Coast Guard Polar Security Cutter (Polar Icebreaker) Program: Background and Issues for Congress Updated June 10, 2020 Congressional Research Service https://crsreports.congress.gov RL34391 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Summary The Coast Guard Polar Security Cutter (PSC) program is a program to acquire three new PSCs (i.e., heavy polar icebreakers), to be followed years from now by the acquisition of up to three new medium polar icebreakers. The PSC program has received a total of $1,169.6 million (i.e., about $1.2 billion) in procurement funding through FY2020, including $135 million in FY2020, which was $100 million more than the $35 million that the Coast Guard had requested for FY2020. With the funding it has received through FY2020, the first PSC is now fully funded and the second PSC has received initial funding. The Coast Guard’s proposed FY2021 budget requests $555 million in procurement funding for the PSC program. It also proposes a rescission of $70 million in FY2020 funding that Congress had provided for the procurement of long lead time materials (LLTM) for a 12th National Security Cutter (NSC), with the intent of reprogramming that funding to the PSC program. The Coast Guard states that its proposed FY2021 budget, if approved by Congress, would fully fund the second PSC. The Coast Guard estimates the total procurement costs of the three PSCs as $1,039 million (i.e., about $1.0 billion) for the first ship, $792 million for the second ship, and $788 million for the third ship, for a combined estimated cost of $2,619 million (i.e., about $2.6 billion). Within those figures, the shipbuilder’s portion of the total procurement cost is $746 million for the first ship, $544 million for the second ship, and $535 million for the third ship, for a combined estimated shipbuilder’s cost of $1,825 million (i.e., about $1.8 billion). On April 23, 2019, the Coast Guard-Navy Integrated Program Office for the PSC program awarded a $745.9 million fixed-price, incentive-firm contract for the detail design and construction (DD&C) of the first PSC to VT Halter Marine of Pascagoula, MS, a shipyard owned by Singapore Technologies (ST) Engineering. VT Halter was the leader of one of three industry teams that competed for the DD&C contract. The first PSC is scheduled to begin construction in 2021 and be delivered in 2024, though the DD&C contract includes financial incentives for earlier delivery. The DD&C contract includes options for building the second and third PSCs. If these options are exercised, the total value of the contract would increase to $1,942.8 million (i.e., about $1.9 billion). The figures of $745.9 million and $1,942.8 million cover only the shipbuilder’s costs; they do not include the cost of government-furnished equipment (GFE), which is equipment for the ships that the government purchases and then provides to the shipbuilder for incorporation into the ship, or government program-management costs. When GFE and government programmanagement costs are included, the total estimated procurement cost of the first PSC is between $925 million and $940 million, and the total estimated procurement cost of the three-ship PSC program is about $2.95 billion. The operational U.S. polar icebreaking fleet currently consists of one heavy polar icebreaker, Polar Star, and one medium polar icebreaker, Healy. In addition to Polar Star, the Coast Guard has a second heavy polar icebreaker, Polar Sea. Polar Sea, however, suffered an engine casualty in June 2010 and has been nonoperational since then. Polar Star and Polar Sea entered service in 1976 and 1978, respectively, and are now well beyond their originally intended 30-year service lives. The Coast Guard plans to extend the service life of Polar Star until the delivery of at least the second PSC. The Coast Guard is using Polar Sea as a source of spare parts for keeping Polar Star operational. Congressional Research Service Coast Guard Polar Security Cutter (Polar Icebreaker) Program Contents Introduction ..................................................................................................................................... 1 Background ..................................................................................................................................... 1 Missions of U.S. Polar Icebreakers ........................................................................................... 1 Statutory Duties and Missions ............................................................................................ 1 Multiple Missions (Not Just Icebreaking) ........................................................................... 2 Polar (Not Just Arctic) Operations ...................................................................................... 2 Current U.S. Polar Icebreakers.................................................................................................. 3 Required Numbers of U.S. Polar Icebreakers ........................................................................... 4 Coast Guard Polar Security Cutter (PSC) Program .................................................................. 4 Overview ............................................................................................................................. 4 Program Name .................................................................................................................... 5 Coast Guard-Navy Integrated Program Office (IPO) ......................................................... 5 Parent Design Approach ..................................................................................................... 5 Program Schedule ............................................................................................................... 5 Procurement Cost ................................................................................................................ 5 Program Funding ................................................................................................................ 5 Contract Award ................................................................................................................... 6 Ship Design ......................................................................................................................... 7 Home Port .......................................................................................................................... 11 FY2021 Funding Request .................................................................................................. 11 Service Life Extension for Polar Star ..................................................................................... 12 Issues for Congress ........................................................................................................................ 12 Potential Impact of COVID-19 (Coronavirus) Situation ........................................................ 12 FY2021 Funding ..................................................................................................................... 12 Contract with Options vs. Block Buy Contract ....................................................................... 13 Funding Coast Guard Polar Icebreakers through Navy’s Shipbuilding Account .................... 14 Technical, Schedule, and Cost Risk for PSC Program ............................................................ 16 Parent Design and PSC Design ......................................................................................... 16 February 2020 GAO Testimony ........................................................................................ 17 Common Design for Heavy and Medium Polar Icebreakers .................................................. 18 Legislative Activity for FY2021 .................................................................................................... 20 Summary of Appropriation Action on FY2021 Funding Request ........................................... 20 Figures Figure 1. Rendering of VT Halter Design for PSC ........................................................................ 7 Figure 2. Rendering of VT Halter Design for PSC ........................................................................ 8 Figure 3. Rendering of VT Halter Design for PSC ........................................................................ 8 Figure 4. Rendering of VT Halter Design for PSC ........................................................................ 9 Figure 5. Rendering of SDC Concept Design for Polarstern II .................................................... 10 Figure A-1. Polar Star and Polar Sea ........................................................................................... 22 Figure A-2. Polar Sea .................................................................................................................... 23 Congressional Research Service Coast Guard Polar Security Cutter (Polar Icebreaker) Program Figure A-3. Healy .......................................................................................................................... 24 Figure A-4. Nathaniel B. Palmer ................................................................................................... 25 Figure A-5. Laurence M. Gould .................................................................................................... 26 Figure A-6. Sikuliaq ...................................................................................................................... 27 Figure E-1. Great Lakes Icebreaker Mackinaw ............................................................................. 58 Tables Table 1. Estimated PSC Procurement Costs .................................................................................... 6 Table 2. Summary of Congressional Appropriations Action on FY2021 Procurement Funding Request......................................................................................................................... 21 Table A-1. Coast Guard and NSF Polar Ships ............................................................................... 28 Table B-1. Major Icebreakers of the World as of May 1, 2017 ..................................................... 34 Table C-1. Funding for PSC Program in FY2013-FY2021 Budget Submissions ......................... 48 Table C-2. Funding in Procurement, Construction, and Improvements (PC&I) Account ............. 49 Appendixes Appendix A. Current U.S. Polar Icebreakers and Polar Research Ships ....................................... 22 Appendix B. Required Numbers of U.S. Polar Icebreakers .......................................................... 29 Appendix C. PSC Program Funding ............................................................................................. 48 Appendix D. Funding Level in PC&I Account ............................................................................. 54 Appendix E. Great Lakes Icebreakers ........................................................................................... 58 Contacts Author Information........................................................................................................................ 62 Congressional Research Service Coast Guard Polar Security Cutter (Polar Icebreaker) Program Introduction This report provides background information and issues for Congress on the Polar Security Cutter (PSC) program—the Coast Guard’s program for acquiring new PSCs (i.e., heavy polar icebreakers). The PSC program has received a total of $1,169.6 million (i.e., about $1.2 billion) in procurement funding through FY2020, including $135 million in FY2020, which was $100 million more than the $35 million that the Coast Guard had requested for FY2020. With the funding it has received through FY2020, the first PSC is now fully funded and the second PSC has received initial funding. The Coast Guard’s proposed FY2021 budget requests $555 million in procurement funding for the PSC program. It also proposes a rescission of $70 million in FY2020 funding that Congress had provided for the procurement of long lead time materials (LLTM) for a 12th National Security Cutter (NSC), with the intent of reprogramming that funding to the PSC program. The Coast Guard states that its proposed FY2021 budget, if approved by Congress, would fully fund the second PSC. The issue for Congress is whether to approve, reject, or modify the Administration’s FY2021 procurement funding request for the PSC program and the proposed rescission of FY2020 NSC funding, and, more generally, whether to approve, reject, or modify the Coast Guard’s overall plan for procuring new polar icebreakers. Congress’s decisions on this issue could affect Coast Guard funding requirements, the Coast Guard’s ability to perform its polar missions, and the U.S. shipbuilding industrial base. For a brief discussion of the Coast Guard’s Great Lakes icebreakers, see Appendix E. A separate CRS report covers acquisition of general-purpose cutters (including NSCs) for the Coast Guard.1 Another CRS report provides an overview of various issues relating to the Arctic.2 Background Missions of U.S. Polar Icebreakers Statutory Duties and Missions The permanent statute that sets forth the Coast Guard’s primary duties—14 U.S.C. 102—states that among other things, the Coast Guard shall (emphasis added) “develop, establish, maintain, and operate, with due regard to the requirements of national defense, aids to maritime navigation, icebreaking facilities, and rescue facilities for the promotion of safety on, under, and over the high seas and waters subject to the jurisdiction of the United States,” and “pursuant to international agreements, develop, establish, maintain, and operate icebreaking facilities on, under, and over waters other than the high seas and waters subject to the jurisdiction of the United States.... ”3 1 CRS Report R42567, Coast Guard Cutter Procurement: Background and Issues for Congress, by Ronald O'Rourke. CRS Report R41153, Changes in the Arctic: Background and Issues for Congress, coordinated by Ronald O'Rourke. 3 14 U.S.C. 102(4) and 102(5), respectively. This statute was previously 14 U.S.C. 2; it was renumbered as 14 U.S.C. 102 by Section 103 of the Frank LoBiondo Coast Guard Authorization Act of 2018 (S. 140/P.L. 115-282 of December 4, 2018). (Title I of P.L. 115-282, consisting of Sections 101-124, specified a general reorganization of Title 14.) 2 Congressional Research Service 1 Coast Guard Polar Security Cutter (Polar Icebreaker) Program In addition, Section 888(a) of the Homeland Security Act of 2002 (H.R. 5005/P.L. 107-296 of November 25, 2002)—the law that established the Department of Homeland Security (DHS) and transferred the Coast Guard from the Department of Transportation to DHS—sets forth 11 specific missions for the Coast Guard (often referred to as the Coast Guard’s 11 statutory missions), including the mission of “ice operations.”4 Multiple Missions (Not Just Icebreaking) The Coast Guard’s polar icebreakers do not simply break ice—they are multimission cutters5 that conduct a variety of other operations that are conducted in lower-latitude waters by the Coast Guard’s general-purpose cutters. U.S. polar ice operations conducted in large part by the Coast Guard’s polar icebreakers support 9 of the Coast Guard’s 11 statutory missions.6 The roles of U.S. polar icebreakers can be summarized as follows:      conducting and supporting scientific research in the Arctic and Antarctic; defending U.S. sovereignty in the Arctic by helping to maintain a U.S. presence in U.S. territorial waters in the region; defending other U.S. interests in polar regions, including economic interests in waters that are within the U.S. exclusive economic zone (EEZ) north of Alaska; monitoring sea traffic in the Arctic, including ships bound for the United States; and conducting other typical Coast Guard missions (such as search and rescue, law enforcement, and protection of marine resources) in Arctic waters, including U.S. territorial waters north of Alaska.7 Polar (Not Just Arctic) Operations The Coast Guard’s large icebreakers are called polar icebreakers rather than Arctic icebreakers because they perform missions in both the Arctic and Antarctic. Operations to support National Science Foundation (NSF) research activities in both polar regions account for a significant portion of U.S. polar icebreaker operations. Supporting NSF research in the Antarctic focuses on performing an annual mission, called Operation Deep Freeze (ODF), to break through Antarctic sea ice so as to reach and resupply McMurdo Station, the large U.S. Antarctic research station located on the shore of McMurdo Sound, near the Ross Ice Shelf. The Coast Guard states that Polar Star, the Coast Guard’s only currently operational heavy polar icebreaker, “spends the [northern hemisphere] winter [i.e., the southern hemisphere summer] breaking ice near Antarctica in order to refuel and resupply 4 The 11 missions set forth in Section 888(a) are marine safety; search and rescue; aids to navigation; living marine resources (fisheries law enforcement); marine environmental protection; ice operations; ports, waterways and coastal security; drug interdiction; migrant interdiction; defense readiness; other law enforcement. 5 Cutters are commissioned Coast Guard vessels greater than 65 feet in length. 6 For a list of the 11 missions, see footnote 4. The two statutory missions not supported by polar ice operations are illegal drug interdiction and undocumented migrant interdiction. (Department of Homeland Security, Polar Icebreaking Recapitalization Project Mission Need Statement, Version 1.0, approved by DHS June 28, 2013, p. 10.) 7 This passage, beginning with “The roles of ... ,” originated in an earlier iteration of this CRS report and was later transferred by the Government Accountability Office (GAO) with minor changes to Government Accountability Office, Coast Guard[:]Efforts to Identify Arctic Requirements Are Ongoing, but More Communication about Agency Planning Efforts Would Be Beneficial, GAO-10-870, September 2010, p. 53. Congressional Research Service 2 Coast Guard Polar Security Cutter (Polar Icebreaker) Program McMurdo Station. When the mission is complete, the Polar Star returns to dry dock [in Seattle] in order to complete critical maintenance and prepare it for the next ODF mission. Once out of dry dock, it’s back to Antarctica, and the cycle repeats itself.”8 In terms of the maximum thickness of the ice to be broken, the annual McMurdo resupply mission generally poses the greatest icebreaking challenge for U.S. polar icebreakers, though Arctic ice can frequently pose its own significant icebreaking challenges for U.S. polar icebreakers. The Coast Guard’s medium polar icebreaker, Healy, spends most of its operational time in the Arctic supporting NSF research activities and performing other operations. Although polar ice is diminishing due to climate change, observers generally expect that this development will not eliminate the need for U.S. polar icebreakers, and in some respects might increase mission demands for them. Even with the diminishment of polar ice, there are still significant ice-covered areas in the polar regions, and diminishment of polar ice could lead in coming years to increased commercial ship, cruise ship, and naval surface ship operations, as well as increased exploration for oil and other resources, in the Arctic—activities that could require increased levels of support from polar icebreakers, particularly since waters described as “ice free” can actually still have some amount of ice.9 Changing ice conditions in Antarctic waters have made the McMurdo resupply mission more challenging since 2000.10 The Coast Guard’s Arctic strategic outlook document, released in April 2019, states In order to prosecute its missions in the Arctic, the Coast Guard must fully understand and operate freely in this vast and unforgiving environment. Effective capability requires sufficient heavy icebreaking vessels, reliable high-latitude communications, and comprehensive Maritime Domain Awareness. In order to respond to crises in the Arctic, our Nation must also muster adequate personnel, aviation, and logistics resources in the region. The Coast Guard is the sole provider and operator of the U.S. polar capable fleet but currently does not have the capability or capacity to assure access in the high latitudes. Closing the gap requires persistent investment in capabilities and capacity for polar operations, including the Polar Security Cutter. 11 Current U.S. Polar Icebreakers The operational U.S. polar icebreaking fleet currently consists of one heavy polar icebreaker, Polar Star, and one medium polar icebreaker, Healy. In addition to Polar Star, the Coast Guard has a second heavy polar icebreaker, Polar Sea. Polar Sea, however, suffered an engine casualty in June 2010 and has been nonoperational since then. Polar Star and Polar Sea entered service in 1976 and 1978, respectively, and are now well beyond their originally intended 30-year service lives. The Coast Guard in recent years has invested millions of dollars to overhaul, repair, and extend the service life of Polar Star, but as a result of its advancing age, the ship’s material condition has nevertheless become increasingly fragile, if not precarious. During its annual deployments to McMurdo Station in Antarctica, NyxoLyno Cangemi, “Coast Guard Icebreaker Crew Completes Second Arctic Mission; U.S. Interests in Arctic Domain Depends [sic] on Fleet Recapitalization,” DVIDS (Defense Visual Information Distribution System), October 19, 2018. 9 For more on changes in the Arctic due to diminishment of Arctic ice, see CRS Report R41153, Changes in the Arctic: Background and Issues for Congress, coordinated by Ronald O'Rourke. 10 National Research Council, Polar Icebreakers in a Changing World, An Assessment of U.S. Needs, Washington, 2007, pp. 6-7, 14, 63. 11 United States Coast Guard, Arctic Strategic Outlook, April 2019, p. 6. 8 Congressional Research Service 3 Coast Guard Polar Security Cutter (Polar Icebreaker) Program shipboard equipment frequently breaks, and shipboard fires sometimes occur.12 Replacements for many of the ship’s components are no longer commercially available. To help keep Polar Star operational, the Coast Guard is using Polar Sea as a source of replacement parts. For additional background information on current U.S. polar icebreakers and polar research ships, see Appendix A. Required Numbers of U.S. Polar Icebreakers Coast Guard officials state that the service in coming years will need six PSCs, including three capable of breaking heavy polar ice, to perform its various polar missions. The Coast Guard testified in February 2020, for example, that The 2010 High Latitude Mission Analysis Report (HL MAR) identified the need for six new polar icebreakers (at least three of which must be heavy) under the assumption that, in the future, the Coast Guard would be required to perform nine of its eleven statutory missions year-round in the Arctic, and meet all icebreaking needs in support of the United States Antarctic Program. In 2017, the Coast Guard’s Center for Arctic Study and Policy completed an addendum to the HL MAR. The objectives were to provide a broad overview of changes in the polar regions over the last seven years and to provide specific information for use in determining potential impacts on mission areas in the polar regions. This addendum provides confidence in the original findings and encourages the sustained reliance on its initial recommendations on the Nation’s need for six icebreakers, three of which must be heavy icebreakers.13 On June 9, 2020, President Trump issued a memorandum directing DHS, in coordination with the Department of Defense (DOD), the Department of Commerce, the Department of State, and the Office of Management and Budget (OMB), to review required numbers of polar security cutters, U.S. and international basing options for polar security cutters, and options for bridging the gap in polar vessels until new polar security cutters are delivered, and to report back to President Trump within 60 days (i.e., by August 8, 2020) on the results of the review. For additional background information on required numbers of U.S. polar icebreakers, including the text of the above-mentioned June 9, 2020, memorandum, see Appendix B. Coast Guard Polar Security Cutter (PSC) Program Overview The PSC program was initiated in the Coast Guard’s FY2013 budget submission, and envisages the acquisition of three new PSCs (i.e., heavy polar icebreakers), to be followed years from now by the acquisition of up to three new medium polar icebreakers. The Coast Guard wants to begin construction of the first new heavy polar icebreaker in 2021 and have it enter service in 2024. See, for example, Richard Read, “Meet the Neglected 43-Year-Old Stepchild of the U.S. Military-Industrial Complex,” Los Angeles Times, August 2, 2019; Melody Schreiber, “The Only Working US Heavy Icebreaker Catches Fire Returning from Antarctica,” Arctic Today, March 2, 2019; Calvin Biesecker, “Fire Breaks Out On Coast Guard’s Aging, and Only, Heavy Icebreaker,” Defense Daily, March 1, 2019. 13 Testimony of Admiral Charles W. Ray, Coast Guard Vice Commandant, on “Arctic Security Issues,” before the House Homeland Security Subcommittee on Transportation & Maritime Security, February 5, 2020, p. 9. 12 Congressional Research Service 4 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Program Name The PSC program was previously known as the polar icebreaker (PIB) program. Changing the program’s name to the PSC program is intended to call attention to the fact that the Coast Guard’s polar icebreakers perform a variety of missions relating to national security, not just icebreaking.14 Although it is now called the PSC program, observers as a matter of convenience might refer to it as the polar icebreaker program. Coast Guard-Navy Integrated Program Office (IPO) The PSC program is managed by a Coast Guard-Navy Integrated Program Office (IPO). A key aim in establishing the IPO was to permit the Navy to share its ship-procurement best practices with the Coast Guard so as to help the Coast Guard reduce the time and cost needed to design and procure the PSCs. Parent Design Approach The PSC program is using the parent design approach, meaning that the design of the PSC is to be based on an existing icebreaker design. A key aim in using the parent design approach is to reduce cost, schedule, and technical risk in the PSC program. Program Schedule The PSC program’s schedule calls for delivering the three PSCs at 12-month intervals, at the end of the third quarters of FY2024, FY2025, and FY2026, respectively. Procurement Cost As shown in Table 1, the Coast Guard estimates the total procurement costs of the three heavy polar icebreakers as $1,039 million (i.e., about $1.0 billion) for the first ship, $792 million for the second ship, and $788 million for the third ship, for a combined estimated cost of $2,619 million (i.e., about $2.6 billion). As also shown in Table 1, within those figures, the shipbuilder’s portion of the total procurement cost is $746 million for the first ship, $544 million for the second ship, and $535 million for the third ship, for a combined estimated shipbuilder’s cost of $1,825 million (i.e., about $1.8 billion). The shipbuilder’s contract-award cost for the first ship is $745.9 million, with options for the second and third ships that, if exercised, would increase the total value of the contract to $1,942.8 million (i.e., about $1.9 billion). Program Funding The PSC program has received a total of $1,169.6 million (i.e., about $1.2 billion) in procurement funding through FY2020. In FY2020, Congress provided $135 million for the program, which was $100 million more than the $35 million that the Coast Guard had requested. The figure of $1,169.6 million includes $300 million that was provided through the Navy’s shipbuilding account in FY2017 and FY2018 ($150 million each year). With the funding it has received through FY2020, the first PSC is now fully funded and the second PSC has received initial funding. See, for example, Ben Werner and Sam LaGrone, “Coast Guard Renames New Icebreaker Program ‘Polar Security Cutter,’” USNI News, September 27, 2018. See also Sydney J. Freedberg Jr., “With Funding In Peril, Coast Guard Pushes Icebreaker As ‘Polar Security Cutter,’” Breaking Defense, October 29, 2018. 14 Congressional Research Service 5 Coast Guard Polar Security Cutter (Polar Icebreaker) Program For additional background information on funding for the PSC program, see Appendix C. Table 1. Estimated PSC Procurement Costs In millions of then-year dollars Cost element 1st PSC 2nd PSC 3rd PSC Total Target contract price 746 544 535 1,825 Program costs (including GFE) 213 165 168 546 Post-delivery costs 45 47 48 140 Costs for Navy-Type, Navy-Owned (NTNO) equipment 35 36 37 108 1,039 792 788 2,619 TOTAL Source: U.S. Navy information paper on PSC program, undated, received from Navy Office of Legislative Affairs, June 14, 2019. Notes: Target contract price includes detail design, construction, and long lead-time materials (LLTM), and does not reflect potential costs rising to the contract ceiling price. GFE is government-furnished equipment— equipment that the government procures and then provides to the shipbuilder for installation on the ship. NTNO equipment is GFE that the Navy provides—such as combat weapons systems, sensors and communications equipment and supplies—for meeting Coast Guard/Navy naval operational capabilities wartime readiness requirements. (For additional discussion, see Coast Guard Commandant Instruction (COMDTINST) 7100.2G, May 16, 2013, accessed June 24, 2019, at https://media.defense.gov/2017/Mar/15/2001716816/-1/-1/0/ CI_7100_2G.PDF.) The Navy information paper states that program costs, post-delivery costs, and NTNO costs were taken from the Program Life Cycle Cost Estimate (PLCCE) and were in the process of being updated based on the contract award, the contractor’s schedule, and refined cost estimates. Contract Award On April 23, 2019, the Coast Guard-Navy Integrated Program Office for the PSC program awarded a $745.9 million fixed-price, incentive-firm contract for the detail design and construction (DD&C) of the first PSC to VT Halter Marine of Pascagoula, MS, a shipyard owned by Singapore Technologies (ST) Engineering. VT Halter was the leader of one of three industry teams that competed for the DD&C contract; the other two bidders reportedly were Bollinger Shipyards of Lockport, Louisiana, and a partnership between Philly Shipyard of Philadelphia and Fincantieri/Marinette Marine, of Marinette, WI.15 The first PSC is scheduled to begin construction in 2021 and be delivered in 2024, though the DD&C contract includes financial incentives for earlier delivery. The DD&C contract includes options for building the second and third PSCs. If these options are exercised, the total value of the contract would increase to $1,942.8 million (i.e., about $1.9 billion).16 The figures of $745.9 million and $1,942.8 million cover the shipbuilder’s costs; they do not include the cost of government-furnished equipment (GFE), which is equipment for the ships that the government purchases and then provides to the shipbuilder for incorporation into the ship, or government program-management costs. “Mississippi Shipyard Gets $746M Contract for Icebreaker,” Associated Press, April 23, 2019. See Naval Sea Systems Command, “Polar Security Cutter Contract Awarded to Recapitalize Nation’s Arctic Capabilities,” April 23, 2019; Department of Defense, “Contracts for April 23, 2019” (Release No. CR-076-19); Sam LaGrone, “VT Halter Marine to Build New Coast Guard Icebreaker,” USNI News, April 23, 2019; Maria Armental, “U.S. Orders First heavy Icebreaking Vessel in Decades, as Rivals Expand Arctic Presence,” Wall Street Journal, April 23, 2019; “Mississippi Shipyard Gets $746M Contract for Icebreaker,” Associated Press, April 23, 2019. 15 16 Congressional Research Service 6 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Ship Design Figure 1, Figure 2, Figure 3, and Figure 4 show renderings of VT Halter’s design for the PSC. An April 25, 2019, press report states that “the Coast Guard and Navy said VT Halter Marine’s winning design for the new Polar Security Cutter (PSC) ‘meets or exceeds all threshold requirements’ in the ship specification” for the PSC program.17 Figure 1. Rendering of VT Halter Design for PSC Source: Illustration accompanying Sam LaGrone, “UPDATED: VT Halter Marine to Build New Coast Guard Icebreaker,” USNI News, April 23, 2019, updated April 24, 2019. The caption to the illustration states “An artist’s rendering of VT Halter Marine’s winning bid for the U.S. Coast Guard Polar Security Cutter. VT Halter Marine image used with permission.” A May 7, 2019, press release from VT Halter about its design for the PSC (which VT Halter updated on May 29 to provide a corrected figure for the design’s full load displacement) stated the following: VT Halter Marine is teamed with Technology Associates, Inc. [TAI] as the ship designer and, for over two years, has participated in the U.S. Coast Guard’s Heavy Polar Icebreaker Industry Study. The ship design is an evolution from the mature ”Polar Stern II” [German icebreaker] currently in design and construction; the team has worked rigorously to demonstrate its maturity and reliability. During the study, TAI incrementally adjusted the design and conducted a series of five ship model tank tests to optimize the design. The vessels are 460 feet in length with a beam of 88 feet overall, a full load displacement of approximately 22,900 long tons at delivery. The propulsion will be diesel electric at over 45,200 horse power and readily capable of breaking ice between six to eight feet thick. The vessel will accommodate 186 personnel comfortably for an extended endurance of 90 days. In addition to TAI, VT Halter Marine has teamed with ABB/Trident Marine for its Azipod propulsion system,18 Raytheon for command and control systems integration, Caterpillar Rich Abott, “Polar Icebreaker Winner Meets Threshold Requirements, Has Incentives For Early Delivery,” Defense Daily, April 25, 2019. 18 ABB is ASEA Brown Boveri, a multinational corporation headquartered in Zurich, Switzerland, that is, among other 17 Congressional Research Service 7 Coast Guard Polar Security Cutter (Polar Icebreaker) Program for the main engines, Jamestown Metal Marine for joiner package, and Bronswerk for the HVAC system. The program is scheduled to bring an additional 900 skilled craftsman and staff to the Mississippi-based shipyard.19 Figure 2. Rendering of VT Halter Design for PSC Source: Illustration posted by Robert A. Socha, Senior Vice President, VT Halter Marine, accessed May 6, 2019, at https://www.linkedin.com/feed/update/urn:li:activity:6526621529113976832. Figure 3. Rendering of VT Halter Design for PSC Source: Technology Associates, Inc. (cropped version of rendering posted at http://www.navalarchitects.us/pictures.html, accessed June 10, 2020). A similar image was included in VT Halter press release, “VT Halter Marine Awarded the USCG Polar Security Cutter,” May 7, 2019, accessed May 8, 2019, at http://www.vthm.com/public/files/20190507.pdf. things, a leading maker of electric-drive propulsion systems for ships. (ASEA is an acronym for Allmänna Svenska Elektriska Aktiebolaget [i.e., General Swedish Electrical Limited Company], which merged with Brown, Boveri & Cie [BBC] in 1988 to create ABB.) Azipod is ABB’s term for its azimuthing (i.e., swiveling) podded propulsors. 19 VT Halter press release, “VT Halter Marine Awarded the USCG Polar Security Cutter,” May 7, 2019, updated May 29, accessed June 12, 2019, at http://vthm.com/wp-content/uploads/2019/05/Press-Release_USCG-PSC_SingaporeExchange-FINAL_updatedMay29.pdf. The original (May 7) version of the press release stated that the design’s full load displacement at delivery would be approximately 33,000 tons. Congressional Research Service 8 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Figure 4. Rendering of VT Halter Design for PSC Source: Photograph accompanying Connie Lee, “New Coast Guard Icebreaker Remains on Tight Schedule,” National Defense, May 21, 2020. The article credits the photograph to Technology Associated, Inc. The German icebreaker design referred to in VT Halter’s press release, Polar Stern II (also spelled Polarstern II) (Figure 5),20 was to be built as the replacement for Polarstern, Germany’s current polar research and supply icebreaker. On February 14, 2020, however, the Alfred Wegener Institute, Helmholtz Centre for Polar and Marine Research, announced that “the [German] Federal Ministry of Education and Research (BMBF) today cancelled the Europe-wide call for tenders for the procurement of a new polar research vessel, Polarstern II, for legal reasons.”21 A May 9, 2019, press report states that Polarstern II was designed by Germany’s Ship Design & Consult (SDC), a firm based in Hamburg, Germany.22 SDC states that its concept design for Polarstern II has a length of 133 meters (about 436.4 feet) long, a beam of 27 meters (about 88.6 feet), and a draft of 10.5 meters (about 34.4 feet), but does not provide the design’s displacement.23 A briefing on a preliminary version of the ship’s design stated that the design at that point was somewhat larger, with a length of 145 meters (about 476 feet), a beam of 27.3 meters (about 89.6 feet), a draft of about 11 meters (about 36.1 feet), and a displacement (including payload) of about 26,000 tons.24 These figures suggest that SDC’s somewhat smaller Polarstern is the German word for Polar Star—coincidentally, the same name as the U.S. Coast Guard’s operational heavy polar icebreaker. 21 Alfred Wegener Institute, Helmholtz Centre for Polar and Marine Research, “Call for tender procedure for the construction of a successor to the icebreaker Polarstern has been cancelled.,” February 14, 2020, accessed March 12, 2020, at: https://www.awi.de/en/about-us/service/press/press-release/call-for-tender-procedure-for-the-construction-ofa-successor-to-the-icebreaker-polarstern-has-been.html . 22 Calvin Biesecker, “Long-Lead Funding In FY ‘20 For Second Polar Security Cutter Would Help With Planning, Shipbuilder Says,” Defense Daily, May 9, 2019. 23 SDC Ship Design & Consult GmbH, design SDC2187, 133m Research Vessel, accessed May 9, 2019, at http://www.shipdesign.de/html/index.php?navi=3&navi2=80&navi3=115. 24 Briefing entitled “Shipboard Polar Research, 32 Years Polarstern and the requirement for Polarstern II,” accessed 20 Congressional Research Service 9 Coast Guard Polar Security Cutter (Polar Icebreaker) Program concept design for Polarstern II might have a displacement (including payload) of something less than 26,000 tons, and perhaps closer to 23,000 tons. Figure 5. Rendering of SDC Concept Design for Polarstern II Source: SDC Ship Design & Consult GmbH, design SDC2187, 133m Research Vessel, accessed May 9, 2019, at http://www.shipdesign.de/html/index.php?navi=3&navi2=80&navi3=115. The image is enlarged at http://www.shipdesign.de/html/detail.php?id=396. The above-mentioned May 9, 2019, press report states that VT Halter’s teammates on the PSC include ship designer Technology Associates, Inc. (TAI), which has been involved in the design for over two years and has made “a lot of modifications” in a number of areas to meet Coast Guard requirements, [Ronald Baczkowski, president and CEO of VT Halter Marine] said. The team went through six design spirals to refine the design and the major modifications include changes in the hull form to enhance the ship’s icebreaking capabilities and keep the ice clear from the propulsors and sensors, habitability improvements for comfort particularly in open water, easier access to different areas of the ship, and maintenance and endurance capabilities…. Raytheon [RTN] is the integrator for C5I capabilities 25 on the ship and the main engines will be supplied by Caterpillar [CAT]. Switzerland-based ABB and Netherlands-based May 8, 2019, at http://www.ervo-group.eu/np4/np4/%7B$clientServletPath%7D/?newsId=43&fileName= Pr_sentation_Markterkundung_09.09.14_fin.pdf. The briefing is undated but includes a statement on one of its slides that refers in the past tense to an event that took place in January 2016. 25 C5I stands for command, control, communications, computers, collaboration, and intelligence. Congressional Research Service 10 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Trident are supplying the Azipod propulsion system, Florida-based Jamestown Metal Marine is supplying the joiner package, and Netherlands-based Bronswerk the heating, ventilation and cooling system.26 VT Halter’s 22,900-ton design for the PSC is considerably larger than the Coast Guard’s current polar icebreakers. As shown in tons Table A-1, the Coast Guard’s largest polar icebreaker, Healy, is 420 feet long and has a full load displacement of 16,000 tons. VT Halter’s 460-foot design for the PSC is 40 feet longer than Healy, and its 22,900-ton displacement is about 43% greater than Healy’s. The horsepower generated by the propulsion plant in VT Halter’s design—more than 45,200, according to the earlier-quoted May 7, 2019 press release from VT Halter—is roughly onequarter less than the 60,000 shaft horsepower of the propulsion plant in the Coast Guard’s heavy polar icebreaker, Polar Star. A shown in Figure 1 and Figure 2, however, VT Halter’s design includes a centerline shafted propeller flanked by two azimuthing (i.e., swiveling) podded propulsors—an arrangement that, along with other modern icebreaker hull design features, is expected to give VT Halter’s design a capability for breaking ice comparable to that of Polar Star. A May 8, 2019, press report states the following: “We picked the most modern icebreaker that was on the market, soon to be productionlevel design that roughly met the Coast Guard’s requirements, and we took it and modified it,” Baczkowski said. “It has a contoured shape. The shape of the hull does the icebreaking. Instead of being a mass breaking ice, this actually slices the ice. The shape of the hull pushed the broken ice aside, so it doesn’t interfere with your propulsion systems, with your instrumentation that’s on the other side of the ship.” The design of the cutter is optimized for seakeeping to support the long voyage from its homeport in Washington state to as far away as the Antarctic, he said. “It’s an optimum design between icebreaking and seakeeping.” “With the propulsors, with one fixed and two steerable, we were able to optimize the seakeeping capability so when you’re going on long transits from Washington to Antarctica the crew is not beat to a pulp or heavily fatigued because of the stability characteristics in open water.”27 Home Port On June 17, 2019, the Coast Guard announced that it intends to homeport its PSCs at Seattle, WA, where the Coast Guard’s current polar icebreakers are homeported.28 FY2021 Funding Request The Coast Guard’s proposed FY2021 budget requests $555 million in procurement funding for the PSC program. It also proposes a rescission of $70 million in FY2020 funding that Congress had provided for the procurement of long lead time materials (LLTM) for a 12th National Security Cutter (NSC), with the intent of reprogramming that funding to the PSC program. The Coast Calvin Biesecker, “Long-Lead Funding In FY ‘20 For Second Polar Security Cutter Would Help With Planning, Shipbuilder Says,” Defense Daily, May 9, 2019. Abbreviations for firm names in brackets as in original. 27 Sam LaGrone, “VT Halter Marine Details Coast Guard Icebreaker Bid,” USNI News, May 8, 2019. 28 See, for example, Ben Werner, “Coast Guard Polar Security Cutter Will Be Homeported in Seattle,” USNI News, June 17, 2019; Navy Times Staff, “Coast Guard Picks Homeport for New Icebreaker Fleet,” Navy Times, June 17, 2019. 26 Congressional Research Service 11 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Guard states that its proposed FY2021 budget, if approved by Congress, would fully fund the second PSC. Service Life Extension for Polar Star The Coast Guard plans to extend the service life of Polar Star until the delivery of at least the second PSC. In February 2020, for example, the Coast Guard testified that The Coast Guard also understands that we must maintain our existing heavy and medium icebreaking capability while proceeding with recapitalization. Construction on the first PSC is planned to begin in 2021 with delivery planned for 2024; however, the contract includes financial incentives for earlier delivery. Maintenance of POLAR STAR will be critical to sustaining this capability until the new PSCs are delivered. Robust planning efforts for a service life extension project on POLAR STAR are already underway and initial work for this project will begin in 2020, with phased industrial work occurring annually from 2021 through 2023. The end goal of this process will be to extend the vessel’s service life until delivery of at least the second new PSC.29 The Coast Guard estimates the cost of Polar Star’s service life extension work at $75 million. The work is being funded at a rate of $15 million per year; the $15 million requested in the FY2021 budget is the third of five planned annual funding increments. This funding is included in the vessels portion of the Coast Guard’s PC&I account, in a line item called “Polar Sustainment” that is separate from the line item for the PSC program. Issues for Congress Potential Impact of COVID-19 (Coronavirus) Situation One issue for Congress concerns the potential impact of the COVID-19 (coronavirus) situation on the execution of U.S. military shipbuilding programs, including the PSC program. For additional discussion of this issue, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O'Rourke. FY2021 Funding Another issue for Congress is whether to approve, reject, or modify the Coast Guard’s $555million FY2021 procurement funding request for the PSC program and the Coast Guard’s proposal in its FY2021 budget submission for a rescission of $70 million in FY2020 funding provided for the procurement of LLTM for a 12th NSC, with the intent of reprogramming that funding to the PSC program. In considering this issue, Congress may consider, among other things, whether the Coast Guard has accurately priced the work it is proposing to do in the PSC program in FY2021, and whether a 12th NSC is to be procured. (The question of whether a 12th NSC is to be procured is discussed further in the CRS report that tracks the Coast Guard’s general-purpose cutter procurement programs.30) Testimony of Admiral Charles W. Ray, Coast Guard Vice Commandant, on “Arctic Security Issues,” before the House Homeland Security Subcommittee on Transportation & Maritime Security, February 5, 2020, p. 9. 30 See CRS Report R42567, Coast Guard Cutter Procurement: Background and Issues for Congress, by Ronald O'Rourke. 29 Congressional Research Service 12 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Contract with Options vs. Block Buy Contract Another potential issue for Congress is whether to use a contract with options or a block buy contract to acquire at least some of the PSCs. As noted earlier, the DD&C contract that the Coast Guard awarded to VT Halter is a contract with options. Coast Guard and Navy officials, however, have expressed openness to the idea of using a block buy contract to acquire at least some of the ships (particularly the second and third PSCs), and requested information on the possibility of using block buy contracting as part of the request for proposals (RFP) for the PSC program that the Coast Guard released on March 2, 2018. Section 311 of the Frank LoBiondo Coast Guard Authorization Act of 2018 (S. 140/P.L. 115-282 of December 4, 2018) provides permanent authority for the Coast Guard to use block buy contracting with economic order quantity (EOQ) purchases (i.e., up-front batch purchases) of components in its major acquisition programs. The authority is now codified at 14 U.S.C. 1137. Although a contract with options covers multiple years, it operates more like a form of annual contracting, and it does not generate the kinds of savings that are possible with a block buy contract. Compared to a contract with options, a block buy contract would reduce the government’s flexibility regarding whether and when to acquire the second and third ships, and what design to build them to,31 and in return reduce the combined acquisition cost of the ships covered by the contract. The Navy has used block buy contracts to reduce procurement costs of Virginia-class attack submarines and (in more recent years) Littoral Combat Ships (LCSs) and John Lewis (TAO-205) class oilers.32 CRS estimates that compared to costs using a contract with options, using a block buy contract that included economic order quantity (EOQ) purchases (i.e., up-front batch purchases) of materials and components for three heavy polar icebreakers could reduce the combined acquisition cost of the three ships by upwards of 7%, which could equate to a savings of upwards of $150 million. A congressionally mandated July 2017 National Academies of Sciences, Engineering, and Medicine (NASEM) report on acquisition and operation of polar icebreakers states the following (emphasis as in original): 3. Recommendation: USCG should follow an acquisition strategy that includes block buy contracting with a fixed price incentive fee contract and take other measures to ensure best value for investment of public funds. Icebreaker design and construction costs can be clearly defined, and a fixed price incentive fee construction contract is the most reliable mechanism for controlling costs for a program 31 Stated more fully, from a congressional perspective, trade-offs in using block buy contracting include the following: —reduced congressional control over year-to-year spending, and tying the hands of future Congresses; —reduced flexibility for making changes in Coast Guard acquisition programs in response to unforeseen changes in strategic or budgetary circumstances (which can cause any needed funding reductions to fall more heavily on acquisition programs not covered by multiyear contracts); —a potential need to shift funding from later fiscal years to earlier fiscal years to fund economic order quantity (EOQ) purchases (i.e., up-front batch purchases) of components; —the risk of having to make penalty payments to shipbuilders if multiyear contracts need to be terminated due to unavailability of funds needed to the continue the contracts; and —the risk that materials and components purchased for ships to be acquired in future years might go to waste if those ships are not eventually acquired. 32 See CRS Report R41909, Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition: Background and Issues for Congress, by Ronald O'Rourke; CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress, by Ronald O'Rourke; and CRS Report R43546, Navy John Lewis (TAO-205) Class Oiler Shipbuilding Program: Background and Issues for Congress, by Ronald O'Rourke. Congressional Research Service 13 Coast Guard Polar Security Cutter (Polar Icebreaker) Program of this complexity. This technique is widely used by the U.S. Navy. To help ensure best long-term value, the criteria for evaluating shipyard proposals should incorporate explicitly defined lifecycle cost metrics.... A block buy authority for this program will need to contain specific language for economic order quantity purchases for materials, advanced design, and construction activities. A block buy contracting program with economic order quantity purchases enables series construction, motivates competitive bidding, and allows for volume purchase and for the timely acquisition of material with long lead times. It would enable continuous production, give the program the maximum benefit from the learning curve, and thus reduce labor hours on subsequent vessels.... If advantage is taken of learning and quantity discounts available through the recommended block buy contracting acquisition strategy, the average cost per heavy icebreaker is approximately $791 million, on the basis of the acquisition of four ships. 33 Funding Coast Guard Polar Icebreakers through Navy’s Shipbuilding Account Another potential issue for Congress is whether to continue providing at least some of the procurement funding for the PSC program through the Navy’s shipbuilding account, known formally as the Shipbuilding and Conversion Navy (SCN) appropriation account. As noted earlier, $300 million of the funding that the PSC program has received through FY2020 was provided through the SCN account in FY2017 and FY2018 ($150 million each year). A May 2018 Government Accountability Office (GAO) report states that agreements between DHS, the Coast Guard, and the Navy that were made following the establishment of the Coast Guard-Navy integrated program office for the PSC program “state that the program’s contracting actions could be funded by either USCG or Navy appropriations, and the source of the appropriations will award the contract.”34 Although providing funding for Coast Guard ships through the SCN account creates some complexity in tracking and executing funding for Coast Guard ship acquisition, and can raise a question as to whether that funding would otherwise go toward the acquisition of Navy ships, it has been used in the past for funding Coast Guard ships other than heavy polar icebreakers:  Healy was funded largely (about 89%) through the SCN account.35 33 National Academies of Sciences, Engineering, and Medicine, Division on Earth and Life Studies and Transportation Research Board, Acquisition and Operation of Polar Icebreakers: Fulfilling the Nation’s Needs, Letter Report, with cover letter dated July 11, 2017, pp. 14, 15. 34 Government Accountability Office, Homeland Security Acquisitions[:] Leveraging Programs’ Results Could Further DHS’s Progress to Improve Portfolio Management, GAO-18-339SP, May 2018, p. 86. 35 The somewhat complicated funding history for the ship is as follows: The Coast Guard’s proposed FY1990 budget requested $244 million for the acquisition of an icebreaker. The FY1990 DOD appropriations act (H.R. 3072/P.L. 101165 of November 21, 1989) provided $329 million for the ship in the SCN account. (See pages 77 and 78 of H.Rept. 101-345 of November 13, 1989.) This figure was then reduced by $4.2 million by a sequester carried out under the Balanced Budget And Emergency Deficit Control Act of 1985, also known as the Gramm-Rudman-Hollings Act (H.J.Res. 372/P.L. 99-177 of December 12, 1985). Another $50 million was rescinded by the Dire Emergency Supplemental Appropriations for Disaster Assistance, Food Stamps, Unemployment Compensation Administration, and Other Urgent Needs, and Transfers, and Reducing Funds Budgeted for Military Spending Act of 1990 (H.R. 4404/P.L. 101-302 of May 25, 1990). An additional $59 million for the ship was then appropriated in the FY1992 DOD Appropriations Act (H.R. 2521/P.L. 102-172 of November 26, 1991). Also, an additional $40.4 million in procurement funding for the ship was provided through a series of annual appropriations in the Coast Guard’s Acquisition, Construction, and Improvements (AC&I) account (as it was known prior to FY2019) from FY1988 through FY2001. Congressional Research Service 14 Coast Guard Polar Security Cutter (Polar Icebreaker) Program  Thirty-three of the Coast Guard’s 49 Island-class 110-foot patrol boats (i.e., about 67% of the boats) were procured under a Navy contract. The contract was for the construction of 21 of the boats, and included FY1990 SCN funds and prior year DOD nonexpiring funding. During the construction phase of the contract, the Navy exercised options under the contract for the construction 12 additional boats using FY1990 SCN funding.36 Subsections (a), (b), and (c) of Section 122 of the FY2018 National Defense Authorization Act (H.R. 2810/P.L. 115-91 of December 12, 2017) state the following: SEC. 122. Icebreaker vessel. (a) Authority to procure one polar-class heavy icebreaker.— (1) IN GENERAL.—There is authorized to be procured for the Coast Guard one polarclass heavy icebreaker vessel. (2) CONDITION FOR OUT-YEAR CONTRACT PAYMENTS.—A contract entered into under paragraph (1) shall provide that any obligation of the United States to make a payment under the contract for a fiscal year after fiscal year 2018 is subject to the availability of appropriations or funds for that purpose for such later fiscal year. (b) Limitation on availability of funds for procurement of icebreaker vessels.—None of the funds authorized to be appropriated by this Act or otherwise made available for the Department of Defense for any fiscal year that are unobligated as of the date of the enactment of this Act may be obligated or expended for the procurement of an icebreaker vessel other than the one polar-class heavy icebreaker vessel authorized to be procured under subsection (a)(1). (c) Contracting authority.— (1) COAST GUARD.—If funds are appropriated to the department in which the Coast Guard is operating to carry out subsection (a)(1), the head of contracting activity for the Coast Guard shall be responsible for contracting actions carried out using such funds. (2) NAVY.—If funds are appropriated to the Department of Defense to carry out subsection (a)(1), the head of contracting activity for the Navy, Naval Sea Systems Command shall be responsible for contracting actions carried out using such funds. (3) INTERAGENCY ACQUISITION.—Notwithstanding paragraphs (1) and (2), the head of contracting activity for the Coast Guard or head of contracting activity for the Navy, Naval Sea Systems Command (as the case may be) may authorize interagency acquisitions that are within the authority of such head of contracting activity. 37 Regarding Section 122, the conference report (H.Rept. 115-404 of November 9, 2017) on H.R. 2810/P.L. 115-91 states the following: Icebreaker vessel (sec. 122) The House bill contained provisions (sec. 122, 123, and 1012) that would authorize the Secretary of the Navy to act as a general agent for the Secretary of the Department in which the Coast Guard is operating and enter into a contract for icebreaker vessels; prohibit funds The resulting net funding for the ship was thus $374.2 million, of which $333.8 million, or 89.2%, was DOD funding, and $40.4 million, or 10.8%, was Coast Guard procurement funding. (Source: Undated Coast Guard information paper provided to CRS by Coast Guard legislative liaison office, March 3, 2016.) 36 Source: Navy information paper dated August 15, 2017, provided to CRS by Navy Office of Legislative Affairs on August 23, 2017. 37 Section 122 also includes a subsection (d) that requires a GAO report assessing the cost of, and schedule for, the procurement of new icebreakers. Congressional Research Service 15 Coast Guard Polar Security Cutter (Polar Icebreaker) Program for the Department of Defense from being used for the procurement of an icebreaker vessel; and amend section 2218 of title 10, United States Code, to authorize funds associated with the National Defense Sealift Fund for the construction of icebreaker vessels. The Senate amendment contained a similar provision (sec. 1048). The Senate recedes with an amendment that would authorize one polar-class heavy icebreaker vessel, prohibit funds for the Department of Defense from being used for the procurement of an icebreaker vessel other than this one polar-class heavy icebreaker vessel, clarify contracting authorities, and require a Comptroller General report. The conferees recognize the national importance of recapitalizing the U.S. icebreaker fleet and the extraordinary circumstances that necessitated use of Department of Defense funding to procure the first polar-class heavy icebreaker, as partially provided in the Department of Defense Appropriations Act for Fiscal Year 2017. Accordingly, the conferees support the authorization of this icebreaker in this Act. The conferees note the Undersecretary of Management in the Department of Homeland Security (DHS) serves as the Acquisition Decision Authority for the Polar Icebreaker Program and that this program is governed in accordance with DHS Acquisition Management Directive 102–01 and Instruction 102–01–001. The conferees believe maintaining clear lines of authority, responsibility, accountability, and resources with the Secretary and Acquisition Decision Authority of the department in which the U.S. Coast Guard is operating are essential to delivering icebreakers on cost and schedule. Accordingly, the conferees believe the Secretary of the Department of Homeland Security and the Undersecretary of Management in the DHS should be the officials provided with authorities and resources related to the Polar Icebreaker Program. Therefore, the conferees expect subsequent icebreakers to be authorized by the congressional committees with jurisdiction over the Coast Guard and funded using Coast Guard appropriations. (Pages 765-766) Technical, Schedule, and Cost Risk for PSC Program Another potential issue for Congress concerns technical, schedule, and cost risk in the PSC program. Parent Design and PSC Design One potential aspect of the issue of technical, schedule, and cost risk in the PSC program relates to the parent design for the PSC design. As mentioned earlier, a key aim in using the parent design approach is to reduce cost, schedule, and technical risk in the PSC program. As also mentioned earlier, VT Halter states that its winning design for the PSC “is an evolution from the mature ‘Polar Stern II’ [German icebreaker] currently in design and construction; the team has worked rigorously to demonstrate its maturity and reliability.” As also mentioned earlier, VT Halter and ship designer Technology Associates, Inc. reportedly made “a lot of modifications” and went through six design spirals to refine the PSC’s design. Potential oversight questions for Congress include the following:   To what degree was Polarstern II’s design developed at the time it was used as the parent design for developing the PSC design? How much of Polarstern II’s detail design and construction plan was completed at that time? How closely related is the PSC’s design to Polarstern II’s design? How many changes were made to Polarstern II’s design to develop the PSC design? What Congressional Research Service 16 Coast Guard Polar Security Cutter (Polar Icebreaker) Program were these changes, and what technical, schedule, and cost risks, if any, might arise from them? February 2020 GAO Testimony February 2020 GAO testimony on Coast Guard Arctic capabilities states: The Coast Guard Has Taken Steps to Address Technology, Design, Cost, and Schedule Risks for the Polar Security Cutters In September 2018, we found that the Coast Guard did not have a sound business case when it established the acquisition baselines for the Polar Security Cutter program in March 2018 due to risks in four key areas: technology, design, cost, and schedule. Our prior work has found that successful acquisition programs start with solid, executable business cases before setting program baselines and committing resources. A sound business case requires balance between the concept selected to satisfy operator requirements and the resources— design knowledge, technologies, funding, and time—needed to transform the concept into a product, which in this case is a ship with polar icebreaking capabilities. Without a sound business case, acquisition programs are at risk of breaching the cost, schedule, and performance baselines set when the program was initiated—in other words, experiencing cost growth, schedule delays, and reduced capabilities. To address the key risks we identified and help establish a sound business case for the Polar Security Cutter program, we made six recommendations to DHS, Coast Guard, and the Navy in our September 2018 report. The agencies concurred with all six recommendations and have taken steps to address some of the risks, as noted below. • Technology. The Coast Guard planned to use proven technologies for the program, but did not conduct a technology readiness assessment to determine the maturity of key technologies prior to setting baselines. As a result, the Coast Guard did not have full insight into whether these technologies were mature and was potentially underrepresenting the technical risk of the program. We recommended that the program conduct a technology readiness assessment, which DHS completed in June 2019. DHS determined that two of the three key technologies were mature and the remaining technology was approaching maturity. The Coast Guard now has plans in place to use testing results to increase the maturity and reduce risks for the remaining technology—the hull form. • Design. The Coast Guard set program baselines before conducting a preliminary design review. This review is a systems engineering event intended to verify that the contractor’s design meets the requirement of the ship specifications and is producible. By not conducting this review before establishing program baselines, the program is at risk of having an unstable design, thereby increasing the program’s cost and schedule risks. We recommended that the program update its baselines prior to authorizing lead ship construction and after completion of the preliminary design review. DHS and the Coast Guard agreed and plan to take these steps by fiscal year 2022. • Cost. The cost estimate that informed the program’s $9.8 billion cost baseline—which includes life cycle costs for the acquisition, [and 30 years of] operations, and maintenance of three polar icebreakers—substantially met our best practices for being comprehensive, well-documented, and accurate. But the estimate only partially met best practices for being credible. The cost estimate did not quantify the range of possible costs over the entire life of the program, such as the period of operations and support. As a result, the cost estimate was not fully reliable and may underestimate the total funding needed for the program. We recommended that the program update its cost estimate to include risk and uncertainty analysis on all phases of the program life cycle, among other things. Subsequently, in December 2019, we found that while the Coast Guard updated the cost estimate in June 2019 to inform the budget process, the estimate did not reflect cost changes resulting from the contract award two months prior. Coast Guard officials acknowledged these cost risks Congressional Research Service 17 Coast Guard Polar Security Cutter (Polar Icebreaker) Program and plan to address them as part of the next update to the program’s cost estimate. Coast Guard officials told us that they plan to update the cost estimate by the end of February 2020. • Schedule. The Coast Guard’s initial planned delivery dates of 2023, 2025, and 2026 for the three ships were not informed by a realistic assessment of shipbuilding activities. Rather, these dates were primarily driven by the potential gap in icebreaking capabilities once the Coast Guard’s only operating heavy polar icebreaker—the Polar Star—reaches the end of its service life. In addition, our analysis of selected lead ships for other Coast Guard and Navy shipbuilding programs found the icebreaker program’s estimated construction time of 3 years to be optimistic. An unrealistic schedule puts the Coast Guard at risk of not delivering the icebreakers when promised. As a result, the potential gap in icebreaking capabilities could widen. We recommended that the program develop a realistic schedule, including delivery dates, and determine schedule risks during the construction phase of the program. In response, the Coast Guard is now tracking additional schedule risks for the program and is in the process of updating its program schedule. Further, in December 2019, we found that the contract delivery date for the lead ship, May 2024, is 2 months after the delivery date in the program’s schedule baseline. Coast Guard officials said they plan to address this risk when they update the program’s schedule by the end of March 2020.38 Common Design for Heavy and Medium Polar Icebreakers Another potential issue for Congress is whether to procure the Coast Guard’s envisioned fleet of PSCs (i.e., heavy polar icebreakers) and medium polar icebreakers to a common basic design. A congressionally mandated July 2017 report from the National Academies of Sciences, Engineering, and Medicine (NASEM) on the acquisition and operation of polar icebreakers concluded that notional operational requirements for new medium polar icebreakers would result in ships that would not be too different in size from new heavy polar icebreakers. (As shown in Table A-1, the Coast Guard’s current medium polar icebreaker, Healy, is actually somewhat larger than the Coast Guard’s heavy polar icebreaker, Polar Star.) Given what it concluded as the probable similarity in size between future U.S. heavy and medium polar icebreakers, the NASEM report recommended building a single medium polar icebreaker to the same common design as three new heavy polar icebreakers. This approach, the report concluded, would reduce the cost of the medium icebreaker by avoiding the cost of developing a new design and by making the medium polar icebreaker the fourth ship on an existing production learning curve rather than the first ship on a new production learning curve. The NASEM report stated the following (emphasis as in original): 2. Recommendation: The United States Congress should fund the construction of four polar icebreakers of common design that would be owned and operated by the United States Coast Guard (USCG). The current Department of Homeland Security (DHS) Mission Need Statement... contemplates a combination of medium and heavy icebreakers. The committee’s recommendation is for a single class of polar icebreaker with heavy icebreaking capability. Proceeding with a single class means that only one design will be needed, which will provide cost savings. The committee has found that the fourth heavy icebreaker could be built for a lower cost than the lead ship of a medium icebreaker class.... 38 Government Accountability Office, Arctic Capabilities[:] Coast Guard Is Taking Steps to Address Key Challenges, but Additional Work Remains, GAO-20-347T, Testimony Before the Subcommittee on Transportation and Maritime Security, Committee on Homeland Security, House of Representatives, Statement of Marie A. Mak, Director, Contracting and National Security Acquisitions, February 5, 2020, pp. 7-9. Congressional Research Service 18 Coast Guard Polar Security Cutter (Polar Icebreaker) Program The DHS Mission Need Statement contemplated a total fleet of “potentially” up to six ships of two classes—three heavy and three medium icebreakers. Details appear in the High Latitude Mission Analysis Report. The Mission Need Statement indicated that to fulfill its statutory missions, USCG required three heavy and three medium icebreakers; each vessel would have a single crew and would homeport in Seattle. The committee’s analysis indicated that four heavy icebreakers will meet the statutory mission needs gap identified by DHS for the lowest cost.... 4. Finding: In developing its independent concept designs and cost estimates, the committee determined that the costs estimated by USCG for the heavy icebreaker are reasonable. However, the committee believes that the costs of medium icebreakers identified in the High Latitude Mission Analysis Report are significantly underestimated.... Although USCG has not yet developed the operational requirements document for a medium polar icebreaker, the committee was able to apply the known principal characteristics of the USCG Cutter Healy to estimate the scope of work and cost of a similar medium icebreaker. The committee estimates that a first-of-class medium icebreaker will cost approximately $786 million. The fourth ship of the heavy icebreaker series is estimated to cost $692 million. Designing a medium-class polar icebreaker in a second shipyard would incur the estimated engineering, design, and planning costs of $126 million and would forgo learning from the first three ships; the learning curve would be restarted with the first medium design. Costs of building the fourth heavy icebreaker would be less than the costs of designing and building a first-of-class medium icebreaker.... 6. Recommendation: USCG should ensure that the common polar icebreaker design is science-ready and that one of the ships has full science capability. All four proposed ships would be designed as “science-ready,” which will be more costeffective when one of the four ships—most likely the fourth—is made fully science capable. Including science readiness in the common polar icebreaker design is the most cost-effective way of fulfilling both the USCG’s polar missions and the nation’s scientific research polar icebreaker needs.... The incremental costs of a science-ready design for each of the four ships ($10 million to $20 million per ship) and of full science capability for one of the ships at the initial build (an additional $20 million to $30 million) are less than the independent design and build cost of a dedicated research medium icebreaker.... In briefings at its first meeting, the committee learned that the National Science Foundation and other agencies do not have budgets to support full-time heavy icebreaker access or the incremental cost of design, even though their science programs may require this capability. Given the small incremental cost, the committee believes that the science capability cited above should be included in the acquisition costs. Science-ready design includes critical elements that cannot be retrofitted cost-effectively into an existing ship and that should be incorporated in the initial design and build. Among these elements are structural supports, appropriate interior and exterior spaces, flexible accommodation spaces that can embark up to 50 science personnel, a hull design that accommodates multiple transducers and minimizes bubble sweep while optimizing icebreaking capability, machinery arrangements and noise dampening to mitigate interference with sonar transducers, and weight and stability latitudes to allow installation of scientific equipment. Such a design will enable any of the ships to be retrofitted for full science capability in the future, if necessary.... Within the time frame of the recommended build sequence, the United States will require a science-capable polar icebreaker to replace the science capabilities of the Healy upon her retirement. To fulfill this need, one of the heavy polar icebreakers would be procured at the initial build with full science capability; the ability to fulfill other USCG missions would be retained. The ship would be outfitted with oceanographic overboarding equipment and instrumentation and facilities comparable with those of modern oceanographic research Congressional Research Service 19 Coast Guard Polar Security Cutter (Polar Icebreaker) Program vessels. Some basic scientific capability, such as hydrographic mapping sonar, should be acquired at the time of the build of each ship so that environmental data that are essential in fulfilling USCG polar missions can be collected.39 If policymakers decide to procure a second new medium polar icebreaker or a third new medium polar icebreaker, the same general approach recommended by the NASEM report could be followed—a second medium polar icebreaker and third medium polar icebreaker could be built to the same common design used for the three new heavy polar icebreakers and the first new medium polar icebreaker. An April 12, 2018, press report states the following: As the Coast Guard prepares to review industry bids for a new heavy polar icebreaker, the service is keeping its options open for the right number and mix of polar icebreakers it will need in the future, Adm. Paul Zukunft, the [then-]commandant of the Coast Guard, said on Wednesday [April 11]. The Coast Guard’s program of record is for three heavy and three medium polar icebreakers but Zukunft said the “jury is still out” whether that will remain so. Right now, the service is aiming toward building three new heavy icebreakers, but it might make sense just to keep building these ships, he told reporters at a Defense Writers Group breakfast in Washington, D.C. Zukunft said that “when you start looking at the business case after you build three, and then you need to look at what is the economy of scale when you start building heavy icebreakers, and would it be less expensive to continue to build heavies and not mediums.” He added that the heavy icebreakers provide more capability, and if the price is “affordable” and in “the same range” as building medium icebreakers, then “maybe you end up with one class of heavy icebreakers.” Building only one class of ships has a number of advantages in terms of maintenance, crew familiarity, configuration management, and more, he said. A decision on what the future icebreaker fleet will consist of is “still probably several years out .... but that’s one option that we want to keep open going forward,” Zukunft said. 40 Legislative Activity for FY2021 Summary of Appropriation Action on FY2021 Funding Request The Coast Guard’s proposed FY2021 budget requests $555 million in procurement funding for the PSC program. It also proposes a rescission of $70 million in FY2020 funding that Congress had provided for the procurement of long lead time materials (LLTM) for a 12th National Security Cutter (NSC), with the intent of reprogramming that funding to the PSC program. Table 2 summarizes congressional appropriation action on the program’s FY2021 funding request. 39 National Academies of Sciences, Engineering, and Medicine, Division on Earth and Life Studies and Transportation Research Board, Acquisition and Operation of Polar Icebreakers: Fulfilling the Nation’s Needs, Letter Report, with cover letter dated July 11, 2017, pp. 2, 4-6. 40 Calvin Biesecker, “Coast Guard Leaving Options Open For Future Polar Icebreaker Fleet Type,” Defense Daily, April 12, 2018. Ellipse as in original. Congressional Research Service 20 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Table 2. Summary of Congressional Appropriations Action on FY2021 Procurement Funding Request (millions of dollars) Request Procurement funding HAC SAC Conf. 555 Source: Table prepared by CRS, based on Coast Guard’s FY2021 budget submission, HAC and SAC committee reports, and conference report on FY2021 DHS Appropriations Act. HAC is House Appropriations Committee; SAC is Senate Appropriations Committee; Conf. is conference agreement. Congressional Research Service 21 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Appendix A. Current U.S. Polar Icebreakers and Polar Research Ships This appendix provides background information on current U.S. polar icebreakers and polar research ships. Three Coast Guard Polar Icebreakers Two Heavy Polar Icebreakers—Polar Star and Polar Sea Polar Star (WAGB-10) and Polar Sea (WAGB-11),41 sister ships built to the same general design (Figure A-1 and Figure A-2), were acquired in the early 1970s as replacements for earlier U.S. icebreakers. They were designed for 30-year service lives, and were built by Lockheed Shipbuilding of Seattle, WA, a division of Lockheed that also built ships for the U.S. Navy, but which exited the shipbuilding business in the late 1980s. Figure A-1. Polar Star and Polar Sea (Side by side in McMurdo Sound, Antarctica) Source: Coast Guard photograph that was accessed on April 21, 2011, at http://www.uscg.mil/pacarea/ cgcpolarsea/history.asp (link no longer active). The photograph accompanies Kyung M. Song, “Senate Passes Cantwell Measure to Postpone Scrapping of Polar Sea Icebreaker,” Seattle Times, September 22, 2012, posted at http://blogs.seattletimes.com/politicsnorthwest/2012/09/22/senate-passes-cantwell-measure-to-postponescrapping-of-polar-sea-icebreaker/. 41 The designation WAGB means Coast Guard icebreaker. More specifically, W means Coast Guard ship, A means auxiliary, G means miscellaneous purpose, and B means icebreaker. Congressional Research Service 22 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Figure A-2. Polar Sea Source: Coast Guard photograph that was accessed April 21, 2011, at http://www.uscg.mil/pacarea/cgcpolarsea/ img/PSEApics/FullShip2.jpg (link no longer active). The photograph accompanies Associated Press, “Reprieve for Seattle-Based Icebreaker Polar Sea,” KOMO News, June 15, 2012, posted at https://komonews.com/news/local/ reprieve-for-seattle-based-icebreaker-polar-sea. The ships are 399 feet long and displace about 13,200 tons.42 They are among the world’s most powerful nonnuclear-powered icebreakers, with a capability to break through ice up to 6 feet thick at a speed of 3 knots. Because of their icebreaking capability, they are considered (in U.S. parlance) heavy polar icebreakers. In addition to a crew of 134, each ship can embark a scientific research staff of 32 people. Polar Star was commissioned into service on January 19, 1976, and consequently is now more than 10 years beyond its originally intended 30-year service life. Due to worn-out electric motors and other problems, the Coast Guard placed the ship in caretaker status on July 1, 2006.43 Congress in FY2009 and FY2010 provided funding to repair Polar Star and return it to service for 7 to 10 years; the repair work, which reportedly cost about $57 million, was completed, and the ship was reactivated on December 14, 2012.44 Polar Sea was commissioned into service on February 23, 1978, and consequently is also more than 10 years beyond its originally intended 30-year service life. In 2006, the Coast Guard completed a rehabilitation project that extended the ship’s expected service life to 2014. On June 25, 2010, however, the Coast Guard announced that Polar Sea had suffered an engine casualty, and the ship was unavailable for operation after that.45 The Coast Guard placed Polar Sea in By comparison, the Coast Guard’s new National Security Cutters—its new high-endurance cutters—are about 418 feet long and displace roughly 4,000 tons. 43 Source for July 1, 2006, date: U.S. Coast Guard email to CRS on February 22, 2008. The Coast Guard’s official term for caretaker status is “In Commission, Special.” 44 See, for example, Kyung M. Song, “Icebreaker Polar Star Gets $57 Million Overhaul,” Seattle Times, December 14, 2012. 45 “Icebreaker POLAR SEA Sidelined By Engine Troubles,” Coast Guard Compass (Official Blog of the U.S. Coast Guard), June 25, 2010. See also “USCG Cancels Polar Icebreaker’s Fall Deployment,” DefenseNews.com, June 25, 2010; Andrew C. Revkin, “America’s Heavy Icebreakers Are Both Broken Down,” Dot Earth (New York Times blog), June 25, 2010. 42 Congressional Research Service 23 Coast Guard Polar Security Cutter (Polar Icebreaker) Program commissioned, inactive status on October 14, 2011. The Coast Guard transferred certain major equipment from Polar Sea to Polar Star to facilitate Polar Star’s return to service.46 Although the Coast Guard in recent years has invested millions of dollars to overhaul, repair, and extend the service life of Polar Star, the ship’s material condition, as a result of its advancing age, has nevertheless become increasingly fragile, if not precarious. During its annual deployments to McMurdo Station in Antarctica, shipboard equipment frequently breaks, and shipboard fires sometimes occur.47 Replacements for many of the ship’s components are no longer commercially available. To help keep Polar Star operational, the Coast Guard continues to use Polar Sea as a source of replacement parts. One Medium Polar Icebreaker—Healy Healy (WAGB-20) (Figure A-3) was funded in the early 1990s as a complement to Polar Star and Polar Sea, and was commissioned into service on August 21, 2000. Figure A-3. Healy Source: Coast Guard photograph accessed August 12, 2019, at https://www.history.uscg.mil/US-Coast-GuardPhoto-Gallery/igphoto/2002136680/. 46 Source: October 17, 2011, email to CRS from Coast Guard Congressional Affairs office. Section 222 of the Coast Guard and Maritime Transportation Act of 2012 (H.R. 2838/P.L. 112-213 of December 20, 2012) prohibited the Coast Guard from removing any part of Polar Sea and from transferring, relinquishing ownership of, dismantling, or recycling the ship until it submitted a business case analysis of the options for and costs of reactivating the ship and extending its service life to at least September 30, 2022, so as to maintain U.S. polar icebreaking capabilities and fulfill the Coast Guard’s high latitude mission needs, as identified in the Coast Guard’s July 2010 High Latitude Study. The business case analysis was submitted to Congress with a cover date of November 7, 2013. For more on the High Latitude Study, see Appendix B. 47 See, for example, Richard Read, “Meet the Neglected 43-Year-Old Stepchild of the U.S. Military-Industrial Complex,” Los Angeles Times, August 2, 2019; Melody Schreiber, “The Only Working US Heavy Icebreaker Catches Fire Returning from Antarctica,” Arctic Today, March 2, 2019; Calvin Biesecker, “Fire Breaks Out On Coast Guard’s Aging, and Only, Heavy Icebreaker,” Defense Daily, March 1, 2019. Congressional Research Service 24 Coast Guard Polar Security Cutter (Polar Icebreaker) Program The ship was built by Avondale Industries, a shipyard located near New Orleans, LA, that built numerous Coast Guard and Navy ships, and which eventually became part of Huntington Ingalls Industries (HII). (HII subsequently wound down shipbuilding activities at Avondale, and the facility is no longer building ships.) Although it is referred to (in U.S. parlance) as a medium polar icebreaker, Healy is actually larger than Polar Star and Polar Sea—it is 420 feet long and displaces about 16,000 tons. Compared to Polar Star and Polar Sea, Healy has less icebreaking capability (which is why it is referred to as a medium polar icebreaker rather than a heavy polar icebreaker), but more capability for supporting scientific research. The ship can break through ice up to 4½ feet thick at a speed of 3 knots, and embark a scientific research staff of 35 (with room for another 15 surge personnel and 2 visitors). The ship is used primarily for supporting scientific research and conducting other operations in the Arctic. Three National Science Foundation (NSF) Polar Research Ships Nathaniel B. Palmer Nathaniel B. Palmer (Figure A-4) was built for the NSF in 1992 by North American Shipbuilding, of Larose, LA. Figure A-4. Nathaniel B. Palmer Source: Photograph accompanying Peter Rejcek, “System Study, LARISSA Takes Unique Approach for Research on Ice Shelf Ecosystem,” Antarctic Sun (Untied States Antarctic Program), September 18, 2009. A caption to the photograph states “Photo Courtesy: Adam Jenkins.” Called Palmer for short, it is operated for NSF by Edison Chouest Offshore (ECO) of Galliano, LA, a firm that owns and operates research ships and offshore deepwater service ships.48 Palmer is 308 feet long and has a displacement of about 6,500 tons. It has a crew of 22 and can embark a 48 For more on ECO, see the firm’s website at http://www.chouest.com/. Congressional Research Service 25 Coast Guard Polar Security Cutter (Polar Icebreaker) Program scientific staff of 27 to 37.49 It was purpose-built as a single-mission ship for conducting and supporting scientific research in the Antarctic. It is capable of breaking ice up to 3 feet thick at speeds of 3 knots, which is sufficient for breaking through the ice conditions found in the vicinity of the Antarctic Peninsula, so as to resupply Palmer Station, a U.S. research station on the peninsula. The ship might be considered less an icebreaker than an oceanographic research ship with enough icebreaking capability for the Antarctic Peninsula. Palmer’s icebreaking capability is not considered sufficient to perform the McMurdo resupply mission. Laurence M. Gould Like Palmer, the polar research and supply ship Laurence M. Gould (Figure A-5) was built for NSF by North American Shipping. It was completed in 1997 and is operated for NSF on a longterm charter from ECO. It is 230 feet long and has a displacement of about 3,800 tons. It has a crew of 16 and can embark a scientific staff of 26 to 28 (with a capacity for 9 more in a berthing van). It can break ice up to 1 foot thick with continuous forward motion. Like Palmer, it was built to support NSF operations in the Antarctic, particularly operations at Palmer Station on the Antarctic Peninsula. Figure A-5. Laurence M. Gould Source: Photograph accompanying Alchetron, “RV Laurence M. Gould,” updated August 25, 2018, accessed August 7, 2019, at https://alchetron.com/RV-Laurence-M.-Gould#-. 49 Sources vary on the exact number of scientific staff that can be embarked on the ship. For some basic information on the ship, see http://www.nsf.gov/od/opp/support/nathpalm.jsp; http://www.usap.gov/vesselScienceAndOperations/documents/prvnews_june03.pdfprvnews_june03.pdf; http://nsf.gov/od/opp/antarct/treaty/pdf/plans0607/15plan07.pdf; http://www.nsf.gov/pubs/1996/nsf9693/fls.htm; and http://www.hazegray.org/worldnav/usa/nsf.htm. Congressional Research Service 26 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Sikuliaq Sikuliaq (see-KOO-lee-auk; Figure A-6), which is used for scientific research in polar areas, was built by Marinette Marine of Marinette, WI, and entered service in 2015. It is operated for NSF by the College of Fisheries and Ocean Sciences at the University of Alaska Fairbanks as part of the U.S. academic research fleet through the University National Oceanographic Laboratory System (UNOLS). Sikuliaq is 261 feet long and has a displacement of about 3,600 tons. It has a crew of 22 and can embark an additional 26 scientists and students. The ship can break ice 2½ or 3 feet thick at speeds of 2 knots. The ship is considered less an icebreaker than an ice-capable research ship. Figure A-6. Sikuliaq Source: Photograph accompanying Lauren Frisch, “UAF Joins International Consortium of Icebreaker Operators,” UAF [University of Alaska Fairbanks] News and Information, February 6, 2018. A caption to the photograph states in part: “Photo by Mark Teckenbrock. The research vessel Sikuliaq navigates through Arctic ice in summer 2016.” Summary Table A-1 summarizes the above six ships. In addition to the ships shown in Table A-1, another U.S.-registered polar ship with icebreaking capability—the Arctic oil-exploration support ship Aiviq—was used by Royal Dutch Shell oil company to support an oil exploration and drilling effort (now ended) in Arctic waters off Alaska. The ship, which completed construction in 2012, is owned by ECO and chartered by Royal Dutch Shell. It was used primarily for towing and laying anchors for drilling rigs, but is also equipped for responding to oil spills. Congressional Research Service 27 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Table A-1. Coast Guard and NSF Polar Ships Coast Guard NSF Polar Star Polar Sea Healy Palmer Laurence M. Gould Sikuliaq Currently operational? Yes No Yes Yes Yes Yes Entered service 1976 1978 2000 1992 1997 2015 Length (feet) 399 399 420 308 230 261 Displacement (tons) 13,200 13,200 16,000 6,500 3,780 3,665 Icebreaking capability (ice thickness in feet) at 3 knots or other speed 6 feet 6 feet 4.5 feet 3 feet 1 foot at continuous forward motion 2.5 or 3 feet at 2 knots Icebreaking capability using back and ram (ice thickness in feet) 21 feet 21 feet 8 feet n/a n/a n/a Operating temperature -60o Fahrenheit -60o Fahrenheit -50o Fahrenheit n/a n/a n/a Crew (when operational) 155a 155a 85b 22 16 22 Additional scientific staff 32 32 35c 27-37 26 to 28d 26 Sources: Prepared by CRS using data from U.S. Coast Guard, National Research Council, National Science Foundation, DHS Office of Inspector General, and (for Palmer) additional online reference sources. n/a is not available. a. Includes 24 officers, 20 chief petty officers, 102 enlisted, and 9 in the aviation detachment. b. Includes 19 officers, 12 chief petty officers, and 54 enlisted. c. In addition to 85 crew members 85 and 35 scientists, the ship can accommodate another 15 surge personnel and 2 visitors. d. Plus 9 more in a berthing van. Congressional Research Service 28 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Appendix B. Required Numbers of U.S. Polar Icebreakers This appendix provides additional background information on required numbers of U.S. polar icebreakers. June 9, 2020, Presidential Memorandum On June 9, 2020, President Trump issued a memorandum, “Memorandum on Safeguarding U.S. National Interests in the Arctic and Antarctic Regions,” which states: Memorandum for the Secretary of State, the Secretary of Defense, the Secretary of Commerce, the Secretary of Energy, the Secretary of Homeland Security, the Director of the Office of Management and Budget, [and] the Assistant to the President for National Security Affairs Subject: Safeguarding U.S. National Interests in the Arctic and Antarctic Regions To help protect our national interests in the Arctic and Antarctic regions, and to retain a strong Arctic security presence alongside our allies and partners, the United States requires a ready, capable, and available fleet of polar security icebreakers that is operationally tested and fully deployable by Fiscal Year 2029. Accordingly, by the authority vested in me as President by the Constitution and the laws of the United States of America, I hereby direct the following: Section 1. Fleet Acquisition Program. The United States will develop and execute a polar security icebreaking fleet acquisition program that supports our national interests in the Arctic and Antarctic regions. (a) The Secretary of Homeland Security, in coordination with the Secretary of State, the Secretary of Defense, the Secretary of Commerce, and the Director of the Office of Management and Budget (OMB), shall lead a review of requirements for a polar security icebreaking fleet acquisition program to acquire and employ a suitable fleet of polar security icebreakers, and associated assets and resources, capable of ensuring a persistent United States presence in the Arctic and Antarctic regions in support of national interests and in furtherance of the National Security Strategy and the National Defense Strategy, as appropriate. Separately, the review shall include the ability to provide a persistent United States presence in the Antarctic region, as appropriate, in accordance with the Antarctic Treaty System. The Secretary of Homeland Security and the Director of OMB, in executing this direction, shall ensure that the United States Coast Guard’s (USCG) Offshore Patrol Cutter acquisition program is not adversely impacted. (b) The Secretary of Homeland Security, acting through the Commandant of the Coast Guard, in coordination with the Secretary of Defense, acting through the Secretary of the Navy, and the Secretary of Energy, as appropriate, shall conduct a study of the comparative operational and fiscal benefits and risks of a polar security icebreaking fleet mix that consists of at least three heavy polar-class security cutters (PSC) that are appropriately outfitted to meet the objectives of this memorandum. This study shall be submitted to the President, through the Director of OMB and the Assistant to the President for National Security Affairs, within 60 days from the date of this memorandum and at a minimum shall include: (i) Use cases in the Arctic that span the full range of national and economic security missions (including the facilitation of resource exploration and exploitation and undersea cable laying and maintenance) that may be executed by a class of medium PSCs, as well as analysis of how these use cases differ with respect to the anticipated use of heavy PSCs Congressional Research Service 29 Coast Guard Polar Security Cutter (Polar Icebreaker) Program for these same activities. These use cases shall identify the optimal number and type of polar security icebreakers for ensuring a persistent presence in both the Arctic and, as appropriate, the Antarctic regions; (ii) An assessment of expanded operational capabilities, with estimated associated costs, for both heavy and medium PSCs not yet contracted for, specifically including the maximum use of any such PSC with respect to its ability to support national security objectives through the use of the following: unmanned aviation, surface, and undersea systems; space systems; sensors and other systems to achieve and maintain maritime domain awareness; command and control systems; secure communications and data transfer systems; and intelligence-collection systems. This assessment shall also evaluate defensive armament adequate to defend against threats by near-peer competitors and the potential for nuclear-powered propulsion; (iii) Based on the determined fleet size and composition, an identification and assessment of at least two optimal United States basing locations and at least two international basing locations. The basing location assessment shall include the costs, benefits, risks, and challenges related to infrastructure, crewing, and logistics and maintenance support for PSCs at these locations. In addition, this assessment shall account for potential burdensharing opportunities for basing with the Department of Defense and allies and partners, as appropriate; and (iv) In anticipation of the USCGC POLAR STAR’s operational degradation from Fiscal Years 2022-2029, an analysis to identify executable options, with associated costs, to bridge the gap of available vessels as early as Fiscal Year 2022 until the new PSCs required to meet the objectives of this memorandum are operational, including identifying executable, priced leasing options, both foreign and domestic. This analysis shall specifically include operational risk associated with using a leased vessel as compared to a purchased vessel to conduct specified missions set forth in this memorandum. (c) In the interest of securing a fully capable polar security icebreaking fleet that is capable of providing a persistent presence in the Arctic and Antarctic regions at the lowest possible cost, the Secretary of State shall coordinate with the Secretary of Homeland Security in identifying viable polar security icebreaker leasing options, provided by partner nations, as a near- to mid-term (Fiscal Years 2022-2029) bridging strategy to mitigate future operational degradation of the USCGC POLAR STAR. Leasing options shall contemplate capabilities that allow for access to the Arctic and Antarctic regions to, as appropriate, conduct national and economic security missions, in addition to marine scientific research in the Arctic, and conduct research in Antarctica in accordance with the Antarctic Treaty System. Further, and in advance of any bid solicitation for future polar security icebreaker acquisitions, the Secretary of State shall coordinate with the Secretary of Homeland Security to identify partner nations with proven foreign shipbuilding capability and expertise in icebreaker construction. (d) The Secretary of Defense shall coordinate with the Secretary of State and the Secretary of Homeland Security to continue to provide technical and programmatic support to the USCG integrated program office for the acquisition, outfitting, and operations of all classes of PSCs. Sec. 2. General Provisions. (a) Nothing in this memorandum shall be construed to impair or otherwise affect: (i) the authority granted by law to an executive department or agency, or the head thereof; or (ii) the functions of the Director of OMB relating to budgetary, administrative, or legislative proposals. Congressional Research Service 30 Coast Guard Polar Security Cutter (Polar Icebreaker) Program (b) This memorandum shall be implemented consistent with applicable law and subject to the availability of appropriations. (c) This memorandum is not intended to, and does not, create any right or benefit, substantive or procedural, enforceable at law or in equity by any party against the United States, its departments, agencies, or entities, its officers, employees, or agents, or any other person.50 June 2013 DHS Polar Icebreaker Mission Need Statement DHS in June 2013 approved a Mission Need Statement (MNS) for the polar icebreaker recapitalization project. The MNS states the following (emphasis added): This Mission Need Statement (MNS) establishes the need for polar icebreaker capabilities provided by the Coast Guard, to ensure that it can meet current and future mission requirements in the polar regions.... Current requirements and future projections based upon cutter demand modeling, as detailed in the HLMAR [High Latitude Mission Analysis Report], indicate the Coast Guard will need to expand its icebreaking capacity, potentially requiring a fleet of up to six icebreakers (3 heavy and 3 medium) to adequately meet mission demands in the high latitudes.... The analysis took into account both the Coast Guard statutory mission requirements and additional requirements for year-round presence in both polar regions detailed in the Naval Operations Concept (NOC) 2010.... The analysis also evaluated employing single and multi-crewing concepts.... Strategic home porting analysis based upon existing infrastructure and distance to operational areas provided the final input to determine icebreaker capacity demand. 51 While the MNS can be viewed as an authoritative U.S. government statement regarding required numbers of U.S. polar icebreakers, it can be noted that the key sentence in the above-quoted passage from the MNS (i.e., the sentence in bold) includes the terms “potentially” and “up to.” These terms, which are often overlooked in discussions of required numbers of U.S. polar icebreakers, make the key sentence less ironclad as a requirements statement than it would have been if the terms had not been included, and could be interpreted as an acknowledgment that the requirement might amount to something less than three heavy and three medium polar icebreakers. It can also be noted, as stated in the above-quoted passage from the MNS, that the MNS was informed by the High Latitude Mission Analysis Report (HILMAR), and that the HLMAR took into account not only Coast Guard statutory mission requirements, but additional DOD requirements for year-round presence in both polar regions as detailed in the 2010 Naval Operations Concept (NOC). This is potentially significant, because DOD appears to have subsequently dropped its 2010 requirement for year-round presence in the polar regions.52 White House, “Memorandum on Safeguarding U.S. National Interests in the Arctic and Antarctic Regions,” June 9, 2020, accessed June 10, 2020, at https://www.whitehouse.gov/presidential-actions/memorandum-safeguarding-u-snational-interests-arctic-antarctic-regions/. For press reports about the memorandum, see, for example, David B. Larter, Joe Gould, and Aaron Mehta, “Trump Memo Demands New Fleet of Arctic Icebreakers Be Ready by 2029,” Defense News, June 9, 2020; Paul McLeary, “White House Orders New Icebreaker Strategy For Coast Guard,” Breaking Defense, June 9, 2020; Cal Biesecker, “Trump Wants Review Of Polar Security Cutter Needs In Arctic, Antarctic,” Defense Daily, June 9, 2020. 51 Department of Homeland Security, Polar Icebreaking Recapitalization Project Mission Need Statement, Version 1.0, approved by DHS June 28, 2013, pp. 1, 2, 9, 10, 11, 12. 52 A September 25, 2017, GAO report on polar icebreakers states the following (emphasis added): 50 Congressional Research Service 31 Coast Guard Polar Security Cutter (Polar Icebreaker) Program The use in the MNS of the terms “potentially” and “up to,” combined with DOD’s decision to drop its requirement for year-round presence in the polar regions, together raise a question, other things held equal, as to whether required numbers of U.S. polar icebreakers might be something less than three heavy and three medium polar icebreakers. It is also possible, however, that there have been other changes since the MNS was issued in 2013 that would have the effect, other things held equal, of increasing U.S. requirements for polar icebreakers. The net result of this situation appears uncertain. In recent years, Coast Guard officials have tended to refer simply to a total Coast Guard requirement for three heavy and three medium polar icebreakers. For example, in the October 25, 2016, summary of a request for information (RFI) that the Coast Guard released the next day to receive industry feedback on its notional polar icebreaker acquisition approach and schedule, the Coast Guard states that “the United States Coast Guard has a need for three Heavy Polar Icebreakers and three Medium Polar Icebreakers with the priority being Heavy Polar Icebreakers.”53 A requirement for three heavy and three medium polar icebreakers is often abbreviated as 3+3. Short of a 3+3 requirement, Coast Guard officials in the past have sometimes stated that, as a bare minimum number of heavy polar icebreakers, the Coast Guard needs two such ships. For example, at a November 17, 2015, hearing before the Europe, Eurasia, and Emerging Threats subcommittee and the Western Hemisphere subcommittee of the House Foreign Affairs Committee, then-Vice Admiral Charles Michel, the Vice Commandant of the Coast Guard, stated during the discussion portion of the hearing that the “Coast Guard needs at least two heavy icebreakers to provide year-round assured access and self-rescueability in the polar regions.”54 Similarly, at a June 14, 2016, hearing before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee, Admiral Michel testified that “our commandant also testified that we need self-rescue capability for our heavy icebreaker and that includes the existing Polar Star that we have out there now. So that means at least two [ships], [and] the High Latitude study says three heavy polar icebreakers is what the In December 2016, DOD reported to Congress that it had no specific defense requirement for icebreaking capability because Navy Arctic requirements are met by undersea and air assets which can provide year-round presence. —DOD reported in April 2017 that its only potential defense requirement—for the Thule Air Force Base resupply [mission] in Greenland—is met by the Canadian Coast Guard through a Memorandum of Understanding with USCG. —USCG’s 2013 Polar Icebreaker Mission Needs Statement identified polar icebreaker capacity needs as partly based on the 2010 Naval Operations Concept—[a document that provides] joint maritime security strategy implementation guidance for the Navy, Marine Corps, and USCG— which stated that U.S. naval forces had a demand for year-round polar icebreaking presence in the Arctic and Antarctic. —In April 2017, DOD joint staff officials confirmed that DOD and Naval defense strategy had been updated and does not include icebreaking requirements. DOD officials in charge of operations in the Pacific said that although they do not have a requirement for a heavy icebreaker, icebreakers play a key role in aiding the icebreaking mission to McMurdo. (Government Accountability Office, Coast Guard: Status of Polar Icebreaking Fleet Capability and Recapitalization Plan, GAO-17-698R, September 25, 2017, p. 20 (briefing slide 11).) 53 Summary of RFI, October 25, 2016, page 2, accessed November 10, 2016, at https://www.uscg.mil/acquisition/ icebreaker/pdf/Acquisition-Strategy-RFI.pdf. 54 Transcript of hearing. Congressional Research Service 32 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Coast Guard’s requirement is. So that’s kind of where we’re talking about for heavy icebreakers.”55 A September 25, 2017, GAO report on polar icebreakers states that the Coast Guard has been unable to address all polar icebreaking requests since 2010. For example, the Coast Guard reported fulfilling 78 percent (25 of 32) of U.S. government agency requests for polar icebreaking services during fiscal year 2010 through 2016. Coast Guard officials cited various factors affecting the Coast Guard’s ability to meet all requests, particularly the unavailability of its heavy polar icebreakers.56 A July 2018 GAO report stated that the Coast Guard operates one medium icebreaker, the Healy, which has an expected end of service life in 2029. Despite the requirement for three medium icebreakers, Coast Guard officials said they are not currently assessing acquisition of the medium polar icebreakers because they are focusing on the heavy icebreaker acquisition and plan to assess the costs and benefits of acquiring medium polar icebreakers at a later time. 57 In addition to the HILMAR, a number of other studies have been conducted in recent years to assess U.S. requirements for polar icebreakers and options for sustaining and modernizing the Coast Guard’s polar icebreaker fleet. Polar Icebreakers Operated by Other Countries In discussions of U.S. polar icebreakers, observers sometimes note the size of the polar icebreaking fleets operated by other countries. Table B-1 shows a Coast Guard summary of major icebreakers around the world; the figures in the table include some icebreakers designed for use in the Baltic Sea. Observers sometimes highlight the difference between the number of U.S. polar icebreakers and the much larger number of Russian polar icebreakers. In considering these relative numbers, it can be noted that Russia’s Arctic coastline is much longer than the U.S. Arctic coastline, that many more people live in Russia’s Arctic (about roughly 2 million) than in the U.S. Arctic (fewer than 68,000 as of July 1, 2017),58 and that maritime transportation along Russia’s Arctic coast is critical for supporting numerous Russian Arctic communities. Countries with interests in the polar regions have differing requirements for polar icebreakers, depending on the nature and extent of their polar interests and activities. 55 Transcript of hearing. Government Accountability Office, Coast Guard: Status of Polar Icebreaking Fleet Capability and Recapitalization Plan, GAO-17-698R, September 25, 2017, pp. 2-3. A similar statement appears on page 4. 57 Government Accountability Office, Coast Guard Acquisitions[:] Actions Needed to Address Longstanding Portfolio Management Challenges, GAO-18-454, July 2018, p. 13. 58 For additional discussion, see the Background section of CRS Report R41153, Changes in the Arctic: Background and Issues for Congress, coordinated by Ronald O'Rourke. 56 Congressional Research Service 33 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Table B-1. Major Icebreakers of the World as of May 1, 2017 (Includes some icebreakers designed for Baltic use) Russia Total all types, in inventory (+ under construction + planned) 46 (+11 + 4) Finland 10 Canada Sweden 7 (+2 +5) 7 (+0 +3) United States 5 (+0 +3) Denmark 45,000 or more BHP 6 (all nuclear powered; 2 not operational) 2 (Polar Star and Polar Sea; Polar Sea not operational) 20,000 to 44,999 BHP 16 (1 nuclear powered; 5 designed for Baltic use) 7 (4 designed for Baltic use) 2 4 (3 designed for Baltic use) 1 (Healy) 10,000 to 19,999 BHP 7 3 (+1 +0) 2 Norway Germany Chile Australia Latvia 1 (+1 +0) 1 (+0 +1) 1 (+0 +1) 1 (+0 +1) 1 Japan South Korea South Africa Argentina 1 1 1 1 In inventory, privately owned and operated 45,000 or more BHP 20,000 to 44,999 BHP 9 1 10,000 to 19,999 BHP 8 2 5 3 1 (Aiviq) 1 (Palmer) 4 (all 4 designed for Baltic use) 4 China Estonia United Kingdom In inventory, government owned or operated 3 2 (both designed for Baltic use) 1 1 1 1 1 (designed for Baltic use) 1 1 1 1 (not operational) 0 (+1 +0) Source: Table prepared by CRS based on U.S. Coast Guard chart showing data compiled by the Coast Guard as of May 1, 2017, accessed September 14, 2017, at http://www.dco.uscg.mil/Portals/9/DCO%20Documents/ Office%20of%20Waterways%20and%20Ocean%20Policy/20170501%20major%20icebreaker%20chart.pdf?ver= 2017-06-08-091723-907. Notes: BHP = the brake horsepower of the ship’s power plant. A ship with 45,000 or more BHP might be considered a heavy polar icebreaker, a ship with 20,000 to 44,999 BHP might be considered a medium polar icebreaker, and a ship with 10,000 to 19,999 BHP might be considered a light polar icebreaker or an ice-capable polar ship. Congressional Research Service 34 Coast Guard Polar Security Cutter (Polar Icebreaker) Program July 2017 National Academies (NASEM) Report A July 2017 report on the acquisition and operation of polar icebreakers by the National Academies of Sciences, Engineering, and Medicine (NASEM) that was directed by Congress in Section 604 of the Coast Guard Authorization Act of 2015 (H.R. 4188/P.L. 114-120 of February 8, 2016) concluded the following: INTRODUCTION The United States has strategic national interests in the polar regions. In the Arctic, the nation must protect its citizens, natural resources, and economic interests; assure sovereignty, defense readiness, and maritime mobility; and engage in discovery and research. In the Antarctic, the United States must maintain an active presence that includes access to its research stations for the peaceful conduct of science and the ability to participate in inspections as specified in the Antarctic Treaty. The committee’s charge... was to advise the U.S. House of Representatives and the U.S. Senate on an assessment of the costs incurred by the federal government in carrying out polar icebreaking missions and on options that could minimize lifecycle costs. The committee’s consensus findings and recommendations are presented below. Unless otherwise specified, all estimated costs and prices for the future U.S. icebreakers are expressed in 2019 dollars, since that is the year in which the contracts are scheduled to be made. Supporting material is found in the appendices. FINDINGS AND RECOMMENDATIONS 1. Finding: The United States has insufficient assets to protect its interests, implement U.S. policy, execute its laws, and meet its obligations in the Arctic and Antarctic because it lacks adequate icebreaking capability. For more than 30 years, studies have emphasized the need for U.S. icebreakers to maintain presence, sovereignty, leadership, and research capacity—but the nation has failed to respond.... The strong warming and related environmental changes occurring in both the Arctic and the Antarctic have made this failure more critical. In the Arctic, changing sea ice conditions will create greater navigation hazards for much of the year, and expanding human industrial and economic activity will magnify the need for national presence in the region. In the Antarctic, sea ice trends have varied greatly from year to year, but the annual requirements for access into McMurdo Station have not changed. The nation is ill-equipped to protect its interests and maintain leadership in these regions and has fallen behind other Arctic nations, which have mobilized to expand their access to ice-covered regions. The United States now has the opportunity to move forward and acquire the capability to fulfill these needs.... 2. Recommendation: The United States Congress should fund the construction of four polar icebreakers of common design that would be owned and operated by the United States Coast Guard (USCG). The current Department of Homeland Security (DHS) Mission Need Statement (DHS 2013) contemplates a combination of medium and heavy icebreakers. The committee’s recommendation is for a single class of polar icebreaker with heavy icebreaking capability. Proceeding with a single class means that only one design will be needed, which will provide cost savings. The committee has found that the fourth heavy icebreaker could be built for a lower cost than the lead ship of a medium icebreaker class.... The DHS Mission Need Statement contemplated a total fleet of “potentially” up to six ships of two classes—three heavy and three medium icebreakers. Details appear in the High Latitude Mission Analysis Report. The Mission Need Statement indicated that to fulfill its statutory missions, USCG required three heavy and three medium icebreakers; each vessel would have a single crew and would homeport in Seattle. The committee’s analysis Congressional Research Service 35 Coast Guard Polar Security Cutter (Polar Icebreaker) Program indicated that four heavy icebreakers will meet the statutory mission needs gap identified by DHS for the lowest cost. Three of the ships would allow continuous presence in the Arctic, and one would service the Antarctic. As noted in the High Latitude Report, USCG’s employment standard is 185 days away from home port (DAFHP) for a single crew. Three heavy icebreakers in the Arctic provide 555 DAFHP, sufficient for continuous presence. In addition, the medium icebreaker USCG Cutter Healy’s design service life runs through 2030. If greater capacity is required, USCG could consider operating three ships with four crews, which would provide 740 DAFHP. The use of multiple crews in the Arctic could require fewer ships while providing a comparable number of DAFHP. For example, two ships (instead of the recommended three) operating in the Arctic with multiple crews could provide a similar number of annual operating days at a lower cost, but such an arrangement may not permit simultaneous operations in both polar regions and may not provide adequate redundancy in capability. More important, an arrangement under which fewer boats are operated more often would require more major maintenance during shorter time in port, often at increasing cost. In addition, if further military presence is desired in the Arctic, USCG could consider icestrengthening the ninth national security cutter. One heavy icebreaker servicing the Antarctic provides for the McMurdo breakout and international treaty verification. The availability of the vessel could be extended by homeporting in the Southern Hemisphere. If the single vessel dedicated to the Antarctic is rendered inoperable, USCG could redirect an icebreaker from the Arctic, or it could rely on support from other nations. The committee considers both options to be viable and believes it difficult to justify a standby (fifth) vessel for the Antarctic mission when the total acquisition and lifetime operating costs of a single icebreaker are projected to exceed $1.6 billion. Once the four new icebreakers are operational, USCG can reasonably be expected to plan for more distant time horizons. USCG could assess the performance of the early ships once they are operational and determine whether additional capacity is needed. USCG is the only agency of the U.S. government that is simultaneously a military service, a law enforcement agency, a marine safety and rescue agency, and an environmental protection agency. All of these roles are required in the mission need statement for a polar icebreaker. USCG, in contrast to a civilian company, has the authorities, mandates, and competencies to conduct the missions contemplated for the polar icebreakers. Having one agency with a multimission capability performing the range of services needed would be more efficient than potentially duplicating effort by splitting polar icebreaker operations among other agencies. The requirement for national presence is best accomplished with a military vessel. In addition, USCG is fully interoperable with the U.S. Navy and the nation’s North Atlantic Treaty Organization partners. USCG is already mandated to operate the nation’s domestic and polar icebreakers. Continuing to focus this expertise in one agency remains the logical approach.... Government ownership of new polar icebreakers would be less costly than the use of lease financing (see Appendix C). The government has a lower borrowing cost than any U.S.based leasing firm or lessor. In addition, the lessor would use higher-cost equity (on which it would expect to make a profit) to cover a portion of the lease financing. The committee’s analysis shows that direct purchase by the government would cost, at a minimum, 19 percent less than leasing on a net present value basis (after tax). There is also the risk of the lessor going bankrupt and compromising the availability of the polar icebreaker to USCG. For its analysis, the committee not only relied on its extensive experience with leveraged lease financing but also reviewed available Government Accountability Office reports and Office of Management and Budget rules, examined commercial leasing Congressional Research Service 36 Coast Guard Polar Security Cutter (Polar Icebreaker) Program economics and current interest rates, and validated its analysis by consulting an outside expert on the issue.... Chartering (an operating lease) is not a viable option.... The availability of polar icebreakers on the open market is extremely limited. (The committee is aware of the sale of only one heavy icebreaker since 2010.) U.S. experience with chartering a polar icebreaker for the McMurdo resupply mission has been problematic on two prior charter attempts. Chartering is workable only if the need is short term and mission specific. The committee notes that chartering may preclude USCG from performing its multiple missions.... In the committee’s judgment, an enlarged icebreaker fleet will provide opportunities for USCG to strengthen its icebreaking program and mission. Although the number of billets that require an expert is small compared with the overall number of billets assigned to these icebreakers, more people performing this mission will increase the pool of experienced candidates. This will provide personnel assignment officers with a larger pool of candidates when the more senior positions aboard icebreakers are designated, which will make icebreaking more attractive as a career path and increase the overall level of icebreaking expertise within USCG. Importantly, the commonality of design of the four recommended heavy icebreakers will reduce operating and maintenance costs over the service life of these vessels through efficiencies in supporting and crewing them. Having vessels of common design will likely improve continuity of service, build icebreaking competency, improve operational effectiveness, and be more cost-efficient.... 3. Recommendation: USCG should follow an acquisition strategy that includes block buy contracting with a fixed price incentive fee contract and take other measures to ensure best value for investment of public funds. Icebreaker design and construction costs can be clearly defined, and a fixed price incentive fee construction contract is the most reliable mechanism for controlling costs for a program of this complexity. This technique is widely used by the U.S. Navy. To help ensure best long-term value, the criteria for evaluating shipyard proposals should incorporate explicitly defined lifecycle cost metrics.... A block buy authority for this program will need to contain specific language for economic order quantity purchases for materials, advanced design, and construction activities. A block buy contracting program with economic order quantity purchases enables series construction, motivates competitive bidding, and allows for volume purchase and for the timely acquisition of material with long lead times. It would enable continuous production, give the program the maximum benefit from the learning curve, and thus reduce labor hours on subsequent vessels. The acquisition strategy would incorporate (a) technology transfer from icebreaker designers and builders with recent experience, including international expertise in design, construction, and equipment manufacture; (b) a design that maximizes use of commercial off-the-shelf (COTS) equipment, applies Polar Codes and international standards, and only applies military specifications (MIL-SPEC) to the armament, aviation, communications, and navigation equipment; (c) reduction of any “buy American” provisions to allow the sourcing of the most suitable and reliable machinery available on the market; and (d) a program schedule that allows for completion of design and planning before the start of construction. These strategies will allow for optimization of design, reduce construction costs, and enhance reliability and maintainability.... 4. Finding: In developing its independent concept designs and cost estimates, the committee determined that the costs estimated by USCG for the heavy icebreaker are reasonable. However, the committee believes that the costs of medium icebreakers identified in the High Latitude Mission Analysis Report are significantly underestimated. Congressional Research Service 37 Coast Guard Polar Security Cutter (Polar Icebreaker) Program The committee estimates the rough order-of-magnitude (ROM) cost of the first heavy icebreaker to be $983 million. (See Appendix D, Table D-6.) Of these all-in costs, 75 to 80 percent are shipyard design and construction costs; the remaining 20 to 25 percent cover government-incurred costs such as government-furnished equipment and governmentincurred program expenses. If advantage is taken of learning and quantity discounts available through the recommended block buy contracting acquisition strategy, the average cost per heavy icebreaker is approximately $791 million, on the basis of the acquisition of four ships. The committee’s analysis of the ship size to incorporate the required components (stack-up length) suggests an overall length of 132 meters (433 feet) and a beam of 27 meters (89 feet). This is consistent with USCG concepts for the vessel. Costs can be significantly reduced by following the committee’s recommendations. Reduction of MIL-SPEC requirements can lower costs by up to $100 million per ship with no loss of mission capability.... The other recommended acquisition, design, and construction strategies will control possible cost overruns and provide significant savings in overall life-cycle costs for the program. Although USCG has not yet developed the operational requirements document for a medium polar icebreaker, the committee was able to apply the known principal characteristics of the USCG Cutter Healy to estimate the scope of work and cost of a similar medium icebreaker. The committee estimates that a first-of-class medium icebreaker will cost approximately $786 million. The fourth ship of the heavy icebreaker series is estimated to cost $692 million. Designing a medium-class polar icebreaker in a second shipyard would incur the estimated engineering, design, and planning costs of $126 million and would forgo learning from the first three ships; the learning curve would be restarted with the first medium design. Costs of building the fourth heavy icebreaker would be less than the costs of designing and building a first-of-class medium icebreaker... . In developing its ROM cost estimate, the committee agreed on a common notional design and basic assumptions.... Two committee members then independently developed cost estimating models, which were validated internally by other committee members. These analyses were then used to establish the committee’s primary cost estimate.... 5. Finding: Operating costs of new polar icebreakers are expected to be lower than those of the vessels they replace. The committee expects the operating costs for the new heavy polar icebreakers to be lower than those of USCG’s Polar Star. While USCG’s previous experience is that operating costs of new cutters are significantly higher than those of the vessels they replace, the committee does not believe this historical experience applies in this case. There is good reason to believe that operating costs for new ships using commercially available modern technology will be lower than costs for existing ships.... The more efficient hull forms and modern engines will reduce fuel consumption, and a well-designed automation plant will require fewer operation and maintenance personnel, which will allow manning to be reduced or freed up for alternative tasks. The use of COTS technology and the minimization of MIL-SPEC, as recommended, will also reduce long-term maintenance costs, since use of customized equipment to meet MIL-SPEC requirements can reduce reliability and increase costs. A new vessel, especially over the first 10 years, typically has significantly reduced major repair and overhaul costs, particularly during dry-dock periods, compared with existing icebreakers—such as the Polar Star—that are near or at the end of their service life.... The Polar Star has many age-related issues that require it to be extensively repaired at an annual dry-docking. These issues will be avoided in the early years of a new ship. However, the committee recognizes that new ship operating costs can be higher than those of older ships if the new ship has more complexity to afford more capabilities. Therefore, any direct comparisons of operating costs of newer versus older ships would need to take into account the benefits of the additional capabilities provided by the newer ship. Congressional Research Service 38 Coast Guard Polar Security Cutter (Polar Icebreaker) Program USCG will have an opportunity to evaluate the manning levels of the icebreaker in light of the benefits of modern technology to identify reductions that can be made in operating costs.... 6. Recommendation: USCG should ensure that the common polar icebreaker design is science-ready and that one of the ships has full science capability. All four proposed ships would be designed as “science-ready,” which will be more costeffective when one of the four ships—most likely the fourth—is made fully science capable. Including science readiness in the common polar icebreaker design is the most cost-effective way of fulfilling both the USCG’s polar missions and the nation’s scientific research polar icebreaker needs.... The incremental costs of a science-ready design for each of the four ships ($10 million to $20 million per ship) and of full science capability for one of the ships at the initial build (an additional $20 million to $30 million) are less than the independent design and build cost of a dedicated research medium icebreaker.... In briefings at its first meeting, the committee learned that the National Science Foundation and other agencies do not have budgets to support full-time heavy icebreaker access or the incremental cost of design, even though their science programs may require this capability. Given the small incremental cost, the committee believes that the science capability cited above should be included in the acquisition costs. Science-ready design includes critical elements that cannot be retrofitted cost-effectively into an existing ship and that should be incorporated in the initial design and build. Among these elements are structural supports, appropriate interior and exterior spaces, flexible accommodation spaces that can embark up to 50 science personnel, a hull design that accommodates multiple transducers and minimizes bubble sweep while optimizing icebreaking capability, machinery arrangements and noise dampening to mitigate interference with sonar transducers, and weight and stability latitudes to allow installation of scientific equipment. Such a design will enable any of the ships to be retrofitted for full science capability in the future, if necessary.... Within the time frame of the recommended build sequence, the United States will require a science-capable polar icebreaker to replace the science capabilities of the Healy upon her retirement. To fulfill this need, one of the heavy polar icebreakers would be procured at the initial build with full science capability; the ability to fulfill other USCG missions would be retained. The ship would be outfitted with oceanographic overboarding equipment and instrumentation and facilities comparable with those of modern oceanographic research vessels. Some basic scientific capability, such as hydrographic mapping sonar, should be acquired at the time of the build of each ship so that environmental data that are essential in fulfilling USCG polar missions can be collected. 7. Finding: The nation is at risk of losing its heavy polar icebreaking capability— experiencing a critical capacity gap—as the Polar Star approaches the end of its extended service life, currently estimated at 3 to 7 years. The Polar Star, built in 1976, is well past its 30-year design life. Its reliability will continue to decline, and its maintenance costs will continue to escalate. Although the ship went through an extensive life-extending refit in 2011–2012, the Polar Star’s useful life is estimated to end between 2020 and 2024. As USCG has recognized, the evaluation of alternative arrangements to secure polar icebreaking capacity is important, given the growing risks of the Polar Star losing its capability to fulfill its mission.... 8. Recommendation: USCG should keep the Polar Star operational by implementing an enhanced maintenance program (EMP) until at least two new polar icebreakers are commissioned. Even if the committee’s notional schedule for new polar icebreakers is met, the second polar icebreaker would not be ready until July 2025.... The committee’s proposed EMP could be designed with planned—and targeted—upgrades that allow the Polar Star to Congressional Research Service 39 Coast Guard Polar Security Cutter (Polar Icebreaker) Program operate every year for its Antarctic mission. The necessary repairs could be performed in conjunction with the ship’s current yearly dry-docking schedule within existing annual expenditures, estimated to average $5 million. In particular, the EMP would require improvements in the ship’s operating systems, sanitary system, evaporators, main propulsion systems, and controllable pitch propellers. In the committee’s judgment, the EMP could be accomplished within USCG’s average annual repair expenditures for the Polar Star, which currently range between $2 million and $9 million. 59 Coast Guard High Latitude Study Provided to Congress in July 2011 In July 2011, the Coast Guard provided to Congress a study on the Coast Guard’s missions and capabilities for operations in high-latitude (i.e., polar) areas. The study, commonly known as the High Latitude Study, is dated July 2010 on its cover. The High Latitude Study concluded the following: [The study] concludes that future capability and capacity gaps will significantly impact four [Coast Guard] mission areas in the Arctic: Defense Readiness, Ice Operations, Marine Environmental Protection, and Ports, Waterways, and Coastal Security. These mission areas address the protection of important national interests in a geographic area where other nations are actively pursuing their own national goals.... The common and dominant contributor to these significant mission impacts is the gap in polar icebreaking capability. The increasing obsolescence of the Coast Guard’s icebreaker fleet will further exacerbate mission performance gaps in the coming years.... The gap in polar icebreaking capacity has resulted in a lack of at-sea time for crews and senior personnel and a corresponding gap in training and leadership. In addition to providing multi-mission capability and intrinsic mobility, a helicopter-capable surface unit would eliminate the need for acquiring an expensive shore-based infrastructure that may only be needed on a seasonal or occasional basis. The most capable surface unit would be a polar icebreaker. Polar icebreakers can transit safely in a variety of ice conditions and have the endurance to operate far from logistics bases. The Coast Guard’s polar icebreakers have conducted a wide range of planned and unscheduled Coast Guard missions in the past. Polar icebreakers possess the ability to carry large numbers of passengers, cargo, boats, and helicopters. Polar icebreakers also have substantial command, control, and communications capabilities. The flexibility and mobility of polar icebreakers would assist the Coast Guard in closing future mission performance gaps effectively.... Existing capability and capacity gaps are expected to significantly impact future Coast Guard performance in two Antarctic mission areas: Defense Readiness and Ice Operations. Future gaps may involve an inability to carry out probable and easily projected mission requirements, such as the McMurdo resupply, or readiness to respond to less-predictable events. By their nature, contingencies requiring the use of military capabilities often occur quickly. As is the case in the Arctic, the deterioration of the Coast Guard’s icebreaker fleet is the primary driver for this significant mission impact. This will further widen mission performance gaps in the coming years. The recently issued Naval Operations Concept 2010 requires a surface presence in both the Arctic and Antarctic. This further exacerbates the capability gap left by the deterioration of the icebreaker fleet.... 59 National Academies of Sciences, Engineering, and Medicine, Division on Earth and Life Studies and Transportation Research Board, Acquisition and Operation of Polar Icebreakers: Fulfilling the Nation’s Needs, Letter Report, with cover letter dated July 11, 2017, pp. 9-20. Congressional Research Service 40 Coast Guard Polar Security Cutter (Polar Icebreaker) Program The significant deterioration of the Coast Guard icebreaker fleet and the emerging mission demands to meet future functional requirements in the high latitude regions dictate that the Coast Guard acquire material solutions to close the capability gaps.... To meet the Coast Guard mission functional requirement, the Coast Guard icebreaking fleet must be capable of supporting the following missions:  Arctic North Patrol. Continuous multimission icebreaker presence in the Arctic.  Arctic West Science. Spring and summer science support in the Arctic.  Antarctic, McMurdo Station resupply. Planned deployment for break-in, supply ship escort, and science support. This mission, conducted in the Antarctic summer, also requires standby icebreaker support for backup in the event the primary vessel cannot complete the mission.  Thule Air Base Resupply and Polar Region Freedom of Navigation Transits. Provide vessel escort operations in support of the Military Sealift Command’s Operation Pacer Goose; then complete any Freedom of Navigation exercises in the region. In addition, the joint Naval Operations Concept establishes the following mission requirements:  Assured access and assertion of U.S. policy in the Polar Regions. The current demand for this mission requires continuous icebreaker presence in both Polar Regions. Considering these missions, the analysis yields the following findings:  The Coast Guard requires three heavy and three medium icebreakers to fulfill its statutory missions. These icebreakers are necessary to (1) satisfy Arctic winter and transition season demands and (2) provide sufficient capacity to also execute summer missions. Single-crewed icebreakers have sufficient capacity for all current and expected statutory missions. Multiple crewing provides no advantage because the number of icebreakers required is driven by winter and shoulder season requirements. Future use of multiple or augmented crews could provide additional capacity needed to absorb mission growth.  The Coast Guard requires six heavy and four medium icebreakers to fulfill its statutory missions and maintain the continuous presence requirements of the Naval Operations Concept. Consistent with current practice, these icebreakers are single-crewed and homeported in Seattle Washington.  Applying crewing and home porting alternatives reduces the overall requirement to four heavy and two medium icebreakers. This assessment of nonmaterial solutions shows that the reduced number of icebreakers can be achieved by having all vessels operate with multiple crews and two of the heavy icebreakers homeporting in the Southern Hemisphere. Leasing was also considered as a nonmaterial solution. While there is no dispute that the Coast Guard’s polar icebreaker fleet is in need of recapitalization, the decision to acquire this capability through purchase of new vessels, reconstruction of existing ships, or commercial lease of suitable vessels must be resolved to provide the best value to the taxpayer. The multi-mission nature of the Coast Guard may provide opportunities to conduct some subset of its missions with non government-owned vessels. However, serious consideration must be given to the fact that the inherently governmental missions of the Coast Guard must be performed using government-owned and operated vessels. An interpretation of the national policy is needed to determine the resource level that best supports the nation’s interests.... Congressional Research Service 41 Coast Guard Polar Security Cutter (Polar Icebreaker) Program The existing icebreaker capacity, two inoperative heavy icebreakers and an operational medium icebreaker, does not represent a viable capability to the federal government. The time needed to augment this capability is on the order of 10 years. At that point, around 2020, the heavy icebreaking capability bridging strategy expires. 60 At a July 27, 2011, hearing on U.S. economic interests in the Arctic before the Oceans, Atmosphere, Fisheries, and Coast Guard subcommittee of the Senate Commerce, Science, and Transportation Committee, the following exchange occurred: SENATOR OLYMPIA J. SNOWE: On the high latitude study, do you agree with—and those—I would like to also hear from you, Admiral Titley, as well, on these requirements in terms of Coast Guard vessels as I understand it, they want to have—I guess, it was a three medium ice breakers. Am in correct in saying that? Three medium ice breakers. ADMIRAL ROBERT PAPP, COMMANDANT OF THE COAST GUARD: I agree with the mission analysis and as you look at the requirements for the things that we might do up there, if it is in the nation’s interest, it identifies a minimum requirement for three heavy ice breakers and three medium ice breakers and then if you want a persistent presence up there, it would require—and also doing things such as breaking out (inaudible) and other responsibilities, then it would take up to a maximum six heavy and four medium. SNOWE: Right. Do you agree with that? PAPP: If we were to be charged with carrying out those full responsibilities, yes, ma’am. Those are the numbers that you would need to do it. SNOWE: Admiral Titley, how would you respond to the high latitude study and has the Navy conducted its own assessment of its capability? REAR ADMIRAL DAVID TITLEY, OCEANORGRAPHER AND NAVIGATOR OF THE NAVY: Ma’am, we are in the process right now of conducting what we call a capabilities based assessment that will be out in the summer of this year. We are getting ready to finish that—the Coast Guard has been a key component of the Navy’s task force on climate change, literally since day one when the Chief of Naval Operations set this up, that morning, we had the Coast Guard invited as a member of our executive steering committee. So we have been working very closely with the Coast Guard, with the Department of Homeland Security, and I think Admiral Papp—said it best as far as the specific comments on the high latitude study but we have been working very closely with the Coast Guard. 61 January 2011 DHS Office of Inspector General Report A January 2011 report on the Coast Guard’s polar icebreakers from the DHS Office of the Inspector General stated the following: The Coast Guard does not have the necessary budgetary control over its [polar] icebreakers, nor does it have a sufficient number of icebreakers to accomplish its missions in the Polar Regions. Currently, the Coast Guard has only one operational [polar] icebreaker [i.e., Healy], making it necessary for the United States to contract with foreign nations to perform scientific, logistical, and supply activities. Without the necessary budgetary control and a sufficient number of icebreaking assets, the Coast Guard will not have the capability to perform all of its missions, will lose critical icebreaking expertise, and may 60 61 United States Coast Guard High Latitude Region Mission Analysis Capstone Summary, July 2010, pp. 10-13, 15. Source: Transcript of hearing. Congressional Research Service 42 Coast Guard Polar Security Cutter (Polar Icebreaker) Program be beholden to foreign nations to perform its statutory missions. The Coast Guard should improve its strategic approach to ensure that it has the long-term icebreaker capabilities needed to support Coast Guard missions and other national interests in the Arctic and Antarctic regions.62 Regarding current polar icebreaking capabilities for performing Arctic missions, the report states the following: The Coast Guard’s icebreaking resources are unlikely to meet future demands. [The table below] outlines the missions that Coast Guard is unable to meet in the Arctic with its current icebreaking resources. Arctic Missions Not Being Met Requesting Agency United States Coast Guard Missions Not Being Met —Fisheries enforcement in Bering Sea to prevent foreign fishing in U.S. waters and overfishing —Capability to conduct search and rescue in Beaufort Sea for cruise line and natural resource exploration ships —Future missions not anticipated to be met: 2010 Arctic Winter Science Deployment NASA Winter access to the Arctic to conduct oceanography and study Arctic currents and how they relate to regional ice cover, climate, and biology NOAA and NSF Winter research Department of Defense Assured access to ice-impacted waters through a persistent icebreaker presence in the Arctic and Antarctic63 The report also states the following: Should the Coast Guard not obtain funding for new icebreakers or major service life extensions for its existing icebreakers with sufficient lead-time, the United States will have no heavy icebreaking capability beyond 2020 and no polar icebreaking capability of any kind by 2029. Without the continued use of icebreakers, the United States will lose its ability to maintain a presence in the Polar Regions, the Coast Guard’s expertise to perform ice operations will continue to diminish, and missions will continue to go unmet. 64 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance, Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 1 (Executive Summary). Report accessed September 21, 2011, at https://www.oig.dhs.gov/assets/Mgmt/OIG_11-31_Jan11.pdf. 63 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance, Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 9. 64 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance, Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 10. 62 Congressional Research Service 43 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Regarding current polar icebreaking capabilities for performing Antarctic missions, the report states the following: The Coast Guard needs additional icebreakers to accomplish its missions in the Antarctic. The Coast Guard has performed the McMurdo Station resupply in Antarctica for decades, but with increasing difficulty in recent years. The Coast Guard’s two heavy-duty icebreakers [i.e., Polar Star and Polar Sea] are at the end of their service lives, and have become less reliable and increasingly costly to keep in service.... In recent years, the Coast Guard has found that ice conditions in the Antarctic have become more challenging for the resupply of McMurdo Station. The extreme ice conditions have necessitated the use of foreign vessels to perform the McMurdo break-in.... As ice conditions continue to change around the Antarctic, two icebreakers are needed for the McMurdo break-in and resupply mission. Typically, one icebreaker performs the breakin and the other remains on standby. Should the first ship become stuck in the ice or should the ice be too thick for one icebreaker to complete the mission, the Coast Guard deploys the ship on standby. Since the Polar Sea and Polar Star are not currently in service, the Coast Guard has no icebreakers capable of performing this mission. [The table below] outlines the missions that will not be met without operational heavy-duty icebreakers. Arctic Missions Not Being Met Requesting Agency Missions Not Being Met NSF Missions not anticipated to be met: 2010-2011 Operation Deep Freeze – McMurdo Station Resupply Department of State Additional inspections of foreign facilities in Antarctica to enforce the Antarctic Treaty and ensure facilities’ environment compliance 65 The report’s conclusion and recommendations were as follows: Conclusion With an aging fleet of three icebreakers, one operational and two beyond their intended 30year service life, the Coast Guard is at a critical crossroads in its Polar Icebreaker Maintenance, Upgrade, and Acquisition Program. It must clarify its mission requirements, and if the current mission requirements remain, the Coast Guard must determine the best method for meeting these requirements in the short and long term. Recommendations We recommend that the Assistant Commandant for Marine Safety, Security, and Stewardship: Recommendation #1: Request budgetary authority for the operation, maintenance, and upgrade of its icebreakers. Recommendation #2: In coordination with the Department of Homeland Security, request clarification from Congress to determine whether Arctic missions should be performed by Coast Guard assets or contracted vessels. Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance, Upgrade, and Acquisition Program, OIG-11-31, January 2011, pp. 10-11. 65 Congressional Research Service 44 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Recommendation #3: In coordination with the Department of Homeland Security, request clarification from Congress to determine whether Antarctic missions should be performed by Coast Guard assets or contracted vessels. Recommendation #4: Conduct the necessary analysis to determine whether the Coast Guard should replace or perform service-life extensions on its two existing heavy-duty icebreaking ships. Recommendation #5: Request appropriations necessary to meet mission requirements in the Arctic and Antarctic.66 The report states that The Coast Guard concurred with all five of the recommendations and is initiating corrective actions. We consider the recommendations open and unresolved. The Coast Guard provided information on some of its ongoing projects that will address the program needs identified in the report.67 2010 U.S. Arctic Research Commission Report A May 2010 report from the U.S. Arctic Research Commission (USARC) on goals and objectives for Arctic research for 2009-2010 stated the following: To have an effective Arctic research program, the United States must invest in human capital, research platforms, and infrastructure, including new polar class icebreakers, and sustained sea, air, land, space, and social observing systems.... The Commission urges the President and Congress to commit to replacing the nation’s two polar class icebreakers. 68 2007 National Research Council Report A 2007 National Research Council (NRC) report, Polar Icebreakers in a Changing World: An Assessment of U.S. Needs, assessed roles and future needs for Coast Guard polar icebreakers.69 The study was required by report language accompanying the FY2005 DHS appropriations act (H.R. 4567/P.L. 108-334).70 The study was completed in 2006 and published in 2007. Some Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance, Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 12. 67 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance, Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 13. 68 U.S. Arctic Research Commission, Report on Goals and Objectives for Arctic Research 2009-2010, May 2010, p. 4. Accessed online December 5, 2011, at https://storage.googleapis.com/arcticgov-static/publications/goals/ usarc_goals_2009-10.pdf. 69 National Research Council, Polar Icebreakers in a Changing World, An Assessment of U.S. Needs, Washington, 2007, 122 pp. 70 H.R. 4567/P.L. 108-334 of October 18, 2004. The related Senate bill was S. 2537. The Senate report on S. 2537 (S.Rept. 108-280 of June 17, 2004) stated the following: The Committee expects the Commandant to enter into an arrangement with the National Academy of Sciences to conduct a comprehensive study of the role of Coast Guard icebreakers in supporting United States operations in the Antarctic and the Arctic. The study should include different scenarios for continuing those operations including service life extension or replacement of existing Coast Guard icebreakers and alternative methods that do not use Coast Guard icebreakers. The study should also address changes in the roles and missions of Coast Guard icebreakers in support of future marine operations in the Arctic that may develop due to environmental change, including the amount and kind of icebreaking support that may be required in the future to support marine operations in the Northern Sea Route and the Northwest Passage; the suitability of the Polar Class icebreakers for these new roles; and appropriate changes in existing laws governing Coast Guard 66 Congressional Research Service 45 Coast Guard Polar Security Cutter (Polar Icebreaker) Program sources refer to the study as the 2006 NRC report. The report made the following conclusions and recommendations: Based on the current and future needs for icebreaking capabilities, the [study] committee concludes that the nation continues to require a polar icebreaking fleet that includes a minimum of three multimission ships [like the Coast Guard’s three current polar icebreakers] and one single-mission [research] ship [like Palmer]. The committee finds that although the demand for icebreaking capability is predicted to increase, a fleet of three multimission and one single-mission icebreakers can meet the nation’s future polar icebreaking needs through the application of the latest technology, creative crewing models, wise management of ice conditions, and more efficient use of the icebreaker fleet and other assets. The nation should immediately begin to program, design, and construct two new polar icebreakers to replace the POLAR STAR and POLAR SEA. Building only one new polar icebreaker is insufficient for several reasons. First, a single ship cannot be in more than one location at a time. No matter how technologically advanced or efficiently operated, a single polar icebreaker can operate in the polar regions for only a portion of any year. An icebreaker requires regular maintenance and technical support from shipyards and industrial facilities, must reprovision regularly, and has to effect periodic crew changeouts. A single icebreaker, therefore, could not meet any reasonable standard of active and influential presence and reliable, at-will access throughout the polar regions. A second consideration is the potential risk of failure in the harsh conditions of polar operations. Despite their intrinsic robustness, damage and system failure are always a risk and the U.S. fleet must have enough depth to provide backup assistance. Having only a single icebreaker would necessarily require the ship to accept a more conservative operating profile, avoiding more challenging ice conditions because reliable assistance would not be available. A second capable icebreaker, either operating elsewhere or in homeport, would provide ensured backup assistance and allow for more robust operations by the other ship. From a strategic, longer-term perspective, two new Polar class icebreakers will far better position the nation for the increasing challenges emerging in both polar regions. A second new ship would allow the U.S. Coast Guard to reestablish an active patrol presence in U.S. waters north of Alaska to meet statutory responsibilities that will inevitably derive from increased human activity, economic development, and environmental change. It would allow response to emergencies such as search-and-rescue cases, pollution incidents, and assistance to ships threatened with grounding or damage by ice. Moreover, a second new ship will leverage the possibilities for simultaneous operations in widely disparate geographic areas (e.g., concurrent operations in the Arctic and Antarctic), provide more flexibility for conducting Antarctic logistics (as either the primary or the secondary ship for the McMurdo break-in), allow safer multiple-ship operations in the most demanding ice conditions, and increase opportunities for international expeditions. Finally, an up-front decision to build two new polar icebreakers will allow economies in the design and construction process and provide a predictable cost reduction for the second ship.... The [study] committee finds that both operations and maintenance of the polar icebreaker fleet have been underfunded for many years, and the capabilities of the nation’s icebreaking icebreaking operations and the potential for new operating regimes. The study should be submitted to the Committee no later than September 30, 2005. The conference report on H.R. 4567 (H.Rept. 108-774 of October 9, 2004) stated the following: As discussed in the Senate report and the Coast Guard authorization bill for fiscal year 2005, the conferees require the National Academy of Sciences to study the role of Coast Guard icebreakers. The earlier House report on H.R. 4567 (H.Rept. 108-541 of June 15, 2004) contained language directing a similar report from the Coast Guard rather than the National Academies. (See the passage in the House report under the header “Icebreaking.”) Congressional Research Service 46 Coast Guard Polar Security Cutter (Polar Icebreaker) Program fleet have diminished substantially. Deferred long-term maintenance and failure to execute a plan for replacement or refurbishment of the nation’s icebreaking ships have placed national interests in the polar regions at risk. The nation needs the capability to operate in both polar regions reliably and at will. Specifically, the committee recommends the following:  The United States should continue to project an active and influential presence in the Arctic to support its interests. This requires U.S. government polar icebreaking capability to ensure year-round access throughout the region.  The United States should continue to project an active and influential presence in the Antarctic to support its interests. The nation should reliably control sufficient icebreaking capability to break a channel into and ensure the maritime resupply of McMurdo Station.  The United States should maintain leadership in polar research. This requires icebreaking capability to provide access to the deep Arctic and the ice-covered waters of the Antarctic.  National interests in the polar regions require that the United States immediately program, budget, design, and construct two new polar icebreakers to be operated by the U.S. Coast Guard.  To provide continuity of U.S. icebreaking capabilities, the POLAR SEA should remain mission capable and the POLAR STAR should remain available for reactivation until the new polar icebreakers enter service.  The U.S. Coast Guard should be provided sufficient operations and maintenance budget to support an increased, regular, and influential presence in the Arctic. Other agencies should reimburse incremental costs associated with directed mission tasking.  Polar icebreakers are essential instruments of U.S. national policy in the changing polar regions. To ensure adequate national icebreaking capability into the future, a Presidential Decision Directive should be issued to clearly align agency responsibilities and budgetary authorities. 71 The Coast Guard stated in 2008 that it “generally supports” the NRC report, and that the Coast Guard “is working closely with interagency partners to determine a way forward with national polar policy that identifies broad U.S. interests and priorities in the Arctic and Antarctic that will ensure adequate maritime presence to further these interests. Identification and prioritization of U.S. national interests in these regions should drive development of associated USCG [U.S. Coast Guard] capability and resource requirements.” The Coast Guard also stated the following: “Until those broad U.S. interests and priorities are identified, the current USG [U.S. Government] polar icebreaking fleet should be maintained in an operational status.”72 71 National Research Council, Polar Icebreakers in a Changing World, An Assessment of U.S. Needs, Washington, 2007, pp. 2-3. 72 Coast Guard point paper provided to CRS on February 12, 2008, and dated with the same date, providing answers to questions from CRS concerning polar icebreaker modernization. Congressional Research Service 47 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Appendix C. PSC Program Funding This appendix presents additional background information on funding for the PSC program. Summary of Funding in FY2013-FY2021 Budget Submissions Table C-1 shows requested and projected funding for the PSC program in the Coast Guard’s budget submissions from the initiation of the PSC program in the FY2013 submission through the FY2021 submission. Table C-1. Funding for PSC Program in FY2013-FY2021 Budget Submissions (millions of then-year dollars) Budget FY 13 FY 14 FY 15 FY 16 FY 17 FY13 8 120 380 270 82 2 8 100 20 100 6 4 100 20 100 4 10 2 100 50 150 0 50 150 430 19 50 150 430 300 750 125 385 345 200 35 385 345 200 350 555 n/a n/a n/a FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY 18 FY 19 FY 20 FY 21 FY 22 FY 23 FY 24 FY 25 5-year total 860 230 230 166 780 949 1,805 1,315 n/a n/a Source: Table prepared by CRS based on Coast Guard FY2013-FY2021 budget submissions. n/a means not available. Notes: For each line in the table, the first figure shown (e.g., $8 million in the case of the FY2013 budget) is the amount of funding that was requested for that fiscal year. Actual funding figures for FY2013-FY2021 are different. The reduction in programmed five-year funding for a new polar icebreaker during the FY2014FY2016 budget submissions shown in Table C-1 appears to have been related to the substantial reduction in the annual funding levels in the Coast Guard’s Procurement, Construction, and Improvements (PC&I) account73 in those budget submission that is shown in Table C-2. The Coast Guard testified in 2015 that if annual funding levels in the PC&I account were not increased from the reduced levels in those budget submissions, the icebreaker would be, essentially, an unfunded requirement. For example, at an April 28, 2015, hearing on Coast Guard resources and priorities before the Oceans, Atmosphere, Fisheries, and Coast Guard subcommittee of the Senate Commerce, Science, and Transportation Committee, Admiral Paul Zukunft, the then-Commandant of the Coast Guard, testified that by reactivating Polar Star, we have purchased up to 10 years of decision space to recapitalize our ice-breaking fleet. Two of those years have expired. And while I'm exploring several options to reconstitute our nation’s fleet of icebreakers, I will need topline relief [i.e., an increase] in my acquisition budget to make this requirement a reality.74 73 74 Prior to FY2019, the PC&I account was called the Acquisition, Construction, and Improvements (AC&I) account. Source: Transcript of hearing. Congressional Research Service 48 Table C-2. Funding in Procurement, Construction, and Improvements (PC&I) Account (millions of dollars, rounded to nearest tenth) Budget FY13 FY14 FY15 FY16 FY17 FY13 1,217.3 1,429.5 1,619.9 1,643.8 1,722.0 951.1 1,195.7 901.0 1,024.8 1,030.3 1,084.2 1,103.0 1,128.9 1,180.4 1,228.7 1,017.3 1,125.3 1,255.7 1,201.0 1,294.6 1,136.8 1,259.6 1,339.9 1,560.5 1,840.8 1,203.7 1,360.9 1,602.7 1,810.6 1,687.5 1,886.8 1,473.0 1,679.8 1,555.5 1,698.5 1,234.7 1,679.8 1,555.5 1,698.5 1,737.0 1,637.1 n/a n/a n/a FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 1,526.5 1,020.6 1,145.0 1,178.8 1,427.5 1,533.1 1,658.8 1,581.1 n/a Source: Table prepared by CRS based on Coast Guard FY2013-FY2020 budget submissions. Prior to FY2019, the PC&I account was called the Acquisition, Construction, and Improvements (AC&I) account. n/a means not available. CRS-49 Avg. n/a Coast Guard Polar Security Cutter (Polar Icebreaker) Program For additional discussion of the issue of the funding level of the Procurement, Construction, and Improvements (PC&I) account, see Appendix D. Below are some additional details on each of the budget submissions since the FY2013 submission. FY2013 Submission The Administration’s FY2013 budget submission initiated a new project for the design and construction of a new polar icebreaker, and included $860 million over five years for the acquisition of the ship (Table C-1)—enough or almost enough to fully fund the acquisition of a new polar icebreaker. (Any remaining needed funding might have been projected for FY2018 and perhaps also FY2019, which were beyond the five-year window of the FY2013 budget submission.) The submission stated that DHS anticipated awarding a construction contract for the ship “within the next five years” (i.e., by FY2018) and taking delivery on the ship “within a decade” (i.e., by 2023).75 FY2014 Submission The Administration’s FY2014 budget submission reduced the five-year funding for a new polar icebreaker to $230 million (Table C-1)—a 73% reduction from the figure in the FY2013 budget submission—but still stated that DHS anticipated awarding a construction contract for the ship “within the next four years” (i.e., by FY2018).76 FY2015 Submission The Administration’s FY2015 budget submission maintained five-year funding for a new polar icebreaker at $230 million (Table C-1), but did not state when a construction contract for the ship might be awarded, creating uncertainty about the timing of the project.77 FY2016 Submission The Administration’s FY2016 budget submission, submitted to Congress in February 2015, reduced five-year funding for a new polar icebreaker further, to $166 million (Table C-1)—an 81% reduction from the figure in the FY2013 budget submission—and again did not state when a construction contract for the ship might be awarded, maintaining the uncertainty about the timing of the project.78 On September 1, 2015, the White House issued a fact sheet in conjunction with a visit to Alaska by President Obama indicating that the Administration, in its own internal planning, had at some point over the past two years deferred acquisition of a new polar icebreaker to FY2022, but that this had been changed to FY2020.79 The newly announced construction start date of FY2020 was 75 U.S. Department of Homeland Security, Annual Performance Report, Fiscal Years 2011-2013, p. CG-AC&I-40 (PDF page 1,777 of 3,134). 76 Department of Homeland Security, United States Coast Guard, Fiscal Year 2014 Congressional Justification, p. CGAC&I-32 (PDF page 204 of 403). 77 Department of Homeland Security, United States Coast Guard, Fiscal Year 2015, Congressional Justification, p. CGAC&I-42 (PDF page 196 of 474). 78 Department of Homeland Security, United States Coast Guard, Fiscal Year 2016 Congressional Justification, p. CGAC&I-36 (PDF page 202 of 518). 79 The White House, “Fact Sheet: President Obama Announces New Investments to Enhance Safety and Security in the Changing Arctic,” September 1, 2015, accessed September 2, 2015, at https://www.whitehouse.gov/the-press-office/ Congressional Research Service 50 Coast Guard Polar Security Cutter (Polar Icebreaker) Program a two-year acceleration from the previously unpublicized date of FY2022, and a two-year deferral from the FY2018 date implied in the FY2013 and FY2014 budget submissions. The fact sheet states that the Administration will also “begin planning for construction of additional icebreakers” beyond the one that the Obama Administration proposed to begin building in FY2020. On January 13, 2016, the Coast Guard announced that it intended to hold an industry day for the PSC program, followed by one-on-one meetings between the Coast Guard and prospective shipbuilders and ship designers, as a part of the Coast Guard’s ongoing market research for the program.80 The industry day was held on March 18, 2016, and the one-on-one meetings between the Coast Guard and industry officials were scheduled for March 28-31, with industry feedback to be submitted to the Coast Guard by April 5, 2016.81 FY2017 Submission The Coast Guard’s proposed FY2017 budget requested $150 million in procurement funding for a new polar icebreaker. The figure of $150 million included $147.6 million in the polar icebreaker line of the Coast Guard’s Acquisition, Construction, and Improvements (AC&I) account, and $2.4 million that was embedded in the personnel and management line in the AC&I account.82 The Coast Guard’s FY2017-FY2021 five-year Capital Investment Plan (CIP) included a total of $780 million in procurement funding for a new polar icebreaker. As shown in Table C-1, the $150 million requested for FY2017 was the first major increment of procurement funding requested (not just projected for a future fiscal year) for a new polar icebreaker. 2015/09/01/fact-sheet-president-obama-announces-new-investments-enhance-safety-and. Regarding icebreakers, the fact sheet states the following: Accelerating the acquisition of new Coast Guard icebreakers. After World War II, the United States Coast Guard had seven icebreakers in its fleet—four under the U.S. Navy and three under the U.S. Coast Guard. Today, the United States technically has three icebreakers in its fleet—all under the command of the U.S. Coast Guard. However, when age and reliability are taken into account, the fleet is down to the equivalent of two fully functional icebreakers and only one heavy-duty icebreaker. Russia, on the other hand, has forty icebreakers and another eleven planned or under construction. The growth of human activity in the Arctic region will require highly engaged stewardship to maintain the open seas necessary for global commerce and scientific research, allow for search and rescue activities, and provide for regional peace and stability. Accordingly, meeting these challenges requires the United States to develop and maintain capacity for year-round access to greater expanses within polar regions. That is why the Administration will propose to accelerate acquisition of a replacement heavy icebreaker to 2020 from 2022, begin planning for construction of additional icebreakers, and call on Congress to work with the Administration to provide sufficient resources to fund these critical investments. These heavy icebreakers will ensure that the United States can meet our national interests, protect and manage our natural resources, and strengthen our international, state, local, and tribal relationships. 80 “USCG Polar Class Icebreaker Replacement Program,” accessed January 15, 2016, at https://www.fbo.gov/index?s= opportunity&mode=form&id=a778c49349c443d2658666e19cc100e9&tab=core&tabmode=list&=. 81 “Heavy Polar Icebreaker Industry Engagement Activities,” accessed April 4, 2016, at http://www.uscg.mil/ ACQUISITION/icebreaker/Industry_Day_031816.asp. 82 Department of Homeland Security, United States Coast Guard, Fiscal Year 2017 Congressional Justification, pp. CG-AC&I-28 and CG-AC&I-47 (PDF pages 170 and 189 of 407). Congressional Research Service 51 Coast Guard Polar Security Cutter (Polar Icebreaker) Program FY2018 Submission The Coast Guard’s proposed FY2018 budget requested $19 million in procurement funding for a new polar icebreaker and includes a total of $949 million over the five-year period FY2018FY2022. The Coast Guard states that This request supports activities to complete and release a Request for Proposal (RFP) for Detail Design and Construction in FY 2018. Specifically, this funding supports programwide activities including open water and ice tank model testing; review of Industry Studies contract deliverables; Integrated Program Office (IPO) and Ship Design Team (SDT) support; logistics and integration development for government furnished information and equipment; and additional modeling efforts to inform the evaluation and source selection process for the Detail Design & Construction RFP.... Currently, the Program is maturing the system specification, developing the RFP for Detail Design & Construction, and completing required documentation to transition to the “Obtain” phase - planned for early FY 2018. In July 2016, the Coast Guard established an Integrated Program Office with the Navy to continue efforts to accelerate the construction timeline and leverage the expertise and best practices from shipbuilding programs in both services. Based on this collaboration and lessons learned by the Navy, the Program was able to significantly mature the acquisition approach with the incorporation of Industry Studies to identify solutions to minimize cost, schedule, production and technology risks. Industry Studies are focusing on leveraging industry perspectives, existing vessel designs, and use of mature technology to inform the iterative development of the Heavy Polar Icebreaker system specification. Future “Obtain” phase activities include award of a contract for Detail Design & Construction for the heavy polar icebreaker.83 FY2019 Submission The Coast Guard’s proposed FY2018 budget requested $750 million in procurement funding for the PSC program and included a total of $1,805 million for the program over the five-year period FY2019-FY2023. The request for $750 million for the PSC program was a late change to the FY2019 budget that is not reflected in Coast Guard FY2019 budget-justification documents that were printed prior to the change. In those earlier documents, the amount of funding requested for FY2019 shows as $30 million rather than $750 million, and the total amount of funding requested in the Coast Guard’s PC&I account was correspondingly $720 million less than the figure of $1,886.8 million shown in Table C-2. FY2020 Submission The Coast Guard’s proposed FY2020 budget requested $35 million in procurement funding for the PSC program, which was enough to cover the PSC program’s FY2020 government programmanagement costs, and included a total of $1,315 million for the program over the five-year period FY2020-FY2024. FY2021 Submission The Coast Guard’s proposed FY2021 budget requests $555 million in procurement funding for the PSC program. It also proposes a rescission of $70 million in FY2020 funding that Congress had provided for the procurement of long lead time materials (LLTM) for a 12th National Security 83 Department of Homeland Security, U.S. Coast Guard, Fiscal Year 2018 Congressional Justification, undated but released May 2017, pp. AC&I-50 and AC&I-51. Congressional Research Service 52 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Cutter (NSC), with the intent of reprogramming that funding to the PSC program. The Coast Guard states that its proposed FY2021 budget, if approved by Congress, would fully fund the second PSC. Congressional Research Service 53 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Appendix D. Funding Level in PC&I Account This appendix presents additional discussion of the funding level of the Coast Guard’s Procurement, Construction, and Improvements (PC&I) account.84 Overview The Coast Guard has testified that funding the PC&I account at a level of about $1 billion to $1.2 billion per year—the approximate average annual funding level programmed in the FY2014, FY2015, and FY2016 budget submissions, as shown in Table C-2—would make it difficult to fund various Coast Guard acquisition projects, including a new polar icebreaker and improvements to Coast Guard shore installations. Coast Guard plans call for procuring Offshore Patrol Cutters (OPCs) at an eventual rate of two per year.85 If each OPC costs roughly $400 million, procuring two OPCs per year in an PC&I account of about $1 billion to $1.2 billion per year would leave about $200 million to $400 million per year for all other PC&I-funded programs. Since 2017, Coast Guard officials have been stating more regularly what they stated only infrequently in earlier years: that executing the Coast Guard’s various acquisition programs fully and on a timely basis would require the PC&I account to be funded in coming years at a level of about $2 billion per year. Statements from Coast Guard officials on this issue in past years have sometimes put this figure as high as about $2.5 billion per year. Using Past PC&I Funding Levels as a Guide for Future PC&I Funding Levels In assessing future funding levels for executive branch agencies, a common practice is to assume or predict that the figure in coming years will likely be close to where it has been in previous years. While this method can be of analytical and planning value, for an agency like the Coast Guard, which goes through periods with less acquisition of major platforms and periods with more acquisition of major platforms, this approach might not always be the best approach, at least for the PC&I account. More important, in relation to maintaining Congress’s status as a co-equal branch of government, including the preservation and use of congressional powers and prerogatives, an analysis that assumes or predicts that future funding levels will resemble past funding levels can encourage an artificially narrow view of congressional options regarding future funding levels, depriving Congress of agency in the exercise of its constitutional power to set funding levels and determine the composition of federal spending. Past Coast Guard Statements About Required PC&I Funding Level At an October 4, 2011, hearing on the Coast Guard’s major acquisition programs before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee, the following exchange occurred: 84 Prior to FY2019, the PC&I account was called the Acquisition, Construction, and Improvements (AC&I) account. For more on the OPC program, see CRS Report R42567, Coast Guard Cutter Procurement: Background and Issues for Congress, by Ronald O'Rourke. 85 Congressional Research Service 54 Coast Guard Polar Security Cutter (Polar Icebreaker) Program REPRESENATIVE FRANK LOBIONDO: Can you give us your take on what percentage of value must be invested each year to maintain current levels of effort and to allow the Coast Guard to fully carry out its missions? ADMIRAL ROBERT J. PAPP, COMMANDANT OF THE COAST GUARD: I think I can, Mr. Chairman. Actually, in discussions and looking at our budget—and I’ll give you rough numbers here, what we do now is we have to live within the constraints that we’ve been averaging about $1.4 billion in acquisition money each year. If you look at our complete portfolio, the things that we’d like to do, when you look at the shore infrastructure that needs to be taken care of, when you look at renovating our smaller icebreakers and other ships and aircraft that we have, we’ve done some rough estimates that it would really take close to about $2.5 billion a year, if we were to do all the things that we would like to do to sustain our capital plant. So I’m just like any other head of any other agency here, as that the end of the day, we’re given a top line and we have to make choices and tradeoffs and basically, my tradeoffs boil down to sustaining frontline operations balancing that, we’re trying to recapitalize the Coast Guard and there’s where the break is and where we have to define our spending. 86 An April 18, 2012, blog entry stated the following: If the Coast Guard capital expenditure budget remains unchanged at less than $1.5 billion annually in the coming years, it will result in a service in possession of only 70 percent of the assets it possesses today, said Coast Guard Rear Adm. Mark Butt. Butt, who spoke April 17 [2012] at [a] panel [discussion] during the Navy League Sea Air Space conference in National Harbor, Md., echoed Coast Guard Commandant Robert Papp in stating that the service really needs around $2.5 billion annually for procurement. 87 At a May 9, 2012, hearing on the Coast Guard’s proposed FY2013 budget before the Homeland Security subcommittee of the Senate Appropriations Committee, Admiral Papp testified, “I’ve gone on record saying that I think the Coast Guard needs closer to $2 billion dollars a year [in procurement funding] to recapitalize—[to] do proper recapitalization.”88 At a May 14, 2013, hearing on the Coast Guard’s proposed FY2014 budget before the Homeland Security Subcommittee of the Senate Appropriations Committee, Admiral Papp stated the following regarding the difference between having about $1.0 billion per year rather than about $1.5 billion per year in the PC&I account: 86 Source: Transcript of hearing. David Perera, “The Coast Guard Is Shrinking,” FierceHomelandSecurity.com, April 18, 2012, accessed July 20, 2012, at http://www.fiercehomelandsecurity.com/story/coast-guard-shrinking/2012-04-18. 88 Source: transcript of hearing. Papp may have been referring to remarks he made to the press before giving his annual state of the Coast Guard speech on February 23, 2012, in which reportedly stated that the Coast Guard would require about $2 billion per year in procurement funding to fully replace its current assets. (See Adam Benson, “Coast Guard Cutbacks Will Cost 1,000 Jobs,” Norwich Bulletin, February 23, 2012, accessed May 31, 2012, at http://www.norwichbulletin.com/x1138492141/Coast-Guard-cutbacks-will-cost-1-000-jobs. See also “Coast Guard Leader Calls For More Ships,” MilitaryFeed.com, February 24, 2012, accessed May 31, 2012, at http://militaryfeed.com/coast-guard-leader-calls-for-more-ships-5/; Associated Press, “Coast Guard Commandant Calls for New Ships,” TheLog.com, March 10, 2012, accessed May 31, 2012, at http://www.thelog.com/SNW/Article/CoastGuard-Commandant-Calls-for-New-Ships-to-Replace-Aging-Fleet; Mickey McCarter, “Congress Poised to Give Coast Guard More Money Than Requested for FY 2013,” HSToday.us, May 10, 2012, accessed May 31, 2012, at http://www.hstoday.us/focused-topics/customs-immigration/single-article-page/congress-poised-to-give-coast-guardmore-money-than-requested-for-fy-2013.html.) See also “Interview, Adm. Robert Papp, US Coast Guard Commandant,” Defense News, November 11, 2013: 30. 87 Congressional Research Service 55 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Well, Madam Chairman, $500 million—a half a billion dollars—is real money for the Coast Guard. So, clearly, we had $1.5 billion in the [FY]13 budget. It doesn't get everything I would like, but it—it gave us a good start, and it sustained a number of projects that are very important to us. When we go down to the $1 billion level this year, it gets my highest priorities in there, but we have to either terminate or reduce to minimum order quantities for all the other projects that we have going. If we're going to stay with our program of record, things that have been documented that we need for our service, we're going to have to just stretch everything out to the right. And when we do that, you cannot order in economic order quantities. It defers the purchase. Ship builders, aircraft companies—they have to figure in their costs, and it inevitably raises the cost when you're ordering them in smaller quantities and pushing it off to the right. Plus, it almost creates a death spiral for the Coast Guard because we are forced to sustain older assets—older ships and older aircraft—which ultimately cost us more money, so it eats into our operating funds, as well, as we try to sustain these older things. So, we'll do the best we can within the budget. And the president and the secretary have addressed my highest priorities, and we'll just continue to go on the—on an annual basis seeing what we can wedge into the budget to keep the other projects going. 89 At a March 12, 2014, hearing on the Coast Guard’s proposed FY2015 budget before the Homeland Security subcommittee of the House Appropriations Committee, Admiral Papp stated the following: Well, that’s what we've been struggling with, as we deal with the five-year plan, the capital investment plan, is showing how we are able to do that. And it will be a challenge, particularly if it sticks at around $1 billion [per year]. As I've said publicly, and actually, I said we could probably—I've stated publicly before that we could probably construct comfortably at about 1.5 billion [dollars] a year. But if we were to take care of all the Coast Guard’s projects that are out there, including shore infrastructure that that fleet that takes care of the Yemen [sic: inland] waters is approaching 50 years of age, as well, but I have no replacement plan in sight for them because we simply can't afford it. Plus, we need at some point to build a polar icebreaker. Darn tough to do all that stuff when you're pushing down closer to 1 billion [dollars per year], instead of 2 billion [dollars per year]. As I said, we could fit most of that in at about the 1.5 billion [dollars per year] level, but the projections don't call for that. So we are scrubbing the numbers as best we can. 90 At a March 24, 2015, hearing on the Coast Guard’s proposed FY2016 budget before the Homeland Security subcommittee of the House Appropriations Committee, Admiral Paul Zukunft, Admiral Papp’s successor as Commandant of the Coast Guard, stated the following: I look back to better years in our acquisition budget when we had a—an acquisition budget of—of $1.5 billion. That allows me to move these programs along at a much more rapid pace and, the quicker I can build these at full-rate production, the less cost it is in the long run as well. But there’s an urgent need for me to be able to deliver these platforms in a timely and also in an affordable manner. But to at least have a reliable and a predictable acquisition budget would make our work in the Coast Guard much easier. But when we see variances of—of 30, 40% over a period of three or four years, and not knowing what the Budget Control Act may have in store for us going on, yes, we are treading water now 89 90 Transcript of hearing. The remarks were made in response to a question from Sen. Mary Landrieu. Transcript of hearing. Congressional Research Service 56 Coast Guard Polar Security Cutter (Polar Icebreaker) Program but any further reductions, and now I am—I am beyond asking for help. We are taking on water.91 An April 13, 2017, press report states the following (emphasis added): [Then-]Coast Guard Commandant Adm. Paul Zukunft on Wednesday [April 12] said that for the Coast Guard to sustain its recapitalization plans and operations the service needs a $2 billion annual acquisition budget that grows modestly overtime to keep pace with inflation. The Coast Guard needs a “predictable, reliable” acquisition budget “and within that we need 5 percent annual growth to our operations and maintenance (O&M) accounts,” Zukunft told reporters at a Defense Writers Group breakfast. Inflation will clip 2 to 3 percent from that, but “at 5 percent or so it puts you on a moderate but positive glide slope so you can execute, so you can build the force,” he said. 92 In an interview published on June 1, 2017, Zukunft said the following (emphasis added): We cannot be more relevant than we are now. But what we need is predictable funding. We have been in over 16 continuing resolutions since 2010. I need stable and repeatable funding. An acquisition budget with a floor of $2 billion. Our operating expenses as I said, they’ve been funded below the Budget Control Act floor for the past five years. I need 5 percent annualized growth over the next five years and beyond to start growing some of this capability back. But more importantly, we [need] more predictable, more reliable funding so we can execute what we need to do to carry out the business of the world’s best Coast Guard. 93 91 Transcript of hearing. The remarks were made in response to a question from Rep. John Culberson. Calvin Biesecker, “Zukunft Wants $2 Billion Baseline Acquisition Budget; Sustained Growth In O&M Funding,” Defense Daily, April 13, 2017: 1. 93 Jill Aitoro, “Interview: Adm. Paul Zukunft Demands Coast Guard Respect,” Defense News, June 1, 2017. 92 Congressional Research Service 57 Coast Guard Polar Security Cutter (Polar Icebreaker) Program Appendix E. Great Lakes Icebreakers This appendix provides a brief discussion of the Coast Guard’s Great Lakes icebreakers.94 The Coast Guard’s current Great Lakes icebreaker fleet consists of nine cutters:    one heavy icebreaker—Mackinaw (WLBB-30), a 240-foot ship displacing 3,500 tons (Figure E-1); six 140-foot Bay-class icebreaking tugs displacing 662 tons each; and two 225-foot Juniper-class seagoing buoy tenders displacing about 2,000 tons each that have a light icebreaking capability.95 Figure E-1. Great Lakes Icebreaker Mackinaw Source: U.S. Coast Guard, “USCGC Mackinaw,” accessed September 11, 2019, at https://www.atlanticarea.uscg.mil/Our-Organization/District-9/Ninth-District-Staff/Prevention-Division/Cutters/ MACKINAW/. Although Mackinaw is referred to as a heavy icebreaker, the word heavy in this instance is being used in the context of Great Lakes icebreaking—Mackinaw is much larger and has more icebreaking capability than the eight other ships listed above.96 Mackinaw would not, however, This appendix includes material originally present in the section entitled “Great Lakes Icebreakers” on pages 7-10 of CRS Testimony TE10030, Icebreaker Acquisition and the Need for a National Maritime Strategy, by Ronald O'Rourke. 95 Source: U.S. Coast Guard, “Ninth Coast Guard District Units,” accessed November 19, 2018, at https://www.atlanticarea.uscg.mil/Atlantic-Area/Units/District-9/Ninth-District-Units/. A total of 10 cutters are assigned to the Ninth District, which is responsible for the Great Lakes, the Saint Lawrence Seaway, and parts of the surrounding states. The tenth cutter assigned to the Ninth District is a 100-foot inland buoy tender whose primary missions do not include icebreaking. 96 At continuous speeds of 3 knots, Mackinaw can break ice up to 32 inches thick, the 140-foot icebreaking tugs can break ice up to 22 inches thick, and the 225-foot seagoing buoy tenders can break ice up to 14 inches thick. 94 Congressional Research Service 58 Coast Guard Polar Security Cutter (Polar Icebreaker) Program qualify as a heavy polar icebreaker, as it is much smaller and has much less icebreaking capability than a heavy polar icebreaker.97 Coast Guard officials have stated that they do not view the procurement of additional Great Lakes icebreakers as an urgent near-term acquisition need. In support of this assessment, they cite the capabilities of the current Great Lakes icebreaking fleet, the relatively young age of Mackinaw (which entered service in 2006), service life extension work being done on the ice-breaking tugs that is designed to add 15 years to their service lives,98 and Canada’s own Great Lakes icebreaking capabilities. A 2016 Coast Guard report to Congress on the Great Lakes icebreaking mission stated the following: The current mix of heavy and medium [Great Lakes] icebreakers is capable of managing priorities and requests for icebreaking in Tier 1 and 2 waterways. When a severe ice season stresses Coast Guard asset capabilities, the existing agreement and partnership with Canada fills the capability gap and brings in extra heavy-icebreaking resources to manage the ice.... [T]he 2014 and 2015 ice seasons were a 20-year anomaly, consuming almost twice as many cutter resource hours as in any other year since 2005. The Coast Guard cannot reliably predict the economic impact of maintaining a single heavy Great Lakes icebreaker. Additionally, given the extreme conditions when ice coverage exceeds 90 percent, it is not clear that shipping delays would be significantly mitigated by an increase in icebreaking capability. Delays can be associated with several factors such as slow transit speeds, availability of pilots, and simultaneous and competing demand signals for icebreaking services across the Great Lakes. 99 Supporters of procuring an additional Great Lakes icebreaker argue the following:    The 2014 and 2015 ice seasons were a 20-year anomaly, but the Coast Guard should have a capability for supporting maritime commerce in above-average ice seasons. About 24% of recent years (11 out of 46 years) featured 75% or higher ice coverage. The Coast Guard’s Great Lakes icebreaking capability is less sufficient for meeting winter needs than the Coast Guard agues because its cutters are often not available for duty, the Coast Guard reports restrictions for only some of the area’s commercial waterways and not others, and the Coast Guard defines a waterway as restricted or closed when two commercial ships get stuck in the ice in certain waterways, overlooking instances where commercial ship operators decline to operate their ships on those waters because they assess a high risk of the ships getting stuck. While the Canadian Coast Guard usually assigns one or more additional icebreakers to the St. Lawrence River and the Great Lakes in severe ice seasons, As discussed earlier in this report, the Coast Guard’s two heavy polar icebreakers—the operational Polar Star and the nonoperational Polar Sea, are 399 feet long and displace about 13,200 tons each. Polar Star can break ice up to six feet (72 inches) thick at a continuous speed of 3 knots. The Coast Guard states that Mackinaw is equivalent to the Canadian Coast Guard ship Samuel Risley, a Great Lakes-homeported icebreaker and buoy tender that Canada classifies as a light icebreaker in a comparison conducted across its entire icebreaking fleet, including its Arctic icebreakers. (U.S. Coast Guard, Great Lakes Icebreaking Mission Analysis, Fiscal Year 2016 Report to Congress, August 30, 2016, p. 5.) 98 For more on this service life extension work, see U.S. Coast Guard, “In-Service Vessel Sustainment Program,” accessed November 19, 2018, at https://www.dcms.uscg.mil/Our-Organization/Assistant-Commandant-forAcquisitions-CG-9/Programs/Surface-Programs/In-Service-Vessel-Sustainment-Program/. 99 U.S. Coast Guard, Great Lakes Icebreaking Mission Analysis, Fiscal Year 2016 Report to Congress, August 30, 2016, p. 11. The report was required by S.Rept. 114-68 of June 18, 2015, the Senate Appropriations Committee’s report on S. 1619, the Department of Homeland Security Appropriations Bill, 2016 (see page 75). 97 Congressional Research Service 59 Coast Guard Polar Security Cutter (Polar Icebreaker) Program  Canadian Coast Guard ships operating there provide icebreaking assistance to U.S. commercial ships only under certain circumstances, resulting in only a small amount of icebreaking assistance being provided to U.S. commercial ships. The service life extension work being done on the ice-breaking tugs does not include the replacement of their main propulsion engines. Breakdowns of these engines, which are becoming increasingly common, often result in these icebreaking tugs becoming unavailable for icebreaking in winter. Some Members of Congress in recent years have expressed interest in the possibility of bolstering the Coast Guard’s Great Lakes icebreaking fleet by procuring a second icebreaker with capabilities generally similar to those of Mackinaw. Interest in this option was reinforced by the winters of 2013-2014 and 2014-2015, which featured particularly high levels of ice coverage on the Great Lakes.100 The committee report language requiring the above-quoted Coast Guard report to Congress is one example of this interest.101 Another example is Section 820 of the Frank LoBiondo Coast Guard Authorization Act of 2018 (S. 140/P.L. 115-282 of December 4, 2018), which states the following: SEC. 820. Great Lakes icebreaker acquisition. (a) Icebreaking on the Great Lakes.—For fiscal years 2018 and 2019, the Commandant of the Coast Guard may use funds made available pursuant to section 4902 of title 14, United States Code, as amended by this Act, for the construction of an icebreaker that is at least as capable as the Coast Guard Cutter Mackinaw to enhance icebreaking capacity on the Great Lakes. (b) Acquisition plan.—Not later than 45 days after the date of enactment of this Act, the Commandant shall submit a plan to the Committee on Commerce, Science, and Transportation of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives for acquiring an icebreaker described in subsections (a) and (b). Such plan shall include— 100 Although interest in procuring a second heavy Great Lakes icebreaker was reinforced by high levels of ice coverage in the winters of 2013-2014 and 2014-2015, interest in Congress in procuring such a ship dates back further than 2013. See, for example, H.R. 1747 of the 111th Congress, the Great Lakes Icebreaker Replacement Act, which was introduced on March 26, 2009, reported by the Committee on Transportation and Infrastructure on April 21, 2009 (H.Rept. 11181), and agreed to by the House by voice vote on April 27, 2009. A similar bill, S. 1024, was introduced in the Senate on May 12, 2009. 101 S.Rept. 114-68 stated the following: GREAT LAKES ICEBREAKING CAPACITY The Coast Guard is required by law to maintain a heavy icebreaking capability on the Great Lakes to assist in keeping channels and harbors open to navigation in response to the reasonable demands of commerce to meet the winter shipping needs of industry. The Committee is concerned that the Coast Guard does not possess adequate capacity to meet its statutorily required icebreaking mission on the Great Lakes, with negative consequences to the regional and national economy as well as to the safety of local communities. While the Committee fully supports the Coast Guard’s Service Life Extension Project for its nine-vessel 140-foot icebreaking tugs as part of the In-Service Vessel Sustainment Program, it notes that additional assets may be necessary to successfully operate in the heavy ice conditions often experienced by the Great Lakes. The Committee directs the Coast Guard to undertake an updated mission analysis study to determine the assets necessary to effectively carry out its icebreaking requirements on the Great Lakes, including consideration of a second heavy icebreaker for the Great Lakes, consistent with the capabilities of the Mackinaw. The updated mission analysis should factor in recent historically high levels of ice coverage and the economic costs of reduced Great Lakes shipping associated with maintaining only one heavy icebreaker. The updated mission analysis shall be submitted to the Committee not later than 180 days after the date of enactment of this act. (Page 75) Congressional Research Service 60 Coast Guard Polar Security Cutter (Polar Icebreaker) Program (1) the details and schedule of the acquisition activities to be completed; and (2) a description of how the funding for Coast Guard acquisition, construction, and improvements that was appropriated under the Consolidated Appropriations Act, 2017 (Public Law 115–31) will be allocated to support the acquisition activities referred to in paragraph (1).102 An examination of procurement costs for Mackinaw, the National Science Foundation’s icecapable research ship Sikuliaq, new oceanographic research ships being procured for NOAA, and OPCs suggests that a new Mackinaw-sized heavy Great Lakes icebreaker built in a U.S. shipyard might have a design and construction cost between $175 million and $300 million, depending on its exact capabilities and the acquisition strategy employed.103 The design portion of the ship’s cost might be reduced if Mackinaw’s design or the design of some other existing icebreaker were to be used as the parent design. Depending on the capabilities and other work load of the shipyard 102 In addition, Section 819 of S. 140/P.L. 115-282 states the following: SEC. 819. Acquisition plan for inland waterway and river tenders and bay-class icebreakers. (a) Acquisition plan.—Not later than 270 days after the date of the enactment of this Act, the Commandant of the Coast Guard shall submit to the Committee on Commerce, Science, and Transportation of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives a plan to replace or extend the life of the Coast Guard fleet of inland waterway and river tenders, and the Bay-class icebreakers. (b) Contents.—The plan under subsection (a) shall include— (1) an analysis of the work required to extend the life of vessels described in subsection (a); (2) recommendations for which, if any, such vessels it is cost effective to undertake a ship-life extension or enhanced maintenance program; (3) an analysis of the aids to navigation program to determine if advances in navigation technology may reduce the needs for physical aids to navigation; (4) recommendations for changes to physical aids to navigation and the distribution of such aids that reduce the need for the acquisition of vessels to replace the vessels described in subsection (a); (5) a schedule for the acquisition of vessels to replace the vessels described in subsection (a), including the date on which the first vessel will be delivered; (6) the date such acquisition will be complete; (7) a description of the order and location of replacement vessels; (8) an estimate of the cost per vessel and of the total cost of the acquisition program of record; and (9) an analysis of whether existing vessels can be used. 103 Source: CRS analysis of cost per weight for Mackinaw (adjusted for inflation), Sikuliaq, new NOAA oceanographic research ships now being procured, and OPCs. Some press reports in 2015 and 2016 cited a cost of about $200 million for a new heavy Great Lakes icebreaker. (See, for example, Todd Spangler, “A New Icebreaker for the Great Lakes? It’s Far from Certain,” Detroit Free Press, August 7, 2015; “Frozen Commerce: Great Lakes Businesses Need a New Icebreaker,” Pittsburgh Post-Gazette, August 17, 2015; Todd Spangler, “Call for Arctic Icebreakers Could Hurt Great Lakes,” Detroit Free Press, September 1, 2015; Bob Gross, “Congress Authorizes New Icebreaker for Great Lakes,” Times Herald (Port Huron, MI), February 3, 2016; “Task Force Calls Anew for More Great Lakes Icebreakers, Second Poe-Sized Lock,” Professional Mariner, February 17, 2016 [the article states that it presents the text of a news release from the Great Lakes Maritime Task Force].) An opinion column in 2016 cited a figure of $240 million. (John Hageman, “Is Winter Great Lakes Shipping Necessary?” Sandusky Register, February 18, 2016.) The Great Lakes Maritime Task Force, an organization that states that it “was founded in 1992 in Toledo, Ohio, to promote waterborne commerce and related industries on the Great Lakes” (see Great Lakes Maritime Task Force, “About Us,” accessed November 26, 2018, at http://www.glmtf.org/about), states in its annual report for 2017 that a second heavy Great Lakes icebreaker “is projected to cost $240 million.” (2017 Annual Report of Great Lakes Maritime Task Force, PDF page 3 of 6, accessed November 26, 2018, at http://www.glmtf.org/wp-content/uploads/ 2018/05/2017-Annual-Report.pdf.) The same figure is cited in the organization’s annual report for 2016. The organization’s annual report for 2015 cited a figure of approximately $200 million. Congressional Research Service 61 Coast Guard Polar Security Cutter (Polar Icebreaker) Program selected to build the ship, the construction time for a new heavy Great Lakes icebreaker might be less than that of a new heavy polar icebreaker. Author Information Ronald O'Rourke Specialist in Naval Affairs Disclaimer This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff to congressional committees and Members of Congress. It operates solely at the behest of and under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other than public understanding of information that has been provided by CRS to Members of Congress in connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or material from a third party, you may need to obtain the permission of the copyright holder if you wish to copy or otherwise use copyrighted material. Congressional Research Service RL34391 · VERSION 196 · UPDATED 62