Case: 5:09-cv-00272-JRA Doc #: 262 Filed: 12/17/19 1 of 7. PageID #: 33263 UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF OHIO EASTERN DIVISION UNITED STATES OF AMERICA Plaintiff, v. CITY OF AKRON, et al. Defendants. ) ) ) ) ) ) ) ) ) ) ) CASE NO.: 5:09CV272 JUDGE JOHN ADAMS ORDER Four hundred thirty-three million gallons. 433,000,000. By the parties’ current estimates, that is the amount of combined sewage that will flow into Akron’s waterways exclusively due to Akron’s failure to timely complete the Ohio Canal Interceptor Tunnel.1 A. Background On January 17, 2014, the Court approved the parties’ Consent Decree which incorporated their agreed-upon Long-Term Control Plan Update (“LTCP”).2 In reaching its decision, the Court heard testimony about the LTCP projects from Mark Klingenstein, including: “The centerpiece of the program is two large underground storage tunnels that together will have a total volume of almost 50 MG – million gallons.” Doc. 129 at 14. 1 This number is premised upon the current expected completion date, June 30, 2020. The figures related to the impact of the tunnel are taken directly from calculations made by the United States utilizing the model of the sewer system created by the City of Akron. 2 The Court has also approved two subsequent Amendments to the Decree. On September 20, 2016, the Court approved an amendment to change the sequencing of upgrades to the wastewater treatment plant and to eliminate the City’s requirement to build a parallel relief sewer. On December 17, 2019, the Court approved the Second Amendment to the Decree. The Second Amendment permitted the City of Akron to replace numerous rack basins with green infrastructure and permitted the City to utilize BioCEPT technology in place of BioActiflo. 1 Case: 5:09-cv-00272-JRA Doc #: 262 Filed: 12/17/19 2 of 7. PageID #: 33264 Klingenstein described the first tunnel project as follows: “In the case of the Ohio Canal tunnel, it's a 28-foot diameter tunnel which is certainly a very substantial tunnel. It's a bit over a mile long. Somewhat over 25 million gallon capacity.” Doc. 129 at 26. The parties described the Ohio Canal Interceptor Tunnel (“OCIT”) as a “signature[] element” of the LTCP Update (Doc. 123-1 at 11-12) and a “critical aspect of the Decree.” Doc. 123-1 at 41. A fully operational OCIT would eliminate, on a yearly basis, the discharge of 289 million gallons of combined sewage overflow into Akron’s waterways. B. Akron Continues to Pollute the Cuyahoga River and Cuyahoga Valley National Park More than eight years after the parties first requested entry of the Decree and while publicly touting that it has made “significant progress in upgrading its sewer infrastructure,”3 Akron continues to significantly pollute the Cuyahoga River and the Cuyahoga Valley National Park. Akron’s failure to comply with the parties agreed-upon construction schedule has resulted in millions of gallons of untreated or partially treated sewage being discharged into Akron’s waterways.4 Utilizing Akron’s own modeling, the U.S. EPA estimated that a one-year delay in completion of the OCIT would result “in the discharge of 289 million gallons more of untreated combined sewage than would have been discharged had the OCIT been completed on time.” In other words, roughly 800,000 gallons of combined sewage is discharged into the surrounding waterways for every day that the OCIT’s completion is delayed. 3 http://www.akronwaterwaysrenewed.com/news/city-of-akron-celebrates-progress-in-consent-decreeprojects.aspx (last visited on 12/10/19). 4 Despite U.S. EPA and Ohio EPA having knowledge of Akron’s non-compliance, neither entity has made any effort to quantify the actual environmental harm caused by Akron’s delay in completion of the OCIT. 2 Case: 5:09-cv-00272-JRA Doc #: 262 Filed: 12/17/19 3 of 7. PageID #: 33265 Until recent developments, the Court, and by all appearances the public as well, was under the impression that the deadlines for projects in the Decree and LTCP were being upheld by all those involved. However, recent inquiry by the Court related to the parties’ request to enter a Second Amendment made it clear that the Court’s impressions were erroneous. During an April 18, 2019 telephone conference, the parties indicated that the OCIT had not been completed by the date required in the LTCP, December 31, 2018. On July 30, 2019, the United States provided an update that the OCIT was then 374 days behind schedule – or would be completed in early January 2020. When asked if the environmental harm related to the delay had been calculated, the United States replied: “We haven’t taken any specific steps to model what the harm might be.” Doc. 242 at 6. The United States, however, indicated: “But we have no doubt[] there is significant environmental impact, and we will proceed with that expectation.” Doc. 242 at 7. On October 30, 2019, the City of Akron provided the Court its most recent update with respect to completion of the OCIT. The City indicated that with the removal of certain items that were not required to meet full operations, the newest estimate for completion of the OCIT is June 30, 2020.5 The United States provided its most recent update on October 30, 2019 as well. Within that response, the United States indicated that it had not received a substantive response to its July 26, 2019 letter requesting information on the OCIT and that it did not expect to receive such information until November. C. Inaction by the United States EPA and Ohio EPA 5 Based upon the to-date history of the project, it is difficult to place any confidence in this newest estimate for a completion date. 3 Case: 5:09-cv-00272-JRA Doc #: 262 Filed: 12/17/19 4 of 7. PageID #: 33266 The United States EPA defines its mission as follows: “The mission of EPA is to protect human health and the environment.” https://www.epa.gov/aboutepa/our-mission-and-what-we-do (last visited 12/2/19). “EPA is returning to its core mission of protecting human health and the environment. We are committed to providing clean and safe air, water, and land for all Americans. We are building on the enormous progress EPA has made since it was established in 1970 – increasing the safety of lakes and rivers, reducing smog, cleaning up contaminated lands, and guaranteeing the safety of chemicals in the marketplace.” https://www.epa.gov/home/returning-epa-its-core-mission (last visited 12/2/19). Similarly, Ohio EPA describes its role as: “Ohio EPA’s goal is to protect the environment and public health by ensuring compliance with environmental laws and demonstrating leadership in environmental stewardship.”6 Despite the above, neither EPA entity has taken any action to remedy the City of Akron’s non-compliance with the deadline for the “centerpiece” of the Consent Decree, the OCIT. For that matter, neither entity has engaged in any activity to even ascertain the environmental damage flowing from Akron’s failure to meet its deadlines. When the Court ordered the parties to provide updated information regarding the future completion date for the OCIT, the U.S. EPA responded as follows on October 30, 2019: “The United States expects that the City of Akron, which has far more complete and current information, will respond on this topic.” Doc. 257 at 2. U.S. EPA went on to note that it had requested updated information from the City of Akron on August 21, 2019, but “Akron has not yet provided the information requested in our August 21 letter.” Doc. 257 at 2. U.S. EPA continued by indicating that it expected the City of Akron to “begin 6 https://epa.ohio.gov/About (last visited 12/11/19). 4 Case: 5:09-cv-00272-JRA Doc #: 262 Filed: 12/17/19 5 of 7. PageID #: 33267 to provide” the information sought in the August 21, 2019 letter by “mid-November” – some four months after its request. Ohio EPA provided the Court even less information. With respect to the delay in completion of the OCIT, Ohio EPA responded that it “expects that the City of Akron will report on this topic.” Doc. 258 at 1. As detailed above, these are the state and federal entities charged with protecting the waterways surrounding Akron and enforcing the terms of the Decree. With respect to completion of the OCIT, the centerpiece of Akron’s system, they have wholly abdicated their roles. In correspondence with the City, U.S. EPA expressed that it was “disappointed that the City had not provided the information in a more timely fashion” but that it understood “the concerns the City has expressed that fully responding to the information request could disrupt ongoing discussions between the City and its project contractor.” Doc. 257-3. In other words, U.S. EPA has allowed Akron to thumb its nose at the deadlines in the Decree. U.S. EPA has allowed Akron to evade providing basic information about an expected completion date over unspecified concerns regarding the contractor. In the interim, the Cuyahoga River and Cuyahoga Valley National Park have endured an additional twelve months of pollution from Akron’s sewer system. Those same sensitive areas are expected to endure, at a minimum, another six months of millions of gallons of pollution. Meanwhile, U.S. EPA is “continuing to evaluate all enforcement options.” consideration. However, one option has been wholly removed from Current U.S. EPA policy no longer allows the EPA to pursue supplemental environmental projects from municipalities. In other words, one avenue of 5 Case: 5:09-cv-00272-JRA Doc #: 262 Filed: 12/17/19 6 of 7. PageID #: 33268 mitigating the damage caused by Akron’s continued pollution has been foreclosed entirely. D. The Court’s Role The Consent Decree contained Section XXIII, Retention of Jurisdiction, which reads as follows: The Court shall retain jurisdiction of this case until termination of this Consent Decree, for the purpose of resolving disputes arising under this Decree or entering order modifying this Decree, pursuant to Sections XIV (Dispute Resolution) and XXIV (Modifications), or effectuating or enforcing compliance with the terms of this Decree. Doc. 155 at 56. The Sixth Circuit also recently explained in a matter involving alleged violations of the Clean Water Act by a municipality: A consent decree is a settlement agreement subject to continued judicial policing. It is well-settled that courts retain the inherent power to enforce agreements entered into in settlement of litigation pending before them. We have emphasized that the district court’s inherent power is broad, and the court’s choice of remedies is reviewed for an abuse of discretion. United States v. Bd. of Cty. Commissioners of Hamilton Cty., Ohio, 937 F.3d 679, 688 (6th Cir. 2019)(citations, quotations, and alterations omitted). The Sixth Circuit went on to note that “[d]istrict courts possess broad authority to enforce the terms of consent decrees, even where doing so requires interfering with municipal prerogatives or commitments.” Id. at 691. Based upon the above facts, the parties are hereby ordered to show cause why the Court should not utilize its retained jurisdiction and inherent power to appoint a monitor to oversee compliance with the Decree. The record before the Court is clear. The parties do not dispute that the City of Akron has not complied with the deadline for completion of the OCIT. It is further undisputed that the parties failed to take any affirmative steps 6 Case: 5:09-cv-00272-JRA Doc #: 262 Filed: 12/17/19 7 of 7. PageID #: 33269 to inform the Court of this noncompliance. Additionally, while the U.S. EPA and Ohio EPA continue to evaluate their options, they have taken no action to compel Akron’s compliance, nor has either entity proposed any solution to mitigate the harm to the environment flowing from Akron’s noncompliance. This past June marked the 50th anniversary of the Cuyahoga River Fire – the event which generated a public response so strong that it culminated in the creation of the U.S. Environmental Protection Agency.7 Regulations such as the Clean Water Act helped to renew the area, and the Cuyahoga Valley National Park has annually hosted more than 2 million visitors every year following entry of the Consent Decree.8 Unfortunately. Akron continues to impact the ability of those visitors to fully enjoy all the Park has to offer by its continual pollution of the waterways that run through the Park. As the result of this continued pollution and the inaction of the governing agencies, the Court is left with no alternative other than to explore the appointment of a neutral monitor to help ensure future compliance with the deadlines and standards in the Consent Decree. The parties shall submit their responses to this Order by no later than January 10, 2020. IT IS SO ORDERED. Date: December 17, 2019 /s/ John R. Adams_______ JUDGE JOHN R. ADAMS UNITED STATES DISTRICT COURT 7 https://www.history.com/news/epa-earth-day-cleveland-cuyahoga-river-fire-clean-water-act (last visited 12/16/19). 8 https://irma.nps.gov/ (last visited 12/16/19). 7