Washington State Department of Transportation (WSDOT) Fish Passage Program Roger Millar Paul Wagner WSDOT Keith Metcalf Secretary Environmental Services Office Deputy Secretary South Sound Estuary Association October 20, 2016 Fish Passage at Highway Culverts • WSDOT is responsible for – o7,056-mile long highway system o>3,600 crossings of fish bearing streams • WSDOT recognizes – o Poorly designed/installed culverts can delay or block fish access to habitat. o Culverts can fail over time and become fish barriers. 2 This Fool's Too Shallow What makes a fish passage barrier? . Ljump?s . Too HighhHey!Wha+ AbomL Transportation Fish Passage Barrier Culvert Conditions: Excessive Water Surface Drop Kitsap Sun photo WDFW photo High Velocity Shallow Water Depth WDFW photo WDFW photo WDFW photo WDFW photo 4 Other Fish Passage Barrier Conditions: Trash Racks and Flap Gates Culvert Plugged with Sediment or Debris Deteriorating Culverts WDFW photos WSDOT Fish Passage Program • Partnership with WDFW starting early 1990’s • Fish barrier inventory & prioritization • Statewide: 7,143 water crossings inspected • 3,623 were identified as fish bearing waters • About 2,000 fish barriers identified • Updated in 2009 • Fish Passage Features o Road Crossings o Dams o Fishways o Natural Barriers • Surface Water Diversions • Habitat Assessment • Prioritization http://wdfw.wa.gov/publications/pub.php?id=00061 7 How WSDOT corrects its fish passage barriers • By constructing stand-alone fish passage projects using dedicated funding. • Through safety and mobility road construction projects. • And during other road maintenance projects when heavy equipment is already mobilized in the area. Fish Passage Barrier Correction • In 1991 WSDOT developed a program to • identify high priority barriers, • correct barriers with dedicated fish passage funds, and • correct barriers during transportation projects • As of July 2016, WSDOT has • completed 301 projects opening up 1,000 miles of potential upstream habitat. 20 additional barriers were corrected in 2016 9 . 'SzInJuan .- . 0. a . Skat?it . .0 a . Island . 'In ?0 I 'o hatcnm ()Iumn" In ?I?uId . ?ofgminc; . 0? .o ,3 Jefferson . Douglas I .. (Iran! II Irhnr o. Killilas A 90 . \(Iams '5 .0 . - ?hitm anI?rIInklIn Q. . (.?nr?cld' . 82 . Yakima . (olunIhIa . . . - ?alla Asmin (mllt/ Benton 0 . . Skzunaniu . - . K'it?kim WSDOT Fish Passage .(?lark I, 0.0 A 0 Fixed In Design or In Construction 0 Barriers 10 Prioritizing Culverts for Correction Factors include: • • • • • Habitat Gain – quality and quantity Severity of the barrier Species presence – number that benefit from the habitat Endangered Species Act species – presence and number Cost of the project – barrier correction costs cover a wide range: from solutions that modify existing culverts to those that replace a culvert with a bridge • Coordination with others 11 Culvert Case US v WA Background • 1850’s Stevens Treaties: Tribes ceded lands; reserved fishing rights. • 1974 Boldt Decision: Treaties entitle Tribes to a fair share of fish, while ensuring habitat that supports fish. • In 2001, Twenty-one Western WA Tribes filed suit against the State claiming culverts were blocking substantial amounts of salmon habitat, thus reducing the salmon available for harvest. • In 2007, Federal District Court Judge Martinez agreed to the claim and said the State was in breach of the Tribes’ treaty rights. • In October 2009, the court convened a trial to determine what the remedy should be. • On March 29, 2013, Judge Martinez issued a permanent injunction for the State to accelerate barrier correction within the case area. 12 US v. WA Culvert Injunction March 2013 Who? State of Washington WSDOT, WDNR, WDFW, Parks Where? Case area Western Washington WRIA’s 1-23 Area subject to culvert injunction. How many WSDOT barrier culverts? About 980 total including (as of August 2015) About 818 with Significant Habitat (>200 m upstream) * Corrected 21 injunction barriers since 2013 * Correcting 20 injunction barriers in 2016 13 Injunction Requirements o Fix WSDOT barriers blocking 90% of potential upstream habitat by March 2030. o Correct culverts with <200 meters of upstream habitat at the end of their useful life or sooner as part of larger transportation projects. o Bridge or stream simulation culvert corrections. o Ongoing efforts to identify and assess barriers, monitor effectiveness, and maintain culverts. o Coordinate all efforts with tribes. 14 Culverts Block varied amounts of habitat Percent of Potential Habitat Opened by Fixing Barriers 42.0 39.0 36.0 Potential Lineal Gain in Miles 33.0 10 % 30.0 30% 20% 51 Projects 27.0 50% 40% 88 Projects 60% 153 Projects 24.0 70% 21.0 80% 18.0 15.0 90% 12.0 9.0 6.0 3.0 0.0 0 50 100 150 200 250 300 350 400 450 500 550 Number of Fish Passage Projects 600 650 700 750 800 850 Injunction Barrier Correction Standards o Bridges – full channel spanning bridges facilitate habitat connection for fish and wildlife o Stream Simulation – mimics natural stream channel processes throughout the culvert Bridge Stream Simulation Culvert 16 Q100 QBFW Bridge example BFW BFW Stream Simulation Culvert examples 1.2BFW + 2 ft 1.2BFW + 2 ft http://wdfw.wa.gov/publications/01501/ 17 Stand-alone Fish Passage Barrier Correction Project BEFORE: SR 530 Fortson Creek, west of Darrington. Previous culvert had excessive outfall drop AFTER: Fortson Creek with new stream simulation crossing 18 Before Stand-alone Barrier Correction Project SR 99 WF Hylebos Creek During 6 ft box with deficient fishway After • $2.6 M cost • 2 miles habitat gain • Chum, coho, steelhead, coastal cutthroat, & resident trout New 20 ft wide structure 19 A V, Washington State Department of Tiansporlat SR 99 Hylebos Creek -year one 2016 Corrections as part of a larger transportation project: SR 520 Culvert 1 Culvert 2 Culvert 3 21 Correction as part of a project: SR 520 WB off-ramp Yarrow Creek Before: 3.5’ x 2.5’ squash culvert • Part of larger transportation project • 2.8 miles habitat gain • Sockeye, coho, steelhead, resident trout After: 16’ box 22 Chronic Environmental Deficiency Project: SR 203 Coe Clemons Creek Before Undersized culvert regularly plugged with debris requiring maintenance After: culvert replaced with a 25 ft wide stream simulation culvert https://www.youtube.com/watch?v=nMixgoOOSoQ 23 What makes a successful fish passage project? Built according to plans: Bed material right size, well-graded, well-placed Critical elevations verified Proper wood placement Other habitat elements October 2015 November 2015 24 IS Passage Monitoring A Washl Stat Domm of ansporlation Fish Passage Coordination • WSDOT coordinates barrier correction efforts with private landowners, enhancement groups, state and local governments, tribes other entities. • Fish Passage Barrier Removal Board in Washington o 2014 Legislation, HB 2251 o WDFW, WSDOT, DNR, Governor’s Salmon Recovery Office, Tribes, local governments participate o Purpose is to develop statewide strategy based on maximizing habitat recovery through a coordinated, watershed approach o Streamlined permitting for fish passage projects 26 Partnership Example: I-5 Squalicum Creek • WSDOT partnered with the City of Bellingham, WDFW, the WA Department of Ecology, and others to restore Squalicum Cr, which flows to Bellingham Bay. • In 2013, WSDOT constructed an open, fish-friendly culvert to protect the existing I-5 bridges. • In 2015, the stream was re-routed by the City of Bellingham under the I-5 bridges into an old, historic channel. • This project will open up ~22 miles (35 km) salmon habitat. Before – twin culverts are a velocity barrier After – stream flows through open culvert 27 SR 548 Terrell Creek After construction – 2011 • • • • 3 years after construction – 2014 Good installation Dry bank most flows Natural streambed Still performing well A 2007 - WSDOT culvert replacement SR 548/ Blaine Rd Terrell Creelk ?sh passage inventory I 2008 - Whatcom County fishway Hekerville Rd A f? 2008 - dam removed 2011 - WSDOT culvert SR 548/Grandview Rd m1 mow, Ald ergrove Rd 2016 - Proposed Whatcom County culvert replacement project replacement 3 2014 - bridge 7' Private road crossing All n. f. 2012 - WDFW dam modification l?shway Lake Terrell VWdife Area Legend Rivers Streams State Routes (1 2.32, n. im-I INS- 0 Fish Passage am? Soccesg?sri. Deborme. NAVTEQ. TomTom. lnta?map. inc: - tPCorp.. GE- 0 U863. FAO NPS . Fish Barrier Culvert f? 1? NRCAN. Geoaas?. iGNmriu?gtecNL. Survey Esri?jiapan METI. Ichigg {Hong Kong). swiss topo. and th? GIS User Community I ff 2 1 2 Ewes Project Bundling Example – Kitsap Peninsula • • • Minimizes impacts to public Full closure shortens construction duration Economy of scale 30 a? 5i} SR 3 Twanoh Creek under Construction as(I) .1 .1 . a; he .. ,mepr.? mm mow 08% mg ?k (wxi?k ?Mv 920m x090 ?258 Sm mm 7" Washington State V, Department of Transportation Traffic Cameras Projects Business Environment Maps Data You are here: Home Agency Projects Fish Passage SID Project Info - Home - Coordinating with Others - Costs for Fish Barrier B_e_r_n_qxa_ - Determining Culvert Repair Priorities - Environmental Stewardship - Federal Court Injunction - Fish Barrier Correction Construction Process - Frequently Asked ueonns - Fish Passage Responsibilities - Culverts as Barrier to - Number of Fish Barriers - Fish Passage Contacts - Working with Partners Pubications - Barrier Correction Folio - 2014 Annual Fish Passa Re ort df 9.7 mb Fish Passage State highways cross hundreds of streams and rivers in Washington. At many of those locations, culverts are too small or otherwise inadequate to allow ?sh to migrate upstream and as necessary for growth and reproduction. WSDOT has been working for more than two decades to correct these inadequate culverts to improve ?sh habitat. Find Fish Passage Projects Before Photo US 97 culvert that blocked ?sh passage at Butler Creek, a tributary to the Little Klickitat River near Goldendale. After Photo Why is WSDOT ?xing ?sh barriers? - Environmental Stewardship Related to Fish Passage - Fish Passage Responsibilities - Federal Court Injunction Related to Fish US 97 at Butler Creek after the $3.5?million barrier removal project was completed in April 2013. Passage What makes a ?sh barrier? Fish Passage Partners Email updates Waf?e-main 35 Questions or Comments? Paul Wagner WSDOT Environmental Services Office (360) 705-7406 36 WSDOT Fish Passage Program Comprehensive Fish Passage Inventory 1991-present Fish Passage Inventory Database Dedicated Fish Passage Barrier Removal Program • Washington Department of Fish & Wildlife (WDFW) inventories fish passage barriers on WSDOT Highways. • WDFW conducts Habitat Assessments to help prioritize barrier correction efforts. • WDFW maintains central data repository for culvert, GIS, fish use, and habitat information resulting from inventories. • WSDOT prioritize, select, implement, and monitor fish passage projects. • Stand-alone Projects (Dedicated Funding) • Chronic Environmental Deficiency (CED) and Major Drainage • Safety and Mobility Projects (larger transportation projects) • Other partnerships and Grant Funding 37 Wildlife Passage: an added benefit US 101 south of Aberdeen, WA Before – 1.22 meter (4 ft) After – 4.9 meter (16 ft) constructed in 2009 US 101- Mosquito Creek 38 Wildlife Passage Benefits Goldendale, WA Before – 3.2 meter (10.5 ft) US 97 - Butler Creek 39 US 97 - Butler Creek 65 ft) bridge 8 meter After 19 constructed in 2012 U887 BUTLER CREEK 'f?l?x . ,rrAnderson Creek