ATLANTIC YARDS aka Pacific Park Brooklyn Construction Update Weeks of August 10 and August 17, 2020 During this reporting period: LIRR Yard Activities – West Block 1120 & East Block 1121 ● Site demobilization, including material and equipment removal will continue. B15 ● The concrete superstructure program is in progress and should be completed by the end of August. ● Mechanical trades are installing base building systems and equipment throughout the building ● Interior construction of the residential units has commenced ● The exterior brick facade of the building and window installation has commenced ● Protocols and facilities have been put in place to ensure an orderly, safe workplace in accordance with current government requirements and permits, which include weekday start times at 7 AM and lasting until 7 PM and Saturday permits starting at 8 AM until 5 PM. B4 ● The concrete superstructure program is in progress and should be completed by the end of December. ● Underground utilities work is ongoing on Atlantic Avenue along with hoist erection. ● Mechanical trades are installing base building systems and equipment throughout the building ● Interior construction of the residential units has commenced ● The exterior facade has begun with masonry and window trades working in tandem. ● Protocols and facilities have been put in place to ensure an orderly, safe workplace in accordance with current government requirements and permits, which include weekday start times at 7 AM and lasting until 7 PM and Saturday permits starting at 8 AM until 5 PM. B12 & B13 ● Excavation and Foundation work, including drilling of soldier piles, may commence during the week of August 10. Subcontractor may deliver oversized equipment (i.e. drill rigs, excavators, etc.) during early morning hours. 1 How to Reach Pacific Park Brooklyn Community Liaison Office (CLO) The Community Liaison Office located at 550 Vanderbilt Avenue is temporarily closed. The CLO can be reached by phone at 866-923-5315 and by email at communityliaison@pacificparkbrooklyn.com Noise Receptor Control Program You may be eligible to receive and have installed double paned or storm windows and an in-window air conditioning unit for certain residential units where such air conditioning and/or double paned windows/storm windows do not exist today. The cost of any windows and any air conditioning units, and the cost of their installation, would be borne by the Developer. The locations that may be eligible at this time are the residential sites in proximity to site construction and identified in the 2006 Final Environmental Impact Statement (FEIS) or the 2014 Final Supplemental Environmental Impact Statement (FSEIS) as having the potential to experience significant adverse noise impacts during the construction of the Pacific Park Brooklyn project. In order to schedule an on-site inspection by the Developer to determine which windows may be eligible for replacement and/or AC units provided please contact the Community Liaison Office at 866-923-5315 and by email at communityliaison@pacificparkbrooklyn.com 2