0 0. Motion passed. Mr. Nickerson calted for a motion on the Water Main improvement bills. (5) Mr. DiGiovanna moved to approve payment of the following Water Main Improvement bills: Construction lnv. #73558 in the amount of $12,193.00 and 3&1. Construction lnv. #73559 in the amount of $5,311.49. Mr. Spencer seconded the motion. Vote: 8 - 0 0. Motion passed. 10. Finance Director Report Ms. Johnson said that she would get the information to them once ali of it was entered into the system as it was not ready at this time. She recatied that she had requested the closing out of projects and that had been done along with another one that was completed. 11. Water 8: Sewer Operating Budget Status Reports Mr. Bragaw noted that they had been provided with the spreadsheet as well as the assumptions that he had made with regard to the Welt 1A and 6 upcoming projects. He noted that it assumes a 2.75% water budget increase each year over the next eight (8) years. There are anticipated increased revenues as well and with all of this in mind he said that he felt that they could reasonably afford going forward with the Well 1A and 6 projects white still being able to pay for and implement the meter replacement project. He also noted that they need to get our of the meter deposit business. 12. Water Project Updates - Welt 1A and 6 Treatment Plant Modifications and Upgrades -- Discussion and Possible Project Authorization for Construction Phase Mr. Kargl recalled that the issue here was affordability and that Mr. Bragaw was working on that aspect. Mr. Bragaw explained that they had a debt spike this year but then it goes way down so he felt for the reasons cited above that they could afford this project. East Lyme Water Sewer Commission Reguiar Meeting Minutes -- November 13, 2018 4 (6) Mr. DiGiovanna moved to toward the Well 1A and Well 6 Water Treatment Project with an estimated cost of $4,640,000 to the Board of Selectmen for approval and to begin the authorization process. Mr. Zoller seconded the motion. Vote: 8 0 - 0. Motion passed. 13. Correspondence Log There were no comments. 14. Chairman?s Report Mr. Nickerson reported that he had held a meeting on a new Public Safety building going forward and that the proposed project is for for the current Honeywell building as they are leaving their building here and moving to another area in Connecticut. They have made a purchase and sales agreement that is contingent upon all approvals. They need to get the Police out of the-downtown building which has a lot of issues not to mention space. He said that he would like to do this within 120 days and get it to referendum as it is a very important project and this building is well set up for this and for future expansion of the important emergency management system. 15. Appoint Water Regulations Subcommittee Mr. Bragaw said that they are moving forward with the water regulations as this is necessary to support the meter replacement project. Mr. Mingo said that the subcommittee that is for the sewer regulations serves for both so they would also work on the water regulations. Mr. Bragaw asked if Mr. Mingo. Mr. Zoller and Ms. Russell are still interested in serving on this subcommittee and if anyone else wishes to serve on it, they could let him know. 16. Assistant Utility Engineer Update Mr. Bragaw said that they held interviews and that the skill set is a tough one. They have found that they need very strong water skills so they decided to go back out and advertise again for that certain type of person and skill set as he suspects that some of the people who may have been interested were very strong with the water side but did not apply due to how the description was worded. They will re? advertise and reaassess. 17. Staff Updates a. Water Department Report Mr. Murphy noted that there is still 31% that has to come from New London as we have only taken 69%. He asked if they are going to make it before they have to start pumping back. Mr. Kargl said that they are using it to ?ush the hydrants in the north end of Town and that Well 1A will also go off for surging so that will mean that they will utilize more. He said that he is hoping that they will get close to the 100%. b. Sewer Department Report There were no comments. 18. Future Agenda Items No comments. 19. ADJOURNMENT Mr. Nickerson called for a motion to adjourn. East Lyme Water Sewer Commission Regular Meeting Minutes November 13, 2018 5 (7) Mr. Murphy moved to adjourn this Regular Meeting of the East Lyme Water Sewer Commission at 8:51 PM. Mr. DiGiovanna seconded the motion. Vote: 8 0 0. Motion passed. Respectfully submitted, Karen Zmitruk, Recording Secretary East Lyme Water Sewer Commission Regular Meeting Minutes November 13, 2018 Exhibit NO. HHD LND CV 15 60566378 SUPERIOR COURT LANDMARK DEVELOPMENT . GROUP LLC, ET AL. JUDICIAL DISTRICT OF HARTFORD v. LAND USE DOCKET EAST LYME WATER AND SEWER COMMISSION NOVEMBER 27, 2018 AFFIDAVIT OF GLENN RUSSO I, GLENN RUSSO, being duly sworn, depose and state as follows: 1. I am over the age of 18 and believe in the obligations of an oath. 2. I am a resident of Middletown, Connecticut. 3. I am President of Landmark Development Group, LLC and Jarvis of Cheshire, LLC. 4. At its regular meeting on November 13, 2018, the Commission scheduled a Special meeting for December 11, to consider what new criteria it will devise and use to act on Landmark's application on remand. 5. During the November 13 discussion, Chair Nickerson stated that action on Landmark would be based on "what is fair, given the size of our town.? 6. At the November 13 meeting, Attorney Roger Reynolds, representing environmental intervenors, advocated that the Commission base the sewer allocation on controlling land use, by granting capacity for 110 residential units (about 20,000 GPD), that being the "average size? of a 8?30g affordable housing development. 7. At the November 13 meeting, the Commission discussed action in January 2019 on other sewer capacity applications, including 120 additional residential units for Gateway (and thus above its 275 unit plan; and a new application seeking 86,000i GPD. 7135041 8. At the November 13, 2018 hearing on the Costco application, Sewer Administrator Kargl stated that the Gateway residential portion is actually using "about halt? of its projected need. 9. At the November 13, 2018 hearing, none of the Commissioners or the Town Attorney discussed giving Landmark's application, which dates to 2012, priority over applications ?led later, much less in 2018. XL 9244*? GLENN RUSSO Subscribed and sworn to before me this 27th day of November, 2018. .ommissioner of uperi CHRISTAL SHEPPARD Notary Public My Commission Expires NOTARY PUBUG COMMISSION 90911158 MM. 31. 2022 Exhibi $1 3 AGENDA it .. EAST LYME mm a SEWER if I 4 2?31 1 7 Sewer Department Report Oct-17 Running Avg: *Dalty Avg: Batty Max: Batty Min: Nov-17 822.550 GPD 752.273 GFD 952.760 GPD 576,560 Daily Average as 3 Percent of Running Average: Dally Average as 3 Percent at 1.5 M80 Allotment at State CT Fiows: 91.45% 50.15% DOC Camp Niantic Rocky Neck pow Total Actual GPD AVG. 149,741 4,555 0 9,713 134.009 Design GPD AVG. 250.009 58.400 54,600 105,000 475,000 of Design GPO 59.9% 7.80% 0 9.25% 34.31% ?In of East Lyme Average Daily Ftow 19.91% 0.61% 0.00% 1 29% 21.80% of East Lyme 1.5 MGD Allotment 9.98% 0.30% 0.00% 0.65% 10.93% Footnotes: NR No Reading EXHIBITA EAST LYME SEWER FLOWS HISTORY JAN. FEB. MAR. APR. MAY JUN. JUL. AUG. SEPT. OCT. NOV. DEC. AVG. 2010?' 1.037.939 1.001.094 1.424.903 1.341.021 1.110.627 1.067.205 1.117.093 1.040.309 932.705 928.254 869.937 902.347 1.053.094 2011 910.010 959.700 1.001.537 939.509 1.046.507 1.017.256 1.027.843 970.097 1.107.520 905.767 903.002 1.133.107 1.010.895 2012 955.431 012.442 885.778 01 5.628 1.016.580 995.993 1.026.063 1.018.430 912.093 049.710 953.598 983.849 961.551 2013?? 975.330 1.010.625 1.139.232 1.042.500 1.057.182 1.243.099 1.217.939 1.203.703 1.288.055 1.020.390 920.015 944.611 1.089.279 2014 1011.343 994.771 1.026.812 1.120.050 1.145.107 1.007.792 1.030.503 999.147 837.700 052.201 797.709 335.250 971.886 2015 787.645 832.581 1.017.280 038.801 913.816 880.190 1.048.427 977.543 878.563 851.521 803.842 788.121 884.041 2015 747.294 009.701 790.051 799.011 777.440 015.201 079.952 068.636 762.544 739.247 709 491 728.649 785 300 201? 784.837 755.540 777.452 807.151 872.288 849.504 883.851 873.017 759.493 752.273 822.550 (1) March 30. 2010 storm event? 8.88 inches of 7910/1643 inches of ram for the month (Wei: 3131138 rain gauge) (2) 1055100009 of ram for June 2013 (W511 3.1038 rain gauge) 7 18 Inches of rain for July 2013 (Well ENBE ram gauge) "In 44- Prev. Yr. 5 03% 5.44% 4.59% 12.62% 12.20% 4.20% 0.44% 0.50% 0.91% 1.90% 400.00% 400.00% 3.07% Precip. Totai Precip. 2017 (10.) 3.87 . 2.05 3.89 7.34 6.03 4.83 2.23 2.79 2.42 7.22 42 57 EXHIBITB